Commissioning a New Cold Room with a Remote Condensing Unit

BTEB Refrigeration & AC Exam · Put your knowledge to work in context.

All case studies

Commissioning a New Cold Room with a Remote Condensing Unit

You are commissioning a new 4 m x 3 m x 2.5 m chiller cold room (design 2 C, product dairy) with a remote air-cooled condensing unit and a unit cooler. The installing contractor has completed pipework, pressure-tested at 25 bar with nitrogen, and evacuated to 500 microns, holding for 20 minutes. The system is R-449A, charged by weight to the calculated value. On first start the room pulls from 18 C to 5 C in 40 minutes, then stalls. Suction pressure 2.1 bar gauge, discharge 16 bar gauge, superheat at the evaporator 14 K, subcooling 2 K. The evaporator fan is running, coil is partly frosted at the bottom third, and there is a gurgling sound at the TXV. Ambient at the condenser is 30 C.

1. Interpret the pressure, superheat and subcooling readings and identify the most likely fault, with your reasoning.

Read the worked answer

Reading interpretation for R-449A:

  • Suction at 2.1 bar gauge corresponds to an evaporator saturation temperature well below the 2 C room design, so the coil is running a large TD and is being starved rather than flooded.
  • Superheat of 14 K at the evaporator outlet is well above the normal 5-8 K band, which is the strongest single indicator of refrigerant starvation at the coil.
  • Subcooling of 2 K is low, consistent with insufficient liquid column or a restriction upstream of the TXV, not with overcharge.
  • Discharge at 16 bar gauge at 30 C ambient is high for this ambient, suggesting the condenser is not rejecting heat efficiently or the head pressure control is misbehaving, but it is secondary to the starvation.

Most likely fault: a restriction or insufficient liquid supply to the TXV, evidenced by high superheat, low subcooling and gurgling at the valve. Candidate causes: a partially closed liquid line service valve, a blocked filter drier, a kinked or undersized liquid line, or a TXV that is stuck or incorrectly set. The partial frosting only at the bottom third of the coil supports uneven, starved feed.

Less likely: undercharge, which would also give high superheat but usually shows bubbles in the sight glass and a more uniform starved pattern; liquid line restriction is more consistent with the gurgling and low subcooling.

Next step: check the liquid line valve positions and the filter drier temperature drop across it, then observe TXV response to superheat adjustment before changing charge.

2. The contractor proposes adding refrigerant to bring suction pressure up. Assess this and describe the correct diagnostic sequence.

Read the worked answer

Adding refrigerant is unjustified and would be a mistake. Low suction pressure with high superheat and low subcooling points to a supply restriction, not to a shortage of charge. Adding refrigerant would raise subcooling and liquid line pressure but would not fix the restriction; it would push liquid toward the compressor once the restriction clears and could cause slugging.

Correct diagnostic sequence:

  1. Verify valve positions. Confirm the liquid line and suction service valves are fully back-seated. A partly closed valve is the most common and most easily missed cause.
  2. Check the filter drier for a temperature drop across it; a noticeable drop indicates a blockage requiring replacement.
  3. Inspect the liquid line for kinks, undersized pipe, or long vertical lifts without a proper trap.
  4. Observe TXV behavior. Gurgling plus high superheat suggests the valve is hunting, stuck, or has a failed power element. Check the sensing bulb clamping and insulation.
  5. Confirm charge only after the above, by weighing in to nameplate or by subcooling method once the restriction is cleared.
  6. Re-check superheat and subcooling after each intervention and log the values.

Only if all supply-side checks pass and superheat remains high with a clear sight glass should charge be revisited.

3. Define the commissioning acceptance tests you would require before handover of this cold room.

Read the worked answer

Acceptance tests before handover:

  • Pressure and leak test: nitrogen test at the specified pressure held for the required duration with no drop, documented with start and end readings.
  • Evacuation: 500 microns or below, held for at least 20-30 minutes with the pump isolated, decay not exceeding the agreed limit.
  • Charge: weighed in to the calculated value, recorded on the commissioning sheet; superheat 5-8 K and subcooling 4-8 K at steady state.
  • Pull-down: room reaches 2 C from ambient within an agreed time; no stall; evaporator coil evenly frosted with no ice build-up at the bottom.
  • Defrost: initiates and terminates correctly, with fan delay and drip time verified; no ice left on the coil after a full cycle.
  • Controls and safeties: thermostat setpoint and differential correct, high-pressure and low-pressure cutouts trip and reset, door heater and anti-sweat controls function, alarm and remote monitoring tested.
  • Electrical: running current within nameplate RLA, phase balance within 10 percent, insulation resistance acceptable.
  • Documentation: all readings logged with ambient and room temperatures, signed off by contractor and client.