Bidding and Tendering

  • Open tendering invites any qualified bidder publicly; selective tendering invites only pre-qualified firms; negotiated tendering awards without competition, usually for specialist or urgent work.

  • A tender is an offer, not an acceptance; a binding contract forms only when the client issues an unconditional acceptance, and a conditional acceptance is a counter-offer.

  • A bid bond (typically 5-10% of tender price) protects the client if the successful bidder refuses to sign; a performance bond (typically 10%) covers post-award default.

  • Prequalification screens bidders on financial standing, technical capability, and safety record before tender documents are issued.

  • Addenda issued during the tender period become part of the tender documents and must be acknowledged by bidders; late addenda may justify an extension to the closing date.

  • Two-envelope tendering separates technical proposals from priced offers so technical evaluation is not influenced by price.

  • A tender clarification does not change scope or price; a material change after closing may require re-tendering to preserve fairness.

  • Best value evaluation scores price and non-price criteria (quality, programme, safety) using stated weightings published in the tender documents.

Quick reference

Contract Administration

  • Letters of intent may create binding obligations if they commit payment for defined work; they are not a substitute for a signed contract.

  • A variation is a change to scope, quality, quantity, or timing authorised in writing by the contract administrator; oral instructions should be confirmed in writing.

  • An extension of time adjusts the completion date for excusable delay; it does not automatically entitle the contractor to loss and expense.

  • Liquidated damages are a pre-agreed genuine estimate of loss per day of culpable delay; they are unenforceable if they are a penalty.

  • Interim payments are certified at stated intervals; the final certificate follows the defects liability period and releases retention.

  • Retention is typically 5% deducted from payments, often reduced to 2.5% on practical completion, with the balance released after the defects period.

  • Practical completion marks the date the works are fit for purpose and handed over; it starts the defects liability period and triggers release of half the retention.

  • A site instruction records a directive on site; if it constitutes a variation it must be valued and certified through the change procedure.

  • Substantial completion vs final completion: the former transfers risk and possession, the latter closes all accounts and releases final retention.

Quick reference

Estimating and Cost Planning

  • Unit rate build-up: rate = labour + material + plant + subcontract cost + overheads + profit, divided by the measured quantity.

  • Labour cost per unit = (daily wage x crew size) / daily output, or wage divided by output per hour.

  • All-in labour rate includes base wage plus on-costs such as insurance, holiday pay, and supervision; ignore only if the client requires bare rates.

  • Preliminaries are site-wide costs (site staff, temporary works, insurance, welfare) that are not attributable to a measured item and are often priced as a lump sum.

  • Contingency is an allowance for identified but unquantified risk; it is not a substitute for accurate measurement.

  • Cost planning stages: order-of-magnitude, elemental, and detailed; accuracy improves as design information matures.

  • Escalation adjusts estimates for inflation between the estimating date and the construction period using a stated index.

  • Cash flow forecasting spreads cost over the programme; it differs from the priced bill, which is not time-distributed.

  • Pricing errors: an arithmetically unbalanced bid loads early items for cash flow; it is legitimate only if not misleading.

Quick reference

Project Planning and Scheduling

  • Critical path is the longest duration path through the network; it determines the minimum project duration and has zero total float.

  • Total float = latest finish minus earliest finish for an activity; free float is the delay possible without affecting the next activity's early start.

  • A Gantt chart shows activities against time but does not by itself show logical dependencies; network diagrams show logic.

  • A milestone has zero duration and marks a key event or decision point.

  • Crashing shortens duration by adding resources to critical activities; fast-tracking overlaps activities that would normally be sequential.

  • Resource levelling smooths peaks within float; resource smoothing may extend duration if float is insufficient.

  • Lag is a mandatory delay between finish and start of linked activities; lead is a negative lag allowing overlap.

  • Progress S-curve plots cumulative cost or work against time and is used to compare planned versus actual performance.

  • Programme logic must reflect construction sequence; an activity with no predecessor is a dangling activity and an error.

Quick reference

Construction Technology and Methods

  • Concrete strength is specified by characteristic cube strength at 28 days; curing maintains moisture and temperature for hydration.

  • Formwork must resist fresh concrete pressure, which increases with pour height and rate; strike times depend on strength gain, not fixed hours.

  • Reinforcement cover protects steel from corrosion and provides fire resistance; cover is set by spacers, not by bar diameter alone.

  • Excavation support: battered slopes suit stable ground; shoring or sheet piles are needed where space or ground conditions prevent battering.

  • Dewatering lowers the water table to keep excavations dry; it must consider settlement risk to adjacent structures.

  • Brickwork bond patterns (stretcher, English, Flemish) distribute loads and tie the wall; mortar joint thickness affects compressive strength.

  • Structural steel connections are bolted (friction or bearing) or welded; bolt torque and weld inspection are quality-critical.

  • Foundations: strip footings suit continuous load-bearing walls; pad footings suit isolated columns; rafts spread load over weak ground.

  • Roof pitch and covering selection are governed by weathertightness; minimum pitch depends on the covering material and lap.

Quick reference

Health, Safety and Environment

  • Hierarchy of control: eliminate, substitute, engineering controls, administrative controls, then PPE as last resort.

  • Risk = likelihood x severity; residual risk is what remains after controls are applied and must be recorded.

  • A method statement describes the safe sequence of work; a risk assessment identifies hazards and controls; a permit-to-work authorises high-risk tasks.

  • Working at height: fall protection is required above 2 m in many jurisdictions; guardrails, nets, and harnesses follow the hierarchy.

  • Excavations deeper than 1.2-1.5 m generally require shoring or battering, and must be inspected by a competent person before entry.

  • Silica dust, asbestos, and noise are common occupational health hazards; controls include wet methods, enclosure, and hearing protection.

  • Environmental controls: silt traps and settlement ponds prevent sediment entering watercourses; dust suppression uses water sprays.

  • Waste hierarchy: prevent, reuse, recycle, recover, dispose; disposal is the least preferred option.

  • Incident reporting: near misses are recorded to prevent recurrence; serious incidents trigger statutory notification and investigation.

Quick reference

Professional Ethics and Conduct

  • Conflict of interest must be disclosed in writing as soon as it is known; failure to disclose is a breach of professional duty.

  • Confidentiality: client information is not disclosed without consent except where law or safety requires it.

  • Bribery and facilitation payments are prohibited; gifts and hospitality must be declared and recorded per policy.

  • Competence: professionals must work only within their competence and seek specialist advice where needed.

  • Integrity in tendering: collusion (bid rigging, cover pricing) is unlawful and a serious professional misconduct.

  • Accuracy in certification: certifying work not executed or overstating progress is fraudulent and grounds for dismissal and prosecution.

  • Whistleblowing: concerns about unsafe or unlawful practice should be raised through internal channels first, then regulators if unresolved.

  • Fair dealing: subcontractors and suppliers must be treated consistently with the terms offered to the main contractor; payment terms should be honoured.