BQA Grade 9 · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Open tendering
A procurement method where the invitation to tender is advertised publicly and any interested supplier meeting stated criteria may submit a bid, maximising competition but increasing evaluation workload.
Bid bond purpose
A surety protecting the client against a successful bidder who refuses to sign the contract or provide performance security, usually valued at five to ten percent of the tender price.
Tender vs offer
A tender submitted by a bidder is legally an offer; a binding contract arises only when the client accepts it unconditionally, and a conditional acceptance is a counter-offer.
Two-envelope tendering
A system where technical and priced submissions are submitted separately so the technical evaluation is completed before prices are opened, reducing price bias in assessment.
Prequalification
A pre-tender screening stage assessing bidders on financial capacity, technical experience, and safety record to produce a shortlist of firms invited to tender.
Variation instruction
A written direction from the contract administrator changing scope, quality, quantity, or timing of the works, which is then valued and certified through the change procedure.
Extension of time
An adjustment to the contractual completion date granted for excusable delay such as weather or client-caused events, relieving the contractor of liquidated damages for that period.
Liquidated damages
A pre-agreed sum payable per day of culpable delay representing a genuine estimate of the client's loss; it is unenforceable if it operates as a penalty.
Retention
A percentage withheld from interim payments as security for defects, commonly five percent reducing to two and a half percent at practical completion, with the balance released later.
Practical completion
The stage when the works are substantially complete and fit for their intended purpose, triggering handover, the defects liability period, and release of part retention.
Letter of intent
A pre-contract document authorising limited work or payment; it may create binding obligations if it commits payment, and does not replace a formal contract.
Unit rate build-up
A priced rate per measured item formed by summing labour, material, plant, subcontract, overhead, and profit components, then dividing by the measured quantity.
Preliminaries
Site-wide costs not attributable to measured work items, such as site management, temporary works, welfare facilities, and insurance, often priced as a lump sum.
Contingency allowance
A sum included in an estimate to cover identified but unquantified risk; it is not a substitute for accurate measurement of known scope.
All-in labour rate
A wage rate that includes base pay plus on-costs such as insurance, holiday pay, and supervision, giving the true cost of an hour of labour.
Escalation
An adjustment applied to an estimate to account for inflation between the estimating date and the construction period, using a stated cost index.
Critical path
The longest duration path through the activity network, which determines the minimum project duration and has zero total float on its activities.
Total float
The amount an activity can be delayed without delaying project completion, calculated as latest finish minus earliest finish for that activity.
Free float
The amount an activity can be delayed without affecting the early start of any successor activity, always less than or equal to total float.
Milestone
A zero-duration marker in a programme representing a key event, decision, or contractual date rather than a work activity with resources.
Crashing vs fast-tracking
Crashing shortens duration by adding resources to critical activities; fast-tracking overlaps activities normally done in sequence, increasing risk of rework.
Dangling activity
A network error where an activity has no predecessor or successor, breaking the logic and making the schedule unreliable for float and critical path calculation.
Concrete curing
Maintaining adequate moisture and temperature after placing so cement hydration continues, developing the specified strength and durability without premature drying or cracking.
Reinforcement cover
The depth of concrete between the steel bar surface and the outer face, protecting steel from corrosion and providing fire resistance to the reinforcement.
Dewatering
Lowering the groundwater level around an excavation by pumping or wellpoints to keep the work dry, with assessment of settlement risk to adjacent structures.
Strip vs pad footing
Strip footings support continuous load-bearing walls along their length; pad footings support isolated columns at discrete points, spreading load into the ground.
Hierarchy of control
A ranked order of risk controls: eliminate, substitute, engineering controls, administrative controls, and personal protective equipment as the last resort.
Permit to work
A formal written authorisation for high-risk tasks such as hot work or confined space entry, confirming hazards are identified and controls are in place before work starts.
Excavation shoring
Temporary support such as timbering, sheet piles, or trench boxes used to prevent collapse of excavation sides where ground conditions or space prevent safe battering.
Waste hierarchy
A ranked preference for managing waste: prevent, reuse, recycle, recover energy, and dispose as the least preferred option, applied to construction materials and spoil.
Conflict of interest
A situation where a professional's personal or financial interest could improperly influence their judgement, requiring written disclosure as soon as it becomes known.
Bid rigging
Collusive behaviour where bidders secretly agree on prices or outcomes to distort competition; it is unlawful and constitutes serious professional misconduct.