- Work Breakdown Structure
- A hierarchical, deliverable-oriented decomposition of total project scope. Its lowest elements are work packages that can be estimated, scheduled, and assigned to a single accountable owner.
- Work Package
- The smallest WBS element, defined so its cost and duration can be reliably estimated and one person can be held accountable for its completion and quality.
- Critical Path
- The longest-duration sequence of dependent activities through the network. It determines the shortest possible project duration and normally carries zero total float.
- Total Float
- The amount of time an activity can be delayed without delaying the project finish date. Calculated as late start minus early start, or late finish minus early finish.
- Forward Pass
- A network calculation that moves from project start to finish, assigning each activity its earliest start and earliest finish based on predecessor durations and dependencies.
- Backward Pass
- A network calculation that moves from project finish back to start, assigning each activity its latest finish and latest start without delaying the project completion date.
- PERT Expected Duration
- A weighted three-point estimate equal to (optimistic + 4 times most likely + pessimistic) divided by six, used to model duration uncertainty on activities.
- Schedule Crashing
- A compression technique that shortens critical-path durations by adding resources or overtime. It usually increases cost and is applied to the cheapest critical activities first.
- Fast Tracking
- A compression technique that overlaps activities normally performed in sequence. It can shorten duration without added cost but increases risk of rework and coordination problems.
- Cost Variance
- Earned value minus actual cost. A positive value means the project is under budget for completed work; a negative value means it is over budget.
- Schedule Variance
- Earned value minus planned value. A positive value indicates more work was completed than planned for the reporting date; a negative value indicates slippage.
- Cost Performance Index
- Earned value divided by actual cost. A value below 1.0 means each unit of currency spent is buying less completed work than planned.
- Schedule Performance Index
- Earned value divided by planned value. A value below 1.0 means the project has completed less work than scheduled at the measurement date.
- Estimate At Completion
- The projected total cost of the project. When current cost efficiency is expected to continue, it equals budget at completion divided by the cost performance index.
- Budget At Completion
- The total authorized budget for the project scope as recorded in the approved cost baseline. It is the reference value used to compute variances and forecast final cost.
- To-Complete Performance Index
- The cost efficiency required on remaining work to meet a budget target. Calculated as (BAC minus EV) divided by (BAC minus AC).
- Cost of Quality
- The total of prevention, appraisal, internal failure, and external failure costs. Rework counts as internal failure; warranty claims and liability count as external failure.
- Change Control Board
- The authority that reviews, approves, defers, or rejects change requests affecting baselines. Approved changes update the baseline and the change log.
- Change Log
- A record of every change request, its status, decision, approver, and date. It supports traceability between approved changes and updated project baselines.
- Scope Baseline
- The approved combination of the project scope statement, the work breakdown structure, and the WBS dictionary, used to detect and control scope creep.
- Gold Plating
- Adding features or work not requested in the approved scope. It consumes budget and time without customer authorization and is treated as unapproved scope.
- RACI Matrix
- A responsibility chart assigning Responsible, Accountable, Consulted, and Informed roles per task. Each task should have exactly one Accountable party to avoid ambiguity.
- Risk Register
- A living document listing identified risks with probability, impact, exposure score, owner, planned response, and current status for each entry.
- Risk Transfer
- A response that shifts financial consequence of a threat to a third party, typically through insurance, performance bonds, or warranty clauses, without eliminating the risk.
- Risk Mitigation
- A response that reduces either the probability or the impact of a threat before it occurs, lowering overall exposure rather than waiting to react afterward.
- Contingency Reserve
- Budget held for identified risks with known responses. It sits within the cost baseline and is released by the project manager under defined authority thresholds.
- Management Reserve
- Budget held for unidentified scope or unknown risks. It sits above the cost baseline and normally requires sponsor or senior management approval to release.
- Lessons Learned Register
- A running record of knowledge gained during the project, captured throughout rather than only at closure, so later phases and future projects can reuse it.
- Stakeholder Register
- A record of identified stakeholders with their roles, interests, influence, expectations, and communication needs, used to plan engagement and manage expectations.
- Communications Management Plan
- A document defining who receives which information, in what format, at what frequency, and through which channel, plus escalation paths for issues.
- Quality Assurance vs Control
- Assurance is process-focused and preventive, auditing how work is performed. Control is product-focused and detective, inspecting deliverables against requirements and recording defects.
- Procurement Statement of Work
- A clear description of the products, services, or results to be delivered by a seller, including acceptance criteria, so bids and contracts can be evaluated objectively.