BICSI RTPM key terms
BICSI RTPM · Get comfortable with the vocabulary.
- Project Charter
- Related: Project Sponsor, Scope Statement
A document authorized by the project sponsor that formally starts the project and grants the project manager authority to apply organizational resources to project activities.
- Project Sponsor
- Related: Project Charter, Stakeholder Register
The person or group providing financial and political backing for the project, approving major changes, and removing obstacles beyond the project manager's control.
- Scope Statement
- Related: Work Breakdown Structure, Scope Creep
A written description of the project's deliverables, boundaries, and acceptance criteria that clarifies exactly what work is and is not included.
- Work Breakdown Structure (WBS)
- Related: Work Package, Scope Statement
A hierarchical decomposition of the total project scope into smaller, manageable work packages that can be estimated, scheduled, and assigned.
- Work Package
- Related: Work Breakdown Structure (WBS), Activity Duration Estimate
The lowest level of a work breakdown structure, small enough to estimate cost and duration and to assign to a single accountable owner.
- Scope Creep
- Related: Change Control Board, Scope Statement
Uncontrolled, gradual expansion of project scope without corresponding adjustments to time, cost, or resources, usually caused by unmanaged change requests.
- Change Control Board (CCB)
- Related: Change Request, Scope Creep
A formal group of stakeholders who review, evaluate, approve, or reject proposed changes to the project baseline and communicate decisions to affected parties.
- Change Request
- Related: Change Control Board (CCB), Baseline
A formal document proposing modification to a project component such as scope, schedule, cost, or quality, which must be logged and dispositioned.
- Baseline
- Related: Change Request, Earned Value Management
An approved, frozen version of scope, schedule, or cost used as a reference point for measuring and reporting project performance against plan.
- Stakeholder Register
- Related: Communications Management Plan, Project Sponsor
A living document identifying each stakeholder, their role, interests, influence, and communication needs, used to plan engagement throughout the project life cycle.
- Communications Management Plan
- Related: Stakeholder Register, Issue Log
A plan defining who receives what information, in what format, how often, and through which channels, plus escalation paths for project issues.
- Issue Log
- Related: Risk Register, Communications Management Plan
A record of open problems, concerns, and disputes affecting the project, including owner, status, and resolution target dates for tracking and escalation.
- Risk Register
- Related: Risk Response, Issue Log
A tool listing identified risks with their probability, impact, score, owner, and planned response, reviewed and updated throughout the project.
- Risk Response
- Related: Risk Register, Contingency Reserve
A planned action to address an identified risk, such as avoiding, mitigating, transferring, accepting, or exploiting it, with an assigned owner.
- Contingency Reserve
- Related: Risk Response, Management Reserve
Time or money set aside in the approved baseline to cover known risks that have been identified and analyzed, controlled by the project manager.
- Management Reserve
- Related: Contingency Reserve, Cost Baseline
Budget held outside the cost baseline for unanticipated work within project scope, released only through formal approval, typically by the sponsor.
- Cost Baseline
- Related: Management Reserve, Earned Value Management
The approved, time-phased project budget excluding management reserve, against which actual expenditures and cost performance are measured and reported.
- Earned Value Management (EVM)
- Related: Cost Baseline, Critical Path Method
A technique comparing planned value, earned value, and actual cost to measure schedule and cost performance and forecast final project outcomes.
- Critical Path Method (CPM)
- Related: Total Float, Gantt Chart
A scheduling technique identifying the longest dependent sequence of activities, which determines the shortest possible project duration and has zero total float.
- Total Float
- Related: Critical Path Method (CPM), Schedule Compression
The amount of time an activity can be delayed without delaying the project completion date, calculated as late start minus early start.
- Schedule Compression
- Related: Total Float, Milestone
A technique to shorten project duration without reducing scope, either by overlapping activities (fast tracking) or adding resources (crashing).
- Gantt Chart
- Related: Critical Path Method (CPM), Milestone
A horizontal bar chart displaying scheduled activities against a calendar timeline, showing durations, dependencies, and progress at a glance.
- Milestone
- Related: Gantt Chart, Phase Gate
A significant point or event in the project with zero duration, used to mark completion of a phase, deliverable, or contractual obligation.
- Phase Gate
- Related: Milestone, Lessons Learned
A formal review checkpoint at the end of a project phase where stakeholders decide whether to proceed, pause, or terminate the work.
- Lessons Learned
- Related: Phase Gate, Closeout
Documented knowledge from project experience, capturing what worked and what did not, so future teams can repeat successes and avoid repeated mistakes.
- Closeout
- Related: Lessons Learned, Punch List
The final project process of verifying deliverable acceptance, releasing resources, settling contracts, archiving records, and obtaining formal sign-off.
- Punch List
- Related: Closeout, Quality Assurance
A record of minor incomplete or defective items identified during inspection that must be corrected before final acceptance of the work.
- Quality Assurance
- Related: Quality Control, Punch List
The planned, systematic activities that ensure project processes are being followed correctly so that deliverables meet defined quality requirements.
- Quality Control
- Related: Quality Assurance, Acceptance Criteria
The process of monitoring and measuring specific deliverable results against quality standards and recording findings to verify acceptance.
- Acceptance Criteria
- Related: Quality Control, Scope Statement
The measurable conditions a deliverable must satisfy to be approved by the customer or sponsor, agreed before work begins.
- RACI Matrix
- Related: Stakeholder Register, Work Package
A responsibility chart showing, for each task, who is Responsible, Accountable, Consulted, and Informed, clarifying roles and preventing ownership gaps.
- Procurement
- Related: Request for Proposal, Service Level Agreement
The process of acquiring goods or services from outside vendors, including planning, soliciting, selecting, contracting, and administering supplier agreements.
- Request for Proposal (RFP)
- Related: Procurement, Statement of Work
A formal solicitation document describing project requirements and asking prospective vendors to submit detailed technical and pricing proposals.
- Statement of Work (SOW)
- Related: Request for Proposal (RFP), Service Level Agreement
A document describing the work to be performed under a contract, including deliverables, schedule, standards, and acceptance terms.
- Service Level Agreement (SLA)
- Related: Procurement, Statement of Work
A contract clause or document defining measurable performance levels a vendor must meet, such as response times, uptime, and remedies for shortfalls.
- Resource Leveling
- Related: Critical Path Method (CPM), Schedule Compression
A scheduling technique that adjusts start and finish dates to resolve resource overallocation, often extending the project duration beyond the original plan.
- Triple Constraint
- Related: Baseline, Scope Creep
The interdependent trade-off among scope, time, and cost, where changing one element typically requires adjusting at least one of the others.
- Project Life Cycle
- Related: Milestone, Closeout
The sequence of phases a project passes through from initiation to closure, with each phase producing defined outputs and requiring approval to proceed.