Building Science and Home Performance Fundamentals

  • Stack effect pressure difference: ΔP = ρ·g·h·(1/T_out − 1/T_in) with T in absolute units; a 10 °F indoor-outdoor difference across a two-story house is roughly 3-4 Pa at the neutral pressure level.

  • Three transport mechanisms move heat and moisture: conduction, convection (air leakage), and radiation; air leakage typically dominates sensible shell losses at 30-50% in older homes.

  • Water vapor flows from warm/wet to cold/dry; condensing surfaces occur where temperature falls below the dew point, so air sealing must keep the pressure boundary and thermal boundary aligned.

  • Thermal boundary, air barrier, and vapor retarder must be continuous and in the correct order; a vapor retarder on the wrong side traps moisture and promotes decay.

  • R-value is resistance to conductive heat flow (hr·ft²·°F/Btu); U-value = 1/R is conductance, and assembly U-values add in series: U_total = 1/(R1+R2+...+Rfilm).

  • Dew point of air at 70 °F and 40% RH is about 45 °F; surface temperatures below that value support condensation and mold growth.

  • Capillary suction, air leakage, and vapor diffusion drive moisture in that order of magnitude; diffusion through most building materials is small compared with air-transported moisture.

  • Pressure diagnostics use three reference pressures: inside, outside, and the neutral pressure level where inside equals outside; the NPL shifts with stack, wind, and mechanical imbalance.

Quick reference

Assessment, Testing and Diagnostic Measurement

  • Blower door test per ASTM E779: establish baseline pressures, install door in an exterior opening, and report CFM50 at 50 Pa reference pressure after correcting for temperature and altitude.

  • CFM50 to natural infiltration: divide by 20 for an average home (N-factor 15-25), or use ASHRAE 62.2 effective leakage area for ventilation sizing.

  • ACH50 = (CFM50 × 60) / conditioned volume in ft³; typical pre-weatherization values run 8-20 ACH50, tight homes below 3 ACH50.

  • Duct leakage test per ASTM E1554: pressurize the duct system to 25 Pa with the house at a known pressure and report CFM25 as a percentage of system airflow.

  • Pressure pan readings above 1-2 Pa with reference to the house indicate duct leakage to the outside or to unconditioned space.

  • Infrared imaging requires a minimum indoor-outdoor temperature difference of about 18 °F and steady conditions for at least 3 hours to resolve thermal anomalies.

  • Calibrate and zero instruments before use: manometers, combustion analyzers, and hygrometers drift; record serial numbers and calibration dates in the test report.

  • Zone pressure diagnostics use a calibrated fan and reference tube to measure pressure boundaries and estimate the effective leakage area of an isolated zone.

Quick reference

Building Shell, Insulation and Air Sealing

  • Grade I insulation is uniformly installed with full contact on all six sides; Grade II has minor gaps; Grade III has substantial gaps and compressions that reduce effective R-value.

  • Compression reduces R-value per inch: fiberglass batt compressed to half thickness retains roughly 60-70% of its nominal R-value.

  • The top plate, sill plate, band joist, and rim joist are the highest-priority air sealing locations, along with attic access hatches and recessed fixtures.

  • Attic insulation must maintain a 1-inch clearance around heat-producing fixtures and chimneys unless an approved listed assembly permits contact.

  • Air barrier materials must be continuous and sealed at penetrations, transitions, and framing intersections; the air barrier and thermal boundary should be coincident.

  • Window U-factor and SHGC are separate metrics: U-factor governs heat loss, SHGC governs solar gain, and the selection depends on climate zone and orientation.

  • Insulation depth for a target R-value: depth (in) = target R-value / R-per-inch of the material; loose-fill cellulose is about 3.5 R per inch.

  • Dense-pack wall insulation requires a minimum installed density of about 3.5 lb/ft³ in a 2x4 cavity to control settling and convection.

Quick reference

HVAC Systems

  • Equipment sizing follows ACCA Manual J for load, Manual S for equipment selection, Manual D for duct design, and Manual T for air distribution.

  • Sensible heat ratio SHR = sensible capacity / total capacity; typical residential cooling SHR is 0.70-0.80, and oversizing raises SHR and shortens runtime.

  • Refrigerant charge is verified by superheat (fixed orifice) or subcooling (TXV) methods; target subcooling is typically 8-12 °F per manufacturer data.

  • Airflow target is about 400 CFM per ton of cooling capacity; low airflow causes coil icing, and high airflow reduces latent removal.

  • Combustion air requirements: 50 ft³ per 1,000 Btu/hr input for an unconfined space, or two openings sized per the applicable code for a confined space.

  • Heat pump balance point is the outdoor temperature where capacity equals load; supplementary heat engages below that point.

  • Furnace steady-state efficiency is measured with a combustion analyzer; AFUE accounts for cycling and jacket losses over a heating season.

  • Duct insulation R-value and sealing at joints, boots, and plenums reduce distribution losses, which can reach 20-30% in unconditioned attics.

Quick reference

Combustion Safety and Ventilation

  • Combustion analysis measures O2, CO, CO2, stack temperature, and draft; ambient CO above 35 ppm or undiluted flue CO above 400 ppm (air-free) warrants action.

  • Draft measurement in the flue should show negative pressure relative to the zone, typically -2 to -5 Pa for natural draft appliances at steady state.

  • Worst-case depressurization test: close doors and windows, operate all exhaust fans and dryers, then verify the appliance draft remains within the manufacturer's specified range.

  • Spillage of flue gases into the living space indicates a failed draft; shut down the appliance and correct the cause before returning it to service.

  • ASHRAE 62.2 whole-house ventilation rate: Q = 0.03 × floor area + 7.5 × (bedrooms + 1) in CFM, with local exhaust of 50 CFM intermittent or 20 CFM continuous for baths.

  • A naturally drafting water heater needs a properly sized combustion air supply; tight homes with exhaust fans can backdraft it.

  • Carbon monoxide alarms should be installed on each level and near sleeping areas; CO is produced by incomplete combustion and is undetectable by smell.

  • Ventilation systems require balancing: measure exhaust and supply flows with a calibrated hood and confirm the net house pressure stays near neutral.

Quick reference

Energy Modeling

  • Degree-day method: annual heating energy = (UA × HDD × 24) / (efficiency × ΔT), where UA is the envelope conductance in Btu/hr·°F.

  • HDD and CDD are computed against a 65 °F balance point by convention; a lower balance point is used for internal-gain-dominated buildings.

  • Model inputs must include conditioned volume, envelope areas and R-values, window U-factor and SHGC, infiltration, internal gains, and equipment efficiency.

  • Savings estimates are compared against a calibrated baseline; calibration uses at least 12 months of utility data and targets a mean bias error within ±5%.

  • Interactive effects matter: air sealing reduces both conduction losses and infiltration, so savings cannot be added linearly across measures.

  • Simple payback = installed cost / annual savings; it ignores measure life, financing, and escalation, so pair it with life-cycle cost analysis.

  • Modeling tools include REM/Rate, EnergyPlus, and BEopt; each uses different assumptions, so document the software version and input set.

  • Weather normalization adjusts consumption to a standard climate year so that pre- and post-retrofit comparisons are valid.

Quick reference

Work Scope and Client Reporting

  • A work scope lists each measure with quantity, location, specification, and installed cost, plus the expected savings and the basis for each estimate.

  • Priority order for measures: health and safety first (combustion, moisture, mold), then air sealing and insulation, then equipment replacement.

  • The report should state test-in and test-out values (CFM50, ACH50, duct leakage) so that performance improvement is verifiable.

  • Client communication includes a written summary of findings, the recommended scope, expected savings range, and a clear statement of what is excluded.

  • Contracts should specify warranty terms, change-order procedures, and the standard of work; reference the applicable codes and program requirements.

  • Any measure that changes the building's pressure balance requires a combustion safety check before and after installation.

  • Photos, moisture readings, and instrument data belong in the report appendix to support findings and defend against disputes.

  • Post-retrofit verification repeats the diagnostic tests and compares measured results against the modeled savings assumptions.

Quick reference

Building Science and Home Performance Fundamentals

  • Sensible heat equation: Q = 1.08 × CFM × ΔT for air at standard conditions, where Q is in Btu/hr.

  • Latent heat equation: Q_latent = 0.68 × CFM × ΔW, where ΔW is the humidity ratio difference in grains per pound.

  • Total heat = sensible + latent; the psychrometric chart gives humidity ratio, dew point, enthalpy, and wet-bulb for any air state.

  • Enthalpy difference between indoor and outdoor air drives total (not just sensible) load on ventilation and infiltration.

  • Radiant heat transfer follows Q = σ·ε·A·(T1⁴ − T2⁴); surface temperature, not air temperature, governs comfort near windows and cold walls.

  • Thermal mass shifts and dampens temperature swings; mass inside the insulation is beneficial, mass outside is not.

  • Pressure-driven moisture transport moves 10-100 times more water vapor than diffusion through the same assembly.

  • A building's pressure boundary should coincide with its thermal boundary; misalignment creates cold surfaces and condensation risk.

Quick reference

Assessment, Testing and Diagnostic Measurement

  • Blower door readings must be corrected to standard conditions: correct for air density using indoor and outdoor temperature and barometric pressure.

  • Multiple-point blower door testing produces a leakage curve; the exponent n in Q = C·ΔP^n typically falls between 0.6 and 0.75 for residential buildings.

  • Effective leakage area ELA = CFM50 / 18 for a typical home, expressed in square inches at 4 Pa reference.

  • Duct leakage as a percentage of system airflow: divide CFM25 by total system CFM and compare against program thresholds (commonly 10-15%).

  • Manometer reference tubes must be connected to the correct pressure port; reversed tubing yields sign errors that invalidate the test.

  • Hygrometers should be checked against a saturated salt reference; RH error above ±5% affects moisture diagnosis.

  • Smoke pencils and theatrical fog trace air leakage paths during a blower door test; infrared confirms the thermal signature.

  • Record test conditions (indoor and outdoor temperature, wind, baseline pressure) with every measurement because they affect repeatability.

Quick reference

Building Shell, Insulation and Air Sealing

  • Rim joists and band joists are sealed with rigid foam or spray foam and insulated to the same level as the adjacent wall.

  • Attic knee walls require an air barrier on the conditioned side and insulation on the unconditioned side, with a continuous top plate seal.

  • Recessed can lights must be IC-rated and sealed; older non-IC fixtures require a box or cover that maintains clearance.

  • Chimney chases and flue penetrations need metal flashing and noncombustible sealing, never expanding foam in contact with the flue.

  • Insulation baffles maintain a 1-inch ventilation channel at the roof deck in vented attics to prevent wind-washing and ice dams.

  • Spray foam expands 30-100 times its liquid volume; install in lifts per manufacturer limits to avoid trapped moisture and off-gassing.

  • Air sealing reduces the stack effect, which lowers both heating load and the potential for backdrafting combustion appliances.

  • Windows with a U-factor of 0.30 or lower and SHGC tuned to orientation reduce both heating and cooling loads in mixed climates.

Quick reference

HVAC Systems

  • Static pressure in a residential duct system should stay below about 0.5 in. w.c. total external static pressure; higher values indicate undersized ducts or restrictive filters.

  • Return air paths must be sized to match supply; a starved return raises static pressure and reduces airflow across the coil.

  • Refrigerant lines should be insulated on the suction line to prevent condensation and capacity loss.

  • Combustion efficiency = (stack loss + jacket loss) subtracted from 100%; steady-state efficiency above 80% indicates a condensing or high-efficiency appliance.

  • Heat pump defrost cycles temporarily reverse the refrigerant flow; supplemental heat engages during defrost to maintain supply temperature.

  • Thermostat placement away from supply registers, sunlight, and exterior walls prevents short cycling and false readings.

  • Duct register airflow can be measured with a flow hood; balancing dampers adjust branch flows to design values.

  • Equipment replacement should be matched to the measured load, not the nameplate of the existing unit, to avoid oversizing.

Quick reference

Combustion Safety and Ventilation

  • Air-free CO = measured CO × (20.9 / (20.9 − O2 measured)); this normalizes readings to zero excess air.

  • A CO reading above 100 ppm air-free in the flue gas indicates a problem requiring service; above 400 ppm requires shutdown.

  • Combustion air openings for confined spaces: one within 12 inches of the top and one within 12 inches of the bottom of the enclosure.

  • Exhaust-only ventilation depressurizes the house; it must be balanced with supply air or makeup air to protect combustion appliances.

  • Heat recovery ventilators (HRV) exchange sensible heat; energy recovery ventilators (ERV) exchange both sensible and latent heat.

  • The ASHRAE 62.2 ventilation rate assumes the house is not tighter than 0.35 ACH natural; tighter homes require additional mechanical ventilation.

  • Backdrafting is confirmed with a smoke test or a pressure measurement at the draft hood showing positive pressure relative to the room.

  • Gas leaks are detected with a combustible gas detector or bubble solution; a leak at any joint requires shutdown and repair.

Quick reference

Energy Modeling

  • Manual J load calculation inputs include design temperatures, window areas and orientation, infiltration (ACH natural), internal gains, and duct location.

  • Design conditions come from ASHRAE Fundamentals or the program's climate data; using the wrong design temperature skews equipment sizing.

  • Internal gains: about 230 Btu/hr per occupant sensible, plus appliance and lighting gains per the modeling tool's defaults.

  • Infiltration in models is often entered as ACH natural, derived from CFM50 using an N-factor or the LBL model.

  • Model calibration compares predicted versus actual consumption monthly; adjust infiltration and equipment efficiency within reasonable bounds.

  • Interactive effects: reducing infiltration lowers the heating load but also reduces the ventilation benefit, so pair with mechanical ventilation.

  • Savings uncertainty should be reported as a range, not a single number, to reflect weather and occupancy variability.

  • Document assumptions in the report so that another analyst can reproduce the model and verify the savings estimate.

Quick reference

Work Scope and Client Reporting

  • Test-in data establish the baseline; test-out data verify performance and support program incentives.

  • Health and safety measures take precedence over energy measures and must be documented even when outside the energy scope.

  • Cost-effectiveness screening uses simple payback, savings-to-investment ratio (SIR), or life-cycle cost; SIR above 1.0 indicates cost-effective.

  • The scope should separate measures by priority tier and state dependencies between measures (for example, air seal before insulating).

  • Client reports should include a plain-language summary, the technical appendix, and a clear list of assumptions and exclusions.

  • Program compliance requires specific documentation: BPI or equivalent certifications, test forms, and photo evidence.

  • Change orders require written client approval before additional work proceeds.

  • Post-installation walkthrough with the client confirms operation of ventilation, thermostats, and combustion appliances.

Quick reference

Building Science and Home Performance Fundamentals

  • Heat flows from warm to cold; in winter, heat leaves through the envelope and enters through the ground, and the direction reverses in summer.

  • The three modes of heat transfer are conduction (through solids), convection (through fluids and air), and radiation (electromagnetic).

  • Thermal bridging through framing reduces effective R-value; advanced framing reduces bridging and improves whole-wall performance.

  • Moisture sources include bulk water, capillary action, air-transported vapor, and diffusion; control bulk water first.

  • Mold requires moisture, organic food source, and suitable temperature; controlling moisture is the only practical control.

  • Pressure differences of 1-3 Pa are enough to drive significant air leakage; stack, wind, and fans are the drivers.

  • Air sealing should be done before insulation so that the thermal boundary is continuous and effective.

  • Combustion appliances, exhaust fans, and duct systems all interact with house pressure and must be evaluated together.

Quick reference

Assessment, Testing and Diagnostic Measurement

  • Blower door test setup: seal all exterior openings except the door, open interior doors, and set the reference tube to the outside.

  • Baseline pressure readings are taken before the fan runs; a baseline above 2 Pa suggests wind or stack interference.

  • Test-in and test-out values should be recorded on the same form with the same instrument for valid comparison.

  • Duct leakage testing requires sealing all registers and connecting the fan to the air handler or a register boot.

  • Pressure pan testing measures the pressure difference across a register grille relative to the house; values above 1-2 Pa indicate leakage.

  • Infrared camera emissivity settings affect readings; use tape or a known-emissivity target on reflective surfaces.

  • Moisture meters measure percent moisture content by weight or pin resistance; readings above 20% in wood indicate risk.

  • All test results should be reported with the instrument used, calibration date, and test conditions.

Quick reference

Building Shell, Insulation and Air Sealing

  • Air sealing materials include caulk, spray foam, rigid foam, and housewrap tape; the choice depends on substrate, movement, and temperature.

  • Sill plates on concrete should be sealed with a sill seal gasket or caulk compatible with concrete.

  • Penetrations through the top plate, such as wiring and plumbing, must be sealed with foam or caulk.

  • Attic hatch covers should be insulated and weatherstripped to the same R-value as the attic floor.

  • Duct boots in unconditioned space should be sealed to the drywall with mastic and insulated.

  • Vapor retarders are classed by permeance: Class I below 0.1 perm, Class II 0.1-1.0 perm, Class III 1.0-10 perm.

  • In cold climates, a Class I or II vapor retarder belongs on the warm side of the insulation.

  • Insulation should fill the cavity completely without gaps or compression; gaps reduce effective R-value disproportionately.

Quick reference

HVAC Systems

  • Furnace AFUE is the ratio of annual heat output to annual fuel input; 80% is standard, 90%+ indicates condensing.

  • Air conditioner SEER2 and heat pump HSPF2 are the current efficiency metrics under the updated test procedures.

  • Refrigerant types: R-410A and R-32 are common; R-22 is phased out and must not be mixed with other refrigerants.

  • A TXV maintains a constant superheat; a fixed orifice relies on charge and outdoor temperature.

  • Heat pump auxiliary heat should be locked out above the balance point to avoid unnecessary resistance heating.

  • Duct design uses friction rate and equivalent length; Manual D specifies the method and allowable friction rate.

  • Filters should be sized for low pressure drop; a dirty filter raises static pressure and reduces airflow.

  • Commissioning includes verifying charge, airflow, temperature split, and static pressure against manufacturer specifications.

Quick reference

Combustion Safety and Ventilation

  • Combustion requires fuel, oxygen, and ignition; incomplete combustion produces CO, and excess air dilutes it.

  • The stoichiometric air-fuel ratio for natural gas is about 10:1 by volume; appliances operate with excess air for safety.

  • Draft hoods and barometric dampers regulate draft; a blocked flue causes spillage and CO accumulation.

  • A combustion analyzer should be calibrated and its sensor replaced per manufacturer intervals; O2 sensors degrade over time.

  • Ventilation systems should be commissioned by measuring flows at each terminal and verifying the net pressure effect on the house.

  • Bath fans should be rated for the required CFM at the installed static pressure, not just the free-air rating.

  • Kitchen range hoods above 400 CFM require makeup air in many codes to prevent depressurization.

  • CO alarm placement follows manufacturer instructions; combination smoke/CO alarms are acceptable where listed.

Quick reference

Energy Modeling

  • Modeling software inputs should match the test-in data: measured infiltration, insulation levels, and equipment specifications.

  • The model should be updated after the retrofit to reflect as-built conditions and verified with test-out data.

  • Sensitivity analysis identifies which inputs most affect predicted savings; infiltration and equipment efficiency often dominate.

  • Weather data should come from a typical meteorological year (TMY) dataset for the location, not a single extreme year.

  • Energy savings estimates should be presented with a range and the assumptions behind the range.

  • Interactive effects between measures require whole-house modeling rather than measure-by-measure addition.

  • Model outputs should be checked against utility bills to validate the baseline before reporting savings.

  • Documentation of model version, inputs, and assumptions supports quality assurance and program review.

Quick reference

Work Scope and Client Reporting

  • The report should state the building's test-in condition, the recommended measures, the expected results, and the basis for each recommendation.

  • Cost estimates should include labor, materials, permits, and contingency, and should be separated from energy savings claims.

  • Client education includes thermostat operation, filter maintenance, ventilation operation, and combustion safety awareness.

  • Warranty and call-back procedures should be explained in writing at project closeout.

  • Program incentives and financing options should be disclosed accurately, including eligibility requirements.

  • The scope should identify measures that are not recommended and explain why, so the client understands the trade-offs.

  • Final documentation includes test-out results, photos, invoices, and warranty information in a single package.

  • Client sign-off on the completed scope confirms acceptance and supports program quality assurance.