Mistake 1

Selecting grout volume and mix by rule of thumb (for example 'a bag per ten feet') instead of computing the annular volume from borehole diameter, casing outside diameter, and the excess factor the spec requires.

Candidates memorize a few field shortcuts and never practice the geometry; the exam phrases the annulus as diameters, so they subtract incorrectly or forget to square the radii, and they omit the excess allowance for washed-out or enlarged holes.

What to do instead

Drill the formula until automatic: annular volume per foot equals 0.7854 times (borehole diameter squared minus casing outside diameter squared), converted from square inches to gallons, then multiplied by the required excess percentage and the seal length. Work ten varied problems with different units before exam day.

Mistake 2

Mixing up the purpose and placement of the sanitary seal, the grout seal, and the filter pack, and answering questions as if any one of them performs all three jobs.

The three components sit close together in the well and all relate to 'sealing', so candidates conflate them; study time is spent on installation steps rather than on why each component exists.

What to do instead

Build a one-page comparison table with columns for location, material, primary function, and what fails if it is missing. State each function aloud in one sentence, such as the filter pack stabilizes and filters, the grout seal blocks surface and formation water, and the sanitary seal closes the casing-to-grout path at the surface.

Mistake 3

Answering well development questions by naming a single method without matching it to the formation, screen type, and drilling method, and without stating the acceptance criterion for stopping.

Development is taught as a list of techniques (surging, jetting, airlifting, dispersants) and candidates never learn the selection logic or the endpoint, so they pick whichever term they saw most recently.

What to do instead

For each method, write the formations it suits, the formations it damages, and the observable endpoint such as clear water, stable sand content, and stabilized specific capacity. Practice scenario questions by first identifying the formation and completion type, then choosing the method.

Mistake 4

Calculating the required casing length or screen setting from the total drilled depth rather than from the static and pumping water levels, the desired submergence, and the screen interval.

Depth is the most visible number on a drilling log, so candidates anchor on it and skip the hydraulic reasoning that determines where the screen and pump actually belong.

What to do instead

Before computing, sketch a vertical section to scale and label ground elevation, static water level, pumping water level, screen top and bottom, and pump setting. Derive each number from the labeled sketch rather than from total depth.

Mistake 5

Treating disinfection as a fixed recipe (a set chlorine concentration and contact time) without adjusting for measured chlorine demand, pH, or the volume of water in the well and distribution system.

Field practice often uses a standard dose, and candidates do not connect the dose to the water chemistry that consumes chlorine; they also forget to compute well volume from diameter and water column.

What to do instead

Learn the sequence: compute the water volume, measure or estimate chlorine demand, set the target residual, check pH range for effective hypochlorous acid, then set contact time. Practice problems where the same target dose is applied to a clean well and to a turbid, high-demand well.

Mistake 6

Sizing a pump from the rated capacity on the nameplate instead of from the design yield, total dynamic head, and the pump curve intersection with the system curve.

Candidates look for one number to plug in and the nameplate is the easiest to find; they also confuse shutoff head, operating head, and total dynamic head, so the curve is read at the wrong point.

What to do instead

Practice reading a pump curve at three points (shutoff, best efficiency, and maximum flow) and computing total dynamic head as the sum of lift, drawdown, discharge pressure head, and friction loss. Select the pump whose curve crosses the system curve near the design yield and best efficiency range.

Mistake 7

Omitting friction loss, or estimating it from pipe length alone, when computing total dynamic head for the pump setting and discharge line.

Friction loss depends on flow rate, pipe diameter, and fittings, so it is invisible in a simple sketch; candidates default to a flat percentage or ignore it, which understates head and oversizes the pump.

What to do instead

Work problems with friction tables or the Hazen-Williams relationship, including equivalent lengths for elbows, valves, and the drop pipe, and show how doubling flow raises friction loss sharply. Always state the assumed flow rate and pipe size alongside the result.

Mistake 8

Setting the pump intake without accounting for drawdown, seasonal water level decline, and the required submergence above the pump, or placing it inside or below the screen interval.

Candidates use the static water level because it is the number given, and they do not picture how pumping lowers the water surface; submergence and screen position are treated as details rather than constraints.

What to do instead

For every setting-depth question, compute the pumping water level first, add the required submergence, and confirm the intake stays above the screen top. Practice with seasonal decline scenarios so the margin, not just the current level, drives the answer.

Mistake 9

Confusing electrical diagnostic values, such as mixing up resistance and current readings, or interpreting a motor insulation test without the correct reference and test conditions.

The formulas and units look similar on paper, and candidates memorize meter settings rather than what each measurement proves about the motor, cable, and controls.

What to do instead

Build a troubleshooting table pairing each symptom (no start, tripped overload, low output) with the measurement to take, the expected value, and the likely cause. Practice unit conversions and Ohm's law problems until the relationship between voltage, current, resistance, and insulation readings is automatic.

Mistake 10

Answering pump installation sequence questions in the wrong order, for example energizing and testing the motor before verifying rotation, wiring, and control settings, or backfilling before the grout and seal are verified.

Candidates remember the individual steps but not the dependency between them, and they study checklists as unordered lists rather than as a sequence where each step protects the next.

What to do instead

Write the installation and start-up sequence from memory as a numbered flow with the reason each step must precede the next, then compare against reference material. Rehearse the order for both submersible and line-shaft installations, since the sequences differ.