GSC Project Manager · Keep the key ideas within reach.

Quick reference

Project Initiation and Business Case

  • Business case components: strategic alignment, options analysis, expected benefits, cost estimate, key risks, and a recommendation with a defined investment decision point.

  • Net present value = sum of (cash flow in year t) / (1 + r)^t minus initial investment; accept the option with the highest positive NPV when options are mutually exclusive.

  • Internal rate of return is the discount rate at which NPV equals zero; a project is financially acceptable when IRR exceeds the organization's cost of capital.

  • Payback period = time until cumulative net cash inflows equal the initial outlay; it ignores cash flows after payback and the time value of money.

  • Return on investment = (net benefit / cost) x 100; state the measurement period and whether benefits are gross or net of operating costs.

  • The project charter authorizes the project, names the sponsor and project manager, and records high-level scope, budget, milestones, and success criteria.

  • A project is justified only when the preferred option's benefits exceed those of the 'do nothing' or 'do minimum' baseline over the appraisal period.

  • Benefit-cost ratio = present value of benefits / present value of costs; a ratio above 1.0 indicates benefits exceed costs on a discounted basis.

  • Feasibility appraisal covers technical, financial, legal, operational, and schedule dimensions; a single failed dimension can invalidate the business case.

Quick reference

Planning and Scheduling

  • Critical path = longest duration path through the network; its total float is zero, and any delay on it delays the project finish date by the same amount.

  • Total float = late finish minus early finish (or late start minus early start); free float = early finish of the activity minus early start of its earliest successor minus duration.

  • Forward pass computes early start and early finish; backward pass computes late finish and late start; float is derived from the difference between the two passes.

  • PERT expected duration = (optimistic + 4 x most likely + pessimistic) / 6; standard deviation = (pessimistic - optimistic) / 6.

  • A milestone has zero duration and marks a significant event or approval point; it carries no resources and no float of its own.

  • Fast tracking overlaps sequential activities to compress schedule and increases rework risk; crashing adds resources to critical-path activities and increases cost.

  • Crashing is most cost-effective when applied to critical activities with the lowest cost-per-unit-time slope until a new critical path emerges.

  • Finish-to-start is the default dependency; start-to-start, finish-to-finish, and start-to-finish links each require a defined lag to be meaningful.

  • Resource leveling changes start and finish dates to resolve over-allocation and may extend the critical path; resource smoothing uses float without moving the finish date.

Quick reference

Cost Estimation and Budgeting

  • Cost baseline = sum of authorized work package budgets plus contingency reserves; the management reserve sits outside the baseline and covers unknown-unknown scope.

  • Analogous estimating uses historical comparable projects and is fast but less accurate; bottom-up estimating aggregates detailed work package estimates and is more accurate but costly.

  • Parametric estimating applies a unit rate (cost per unit, per square metre, per line of code) to a measurable parameter; accuracy depends on the validity of the underlying data.

  • Earned value: CV = EV - AC and SV = EV - PV; CPI = EV / AC and SPI = EV / PV; negative variances and indices below 1.0 indicate adverse performance.

  • Estimate at completion (typical variance) = BAC / CPI; EAC (atypical variance) = AC + (BAC - EV); EAC (both variances) = AC + (BAC - EV) / (CPI x SPI).

  • Estimate to complete = EAC - AC; variance at completion = BAC - EAC; to-complete performance index = (BAC - EV) / (BAC - AC).

  • Cost of quality = cost of conformance (prevention plus appraisal) plus cost of non-conformance (internal plus external failure); prevention is generally cheaper than failure.

  • Contingency reserves cover identified risks and are released by the risk owner; management reserves cover unidentified risks and require sponsor approval to use.

  • Sunk costs are excluded from forward-looking decisions; opportunity cost of the chosen option is included in the comparison of alternatives.

Quick reference

Risk Management

  • Risk management sequence: plan risk management, identify risks, perform qualitative analysis, perform quantitative analysis, plan responses, implement responses, monitor risks.

  • Risk exposure (expected monetary value) = probability x impact; EMV of the project is the sum of EMVs across all identified risks and feeds the contingency reserve.

  • Threat responses: avoid, transfer, mitigate, escalate, accept; opportunity responses: exploit, enhance, share, escalate, accept.

  • A risk register records risk ID, cause, event, effect, probability, impact, score, owner, response, residual risk, and trigger conditions.

  • Qualitative analysis uses a probability-impact matrix and urgency assessment; quantitative analysis uses Monte Carlo simulation, decision trees, or sensitivity analysis.

  • A risk trigger is an early warning condition indicating that a risk is about to occur; a secondary risk results from a response, and a residual risk remains after the response.

  • A risk owner is accountable for the response; a risk action owner performs specific response actions; the two roles may be assigned to different people.

  • Monte Carlo simulation produces a distribution of possible project outcomes; the cumulative distribution supports selecting a confidence level for the cost or schedule reserve.

  • Risk appetite is the willingness to accept risk; risk threshold is the measurable level at which exposure becomes unacceptable and escalation is required.

Quick reference

Quality Management

  • Quality management comprises plan quality management, manage quality (assurance), and control quality; control quality verifies deliverables, manage quality audits processes.

  • Prevention over inspection: prevention costs are incurred to avoid defects, appraisal costs to detect them, and failure costs arise when defects reach the customer.

  • A Pareto chart ranks causes by frequency and supports the 80/20 rule; an Ishikawa (fishbone) diagram organizes causes into categories such as people, process, and materials.

  • A control chart distinguishes common-cause variation from special-cause variation; a process is out of control when a point exceeds a control limit or shows a defined non-random pattern.

  • A histogram shows the frequency distribution of a variable; a scatter diagram tests whether two variables are correlated; a flowchart maps process steps and decision points.

  • Quality metrics are measurable attributes of a deliverable or process, such as defect density, cycle time, or first-pass yield, and are recorded in the quality management plan.

  • Marginal analysis compares the cost of achieving the next increment of quality with the benefit obtained; optimal quality is where marginal cost equals marginal benefit.

  • Gold plating is adding unrequested features; it is a defect of scope management and consumes budget without adding validated value.

  • A quality audit is a structured, independent review of whether project activities comply with organizational policies, processes, and procedures.

Quick reference

Procurement and Contract Management

  • Fixed-price contracts place cost risk on the seller; cost-reimbursable contracts place cost risk on the buyer; time-and-materials contracts share risk and require a not-to-exceed ceiling.

  • Contract types: firm-fixed-price (FFP), fixed-price incentive fee (FPIF), fixed-price with economic price adjustment (FP-EPA), cost plus fixed fee (CPFF), cost plus incentive fee (CPIF), cost plus award fee (CPAF).

  • A statement of work describes the work in sufficient detail for sellers to respond; a statement of requirements describes the need and is used when the solution is not yet defined.

  • Procurement documents: request for information gathers market data; request for quotation is used for low-value standard items; request for proposal is used for complex requirements.

  • Source selection may use lowest price, lowest price technically acceptable, or best value with weighted technical and commercial criteria.

  • The bidder conference ensures all prospective sellers receive identical information; any clarification must be communicated to all bidders.

  • A contract change must be formally documented and approved by an authorized person; informal direction from a non-authorized person does not modify the contract.

  • Inspection and acceptance criteria are defined in the contract; final payment is normally conditional on formal acceptance of the deliverables.

  • Contract closure confirms that all deliverables were accepted and all administrative matters, including final payment and records, are complete.

Quick reference

Stakeholder Engagement and Communication

  • Stakeholder identification records interest, influence, power, impact, and expectations; the power/interest grid classifies stakeholders as manage closely, keep satisfied, keep informed, or monitor.

  • Engagement levels range from unaware and resistant through neutral and supportive to leading; the engagement plan records current and desired levels with gap-closing actions.

  • Communication channels for n stakeholders = n(n - 1) / 2; channel count grows quadratically with the number of participants.

  • Communication methods: interactive (meetings, calls), push (email, reports), and pull (intranet, repositories); selection depends on urgency, audience, and information sensitivity.

  • The communication management plan defines who receives what information, in what format, at what frequency, through which channel, and with what escalation path.

  • Sender-receiver models include encoding, the medium, decoding, and feedback; noise is any interference that distorts the message, and feedback confirms receipt and understanding.

  • A stakeholder register is a living document; it is reviewed and updated at defined intervals and at every phase gate or significant change.

  • Escalation paths, decision rights, and meeting cadence are agreed during planning; unplanned escalation is a communication risk and should be logged.

  • Formal written communication is required for contractual matters, approvals, and changes; informal verbal communication suits routine coordination.

Quick reference

Execution, Monitoring, and Control

  • Integrated change control: every change request is logged, assessed for impact on scope, schedule, cost, quality, and risk, then approved or rejected by the change control board.

  • A change approved without updating the baseline creates a discrepancy between plan and performance; the baseline is re-set only through formal approval.

  • Scope creep is uncontrolled scope addition without change control; gold plating is adding unrequested features; both are detected by comparing work to the scope baseline.

  • Earned value uses EV = percent complete x BAC; percent complete should be based on objective measures such as milestones or weighted deliverables.

  • Variance analysis compares planned versus actual performance; trend analysis projects future performance from historical data; earned schedule expresses schedule performance in time units.

  • A work performance report consolidates status, progress, variances, and forecasts; a work performance information process compares actuals with the plan.

  • The issue log records issues, their owners, and resolution status; issues are current problems, distinct from risks, which are uncertain future events.

  • Configuration management controls versions of deliverables and documents; a configuration management system tracks changes and ensures only approved versions are used.

  • Quality control measurements are compared against quality metrics; failed deliverables enter the change request or rework process, not the acceptance process.

Quick reference

Project Closure and Benefits Realization

  • Closure activities: verify deliverables are accepted, obtain formal sign-off, transition the product, release resources, archive records, and capture lessons learned.

  • Administrative closure documents final performance against baselines, records variances and their causes, and closes contracts and financial accounts.

  • Final product transition includes training, support arrangements, warranty terms, and confirmation that operational owners accept the deliverable.

  • Lessons learned are captured throughout the project and consolidated at closure; they are stored in the organizational process assets for future projects.

  • Benefits realization occurs after project closure; the project delivers outputs and capabilities, while the sponsoring organization realizes outcomes and benefits.

  • A benefits register records each benefit, its owner, the metric, the baseline, the target value, the measurement date, and the realization mechanism.

  • Benefits may be tangible (revenue, cost reduction) or intangible (customer satisfaction, compliance); intangible benefits still require a defined measurement approach.

  • A post-implementation review compares realized benefits with the business case and identifies corrective action or lessons for future investment decisions.

  • The project manager's authority typically ends at closure; ongoing ownership of benefits transfers to the business owner or operations manager.

Quick reference

Professional Responsibility and Ethics

  • Core ethical duties: responsibility, respect, fairness, and honesty; these apply to stakeholders, the profession, and society.

  • Conflicts of interest must be disclosed promptly and managed; a project manager must not use position for personal benefit or accept gifts that could influence decisions.

  • Confidential and proprietary information is protected and used only for the purpose for which it was provided, including after the project ends.

  • Estimates, status reports, and forecasts must be accurate and not manipulated to please sponsors; withholding material bad news is a misrepresentation.

  • Whistleblowing is appropriate when internal escalation fails and there is a genuine risk to safety, law, or the public interest; follow organizational channels first where feasible.

  • Cultural sensitivity, non-discrimination, and equal treatment of stakeholders are components of the respect principle in professional conduct.

  • Real or perceived conflicts, gifts, and outside employment are governed by organizational policy; where policy is silent, the stricter ethical standard applies.

  • Professional development is an obligation; certification holders commit to continuing education and to accurate representation of their qualifications.

  • When a directive is unethical or illegal, the project manager escalates, documents the concern, and declines to participate; contractual obligation does not override law or ethics.