GSC Project Manager study materials
GSC Project Manager study resources

GSC Project Manager study plan

GSC Project Manager · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Planning and Scheduling & Execution, Monitoring, and Control

  • Build a one-page process map linking initiation, planning, execution, monitoring, and closure, labeling where each remaining domain enters

  • Draft a work breakdown structure for a sample project to three levels and identify the dependency types between at least ten activities

  • Construct a network diagram and calculate the critical path, total float, and free float for the sample schedule

  • Define the control cycle by writing the inputs, outputs, and frequency for schedule and performance reviews

Your checkpoint

A two-page scheduling and control workbook containing the process map, a three-level WBS, a labeled network diagram with critical path and float calculations, and a written control-cycle summary

Week 2

Planning and Scheduling & Execution, Monitoring, and Control

  • Estimate activity durations using three-point and analogous methods, then compare the results and justify the differences

  • Build a resource-loaded schedule and level resources across at least two competing activities

  • Establish a baseline and write the variance thresholds that would trigger corrective action

  • Practice earned value calculations for schedule and cost performance using a small dataset

Your checkpoint

A baselined schedule with resource histogram plus a one-page earned value report showing planned value, earned value, actual cost, and index interpretations

Week 3

Cost Estimation and Budgeting & Project Initiation and Business Case

  • Compare bottom-up, parametric, and analogous estimating on the sample project and document accuracy tradeoffs

  • Compile a cost baseline with contingency and management reserves clearly separated

  • Draft a business case that states the problem, options considered, expected benefits, and the recommendation

  • Calculate payback period and a simple return measure for two project options and select one with justification

Your checkpoint

A cost baseline spreadsheet paired with a two-page business case that includes option analysis, benefit estimates, and a funding recommendation

Week 4

Risk Management & Quality Management

  • Run a risk identification session and log at least fifteen risks with causes, triggers, and owners

  • Perform qualitative risk analysis using probability and impact scoring, then rank risks and select response strategies

  • Build a quality management plan defining standards, acceptance criteria, and metrics for three deliverables

  • Design a quality control checklist and describe how inspection results feed back into corrective action

Your checkpoint

A risk register with scored and prioritized entries and response plans, plus a quality plan containing measurable acceptance criteria and one control checklist

Week 5

Procurement and Contract Management & Stakeholder Engagement and Communication

  • Select a contract type for two contrasting procurement scenarios and justify risk allocation for each

  • Draft a procurement statement of work with clear deliverables, acceptance terms, and change provisions

  • Map stakeholders by influence and interest, then write tailored engagement strategies for the top five

  • Produce a communication plan specifying audience, message, channel, frequency, and owner

Your checkpoint

A procurement package containing a statement of work and contract-type justification, plus a stakeholder map and communication plan covering at least eight stakeholders

Week 6

Execution, Monitoring, and Control & Quality Management

  • Simulate a change request and walk it through impact assessment, approval, and baseline update

  • Diagnose three performance scenarios and prescribe corrective or preventive actions for each

  • Apply a quality tool such as cause-and-effect analysis or Pareto ranking to a sample defect dataset

  • Write an integrated status report that reconciles scope, schedule, cost, risk, and quality data

Your checkpoint

A change control log with one fully processed change request and an integrated status report that includes defect analysis and recommended corrective actions

Week 7

Project Closure and Benefits Realization & Professional Responsibility and Ethics & Project Initiation and Business Case

  • Assemble a closure checklist covering deliverable acceptance, contract closeout, and lessons learned

  • Draft a benefits realization plan that assigns measures, owners, and review points after handover

  • Analyze three ethics scenarios involving conflicts of interest, reporting accuracy, and procurement fairness, and state the correct course of action

  • Revisit the business case to confirm that benefit assumptions still hold and record any reassessment triggers

Your checkpoint

A closure and benefits package containing the acceptance checklist, lessons-learned template, benefits realization plan, and written responses to three ethics scenarios

Week 8

Project Initiation and Business Case & Planning and Scheduling & Cost Estimation and Budgeting & Risk Management & Quality Management & Procurement and Contract Management & Stakeholder Engagement and Communication & Execution, Monitoring, and Control & Project Closure and Benefits Realization & Professional Responsibility and Ethics

  • Complete two full-length timed practice exams and record scores by domain

  • Analyze every missed item to classify the error as knowledge gap, misread question, or reasoning error

  • Rebuild weak areas by rewriting summary sheets for the three lowest-scoring domains

  • Confirm readiness by reviewing the ethics and closure summary sheets one final time

Your checkpoint

A domain-scored practice exam log with error classifications and rewritten summary sheets for the three weakest domains

Milestones

Week 2: Can build a network diagram and compute critical path and float unaided, and correctly interpret earned value indices from raw data

Week 4: Risk register and quality plan are complete and cross-referenced, with each high-ranked risk linked to at least one response and one monitoring metric

Week 6: Can process a change request end to end and produce an integrated status report without referring to notes

Week 8: Practice exam scores exceed 75 percent overall with no domain below 65 percent, and every missed item has a documented root cause