Planning converts the charter into an integrated baseline. Candidates must know the work breakdown structure (deliverable-oriented decomposition, 100% rule, work packages), the difference between a product breakdown and a WBS, and how dependencies, lags, and leads shape a network diagram. Understand critical path (longest path, zero float), total float versus free float, and how resource levelling differs from resource smoothing - levelling may move the end date, smoothing must not.

Concepts to hold firmly

  • Rolling-wave planning: detailed near term, coarse far term.
  • Baselines (scope, schedule, cost) are approved versions; changes need control.
  • Milestones have zero duration and no effort.
  • Estimating durations should use historical data and team input, not optimism.

Traps

Classic distractors ask you to crash the critical path when the delay sits on a non-critical path with float. Check float first. Another trap: compressing by fast-tracking (overlapping) increases risk, whereas crashing adds cost - questions often want the risk-aware answer. Be careful with questions that call a task "critical" merely because it is important; criticality is a network property.

Rule of thumb

Before proposing any recovery action, compute float. Only activities with zero total float can delay the project end date.

Worked example

Task A (5 days) and Task B (8 days) run in parallel, both feeding Task C. A has 3 days float; B has zero. A supplier delay of 2 days on A consumes float but does not move the finish. The same delay on B moves the finish by 2 days and must be escalated.