Ground Disturbance Level II study materials
Ground Disturbance Level II study resources

Ground Disturbance Level II cheat sheet

Ground Disturbance Level II · Keep the key ideas within reach.

Quick reference

Ground Disturbance Planning and Hazard Assessment

  • Ground disturbance means any activity that displaces or penetrates the ground surface, including excavation, trenching, augering, boring, driving posts or piles, and sometimes compaction or grading that alters soil structure.

  • A pre-job hazard assessment identifies buried facilities, soil conditions, overhead and underground utilities, traffic, adjacent structures, and environmental sensitivities before work starts.

  • Soil type drives hazard: sand and gravel collapse readily, saturated silt flows, and clay can stand temporarily but fails suddenly after drying or vibration.

  • Spoil piles must be set back from the excavation edge; a common rule is at least 1 m (about 3 ft) from the edge, and never closer than the depth of the excavation, whichever is greater.

  • The excavation safety factor: any trench 1.2 m (4 ft) or deeper requires a protective system, and any trench 1.5 m (5 ft) or deeper requires a means of exit within 7.5 m (25 ft) of lateral travel.

  • A written ground disturbance plan records the scope, locate status, crossing agreements, isolation of energy sources, emergency response, and the sign-off of the person supervising the work.

  • Utility Right-of-Way (URW) agreements and crossing agreements are required where the excavation crosses an existing pipeline or utility corridor; without them the work is unauthorized.

  • Hazard assessment must be repeated when conditions change: new crew, weather event, water ingress, or a change in excavation depth or method.

Quick reference

Buried Facility Locating and Notification Requirements

  • One-Call notification must be made before digging, typically with a minimum of 2 to 3 full working days' notice depending on jurisdiction; the locate request ticket number and expiry date must be recorded.

  • The tolerance zone is the area within a set distance either side of the marked facility centreline - commonly 1 m (about 3 ft) - where hand excavation or non-destructive methods are mandatory.

  • Locate marks use a standard colour code: red = electric, yellow = gas/oil/petroleum, orange = communications, blue = potable water, green = sewer/drainage, purple = reclaimed water, white = proposed excavation.

  • Ground disturbance within the tolerance zone requires hand exposure, vacuum excavation, or another approved non-destructive method; mechanical digging in the tolerance zone is prohibited.

  • Locate marks have a limited validity period (often 10 to 30 days) and must be refreshed if the ticket expires or the marks are destroyed by weather or traffic.

  • A locate is not a guarantee of depth or exact position; the excavator must confirm the facility by exposing it, and must stop and re-notify if a facility is found where none was marked.

  • If a facility is contacted or damaged, work must stop, the operator and the One-Call centre must be notified, and the area made safe before any repair or resumption.

  • Private or customer-owned facilities beyond the utility's responsibility are not always located by the One-Call service; the excavator must arrange separate locating for them.

Quick reference

Safe Excavation and Ground Disturbance Practices

  • Competent ground disturbance supervision requires a designated person who is trained, experienced, and authorized to stop work when conditions become unsafe.

  • Spoil, tools, and materials must be kept back from the excavation edge; a minimum setback of 1 m (about 3 ft) is common, and never less than the excavation depth.

  • Access and egress: trenches 1.5 m (5 ft) or deeper need a ladder or ramp within 7.5 m (25 ft) of every worker's travel distance.

  • Atmospheric testing is required before entry into any excavation where a hazardous atmosphere may exist, and continuous monitoring is required where the hazard persists.

  • Excavations must be inspected by a competent person at the start of each shift, after rain or vibration, and after any change in conditions.

  • Barricades, signage, and lighting must protect the excavation perimeter, and open excavations must be covered or guarded when unattended.

  • Water must be controlled with ditching, pumps, or sumps; standing water in a trench increases collapse risk and can hide hazards.

  • Spoil and equipment must not be stored over buried utilities, and the excavation must not undermine adjacent foundations, roads, or utility supports.

Quick reference

Supervision, Roles, and Regulatory Compliance

  • The employer has the primary duty to provide a safe work system, training, supervision, and the resources needed to follow the ground disturbance plan.

  • The supervisor must verify that locates are current, the plan is followed, workers are trained, and the excavation is inspected before and during work.

  • Workers must follow the plan, use required protective equipment, report hazards, and stop work when they believe conditions are unsafe.

  • The utility operator must respond to locate requests, mark its facilities, and provide information about its infrastructure on request.

  • The One-Call centre receives and transmits locate requests and maintains the ticket record; it does not perform the locating itself.

  • Regulatory compliance requires records: locate tickets, hazard assessments, inspection logs, training records, and incident reports must be retained for the required period.

  • Incident reporting duties include notifying the regulator, the utility operator, and emergency services where a contact, injury, or release occurs.

  • A ground disturbance permit or authorization may be required by the landowner, the utility, or the regulator before work begins; work without it is non-compliant.