Power Eng 5th Class · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Boiler and Pressure Vessel Fundamentals

  • Sketch and label a firetube boiler and a watertube boiler from memory, naming the furnace, shell or drums, tubes, tube sheets, and uptake, and state which way combustion gas flows in each.

  • Define the terms MAWP, design pressure, hydrostatic test pressure, and safety-valve set pressure, and compute each of the first three for a stated vessel example.

  • List the fittings and appurtenances a boiler must carry (safety valve, pressure gauge, water column, low-water cutoff, blowdown, feed check, main steam stop) and explain the function of each in one sentence.

  • Explain how a pressure vessel fails: describe creep, overheating from scale, and corrosion thinning, and identify the inspection method that detects each.

  • Read a simplified boiler drawing and mark the steam space, water space, and normal water level, then explain why the water column must be kept clear.

Your checkpoint

A single hand-drawn two-boiler cross-section sheet with all major parts labelled plus a one-page table of fittings, their function, and the failure mode each one guards against.

Week 2

Boiler Operation, Combustion, and Controls

  • Sequence the cold start-up of a packaged boiler from pre-purge through main flame, stating the required purge time and the reason for each step.

  • Describe the three elements of the fire triangle and explain how each is controlled in a boiler furnace, then relate excess air to stack temperature and efficiency.

  • Explain the function of the flame scanner, the program relay, and the fuel valve proving system, and describe what happens on flame failure.

  • Differentiate on-off, high-low, and modulating firing control and state which load pattern suits each.

  • Carry out a routine shift: record steam pressure, water level, stack temperature, and draft, and state the corrective action for low water level, high steam pressure, and a smoking stack.

Your checkpoint

A written start-up and shutdown checklist for one boiler type, in order, with the reason for each step and the operator action on flame failure and low water.

Week 3

Boiler Operation, Combustion, and Controls & Safety, Emergency Procedures, and Legislation

  • Explain combustion safety interlocks and describe a pre-ignition purge and a post-purge, including what would happen if the purge were bypassed.

  • Describe emergency procedures for a furnace explosion, a tube rupture, and a low-water condition, listing the immediate actions in order.

  • Summarize the operator's legal duties under boiler and pressure-vessel safety legislation: qualifications to hold a certificate of competency, logbook entries, accident reporting, and the limits of what an operator may alter.

  • Explain the purpose of the periodic inspection, the hydrostatic test, and the safety-valve pop test, and state who may witness each.

  • Identify the personal protective equipment and lockout/tagout steps required before entering a boiler or working on a fuel train.

Your checkpoint

A one-page emergency response card covering low water, high pressure, tube rupture, and fire, plus a short written summary of the operator's legal responsibilities and recordkeeping duties.

Week 4

Pumps, Compressors, and Auxiliary Equipment

  • Classify pumps as centrifugal, positive displacement reciprocating, or rotary, and match each to a feedwater, fuel oil, or sump duty.

  • Explain cavitation: its cause, its sound, its damage, and three ways to prevent it, including net positive suction head.

  • Describe the parts and operating principle of a reciprocating air compressor and state why an unloading device and a relief valve are needed.

  • Describe how to start, monitor, and shut down a feedwater pump, including checking suction valve position, discharge pressure, bearing temperature, and gland leakage.

  • Explain the function of the economizer, air preheater, superheater, and deaerator and state what each does to efficiency or water quality.

Your checkpoint

A pump and auxiliary equipment comparison table (type, principle, typical duty, common failure, prevention) covering at least five machines, plus a feedwater pump start-up procedure.

Week 5

Water Treatment and Boiler Feedwater

  • Explain why raw water is unacceptable as feedwater: describe scale, corrosion, carryover, and foaming and the damage each causes.

  • Describe external treatment (softening, demineralization, deaeration) and internal treatment (oxygen scavengers, scale inhibitors, alkalinity and pH control) and state which problem each addresses.

  • Interpret a water test sheet: given pH, total hardness, dissolved oxygen, conductivity, and alkalinity values, state whether each is in range and what corrective action follows.

  • Explain blowdown, both bottom and surface, and calculate how blowdown rate relates to dissolved solids concentration.

  • Describe the deaerator's role and the corrosion caused by dissolved oxygen and carbon dioxide in the feed system.

Your checkpoint

A completed water-test interpretation worksheet with a target range and a corrective action for each of six parameters, plus a short written blowdown procedure.

Week 6

Instrumentation, Controls, and Basic Electricity

  • Explain how a pressure transmitter, thermocouple or RTD, and level probe produce a signal, and distinguish a switch from a transmitter.

  • Describe a simple control loop: identify the sensor, controller, and final control element in a boiler water-level or steam-pressure loop and explain proportional and on-off control action.

  • Apply Ohm's law and the power equation to calculate current, voltage, resistance, and power in simple series and parallel circuits.

  • Explain the purpose of fuses, circuit breakers, grounding, and lockout/tagout in a plant electrical system, and describe the danger of arc flash.

  • Describe how to calibrate or verify a pressure gauge and a level control using a known reference, and state why calibration records matter.

Your checkpoint

A worked problem set of at least eight Ohm's law and power calculations with answers, plus a labelled block diagram of one boiler control loop naming the sensor, controller, and final element.

Week 7

HVAC, Refrigeration, and Building Systems

  • Explain the vapour-compression refrigeration cycle stage by stage and identify the evaporator, compressor, condenser, and metering device on a sketch.

  • Describe the safety hazards of refrigerants: frostbite, asphyxiation in low areas, and the legal rules on venting and handling, and state the leak-check and recordkeeping duties.

  • Explain how a building heating, ventilating, and air-conditioning system delivers heat and cooling, and describe the role of the air handler, filters, dampers, and controls.

  • Describe routine checks on a refrigeration or HVAC plant: suction and discharge pressures, superheat and subcooling, filter condition, and belt and bearing condition.

  • Explain how a cooling tower or chiller interacts with the boiler plant and why water treatment matters on the cooling side too.

Your checkpoint

A labelled refrigeration cycle diagram with pressure and temperature behaviour at each stage, plus a one-page routine inspection checklist for an HVAC or refrigeration unit.

Week 8

Boiler and Pressure Vessel Fundamentals & Boiler Operation, Combustion, and Controls & Safety, Emergency Procedures, and Legislation & Pumps, Compressors, and Auxiliary Equipment & Water Treatment and Boiler Feedwater & Instrumentation, Controls, and Basic Electricity & HVAC, Refrigeration, and Building Systems

  • Take two full timed practice exams under exam conditions and record the score for each domain separately.

  • Re-study the two weakest domains, using the missed questions to drive the review rather than rereading notes.

  • Recite from memory the emergency actions for low water, high pressure, flame failure, and tube rupture, and the fittings required on a boiler.

  • Redo every calculation type (MAWP, hydrostatic test pressure, blowdown, Ohm's law) without notes until each is correct twice in a row.

  • Assemble a one-page formula and definition sheet and confirm you can explain every term on it.

Your checkpoint

Two scored practice exams with a per-domain error log, plus a final one-page formula and definition sheet covering all seven domains.

Milestones

Week 2: Can walk through a boiler start-up and shutdown from memory, in order, and name the operator action for flame failure and low water without notes.

Week 4: Scores at least 70% on a mixed set of domain 1 to 4 questions, and can explain cavitation and pump start-up in your own words.

Week 6: Scores at least 70% on a mixed set of domain 5 and 6 questions and gets every Ohm's law and power calculation right on a first attempt.

Week 8: Scores at least 75% overall on a full timed practice exam, with no single domain below 60%, and has a completed formula and definition sheet.