CESSWI flashcards
CESSWI · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Daily inspection report
- A dated record of site conditions, weather, rainfall, BMPs inspected, deficiencies found, and corrective actions taken, signed by the inspector and kept with the SWPPP.
- Photo scale reference
- A ruler, coin, or measuring staff placed beside a feature in a photograph so its size and condition can be verified later; the image is also dated and located on the site map.
- Notice of deficiency
- A written record given to the party responsible for a failing or missing BMP, stating the problem, the required correction, and a deadline, then tracked until verified closed.
- As-built drawing
- A drawing updated after installation to show actual locations, dimensions, and elevations of BMPs, including deviations from the approved plan, used for later inspection and maintenance.
- Chain of custody record
- A form tracking a water sample from collection to the laboratory, listing collection time, sampler, seal number, and preservation method, so the analytical results remain legally defensible.
- Rain gauge log
- A record of measured precipitation, usually to 0.01 inch, kept on site to document whether a storm was large enough to trigger the required post-event inspection.
- Pre-construction conference
- A meeting held before earthwork where owner, contractor, and inspector agree on SWPPP responsibilities, inspection schedules, reporting lines, and emergency contacts.
- Toolbox talk documentation
- A short training record listing topic, date, presenter, and signed attendees, demonstrating that crews were instructed on erosion control and spill response requirements.
- Written confirmation of direction
- A verbal instruction about a stormwater deficiency is restated in writing or email within 24 hours, creating a dated, traceable record of who was told what.
- Escalation sequence
- The documented order for unresolved issues: site superintendent first, then contractor or owner, then the permitting authority, with each step recorded in the project file.
- Stop-work authority
- The documented right of an inspector or owner's representative to halt activity causing an unpermitted discharge, pending correction of the deficient control.
- Single point of contact
- One named person with a 24-hour telephone number who receives and relays stormwater notifications, preventing missed messages among owner, contractor, and regulator.
- Permethrin-treated clothing
- Factory-treated garments that kill ticks and mosquitoes on contact; the treatment survives many washings and supplements, but does not replace, repellent on exposed skin.
- Poison ivy identification
- Three leaflets per leaf in alternate arrangement and no thorns; the plant's urushiol oil causes a rash and can be spread by tools, boots, or pet fur.
- Heat acclimatization
- A gradual increase in workload over one to two weeks for new or returning workers, which lowers heat illness risk and is paired with water, rest, and shade.
- SDS Section 8
- The Safety Data Sheet section listing exposure limits and required personal protective equipment for a chemical; inspectors read it before handling fuels, solvents, or treatment chemicals.
- Trench protective system threshold
- At 5 feet deep or more, OSHA requires sloping, shoring, or a trench box; at 4 feet a competent person must evaluate the soil and may require protection.
- Epinephrine auto-injector
- A prescription device carried by people with severe insect-sting allergy, injected into the outer thigh at the first sign of anaphylaxis and followed by emergency medical care.
- RUSLE equation
- A = R x K x LS x C x P, an estimate of average annual soil loss; the cover factor C and practice factor P are the ones site practices can change.
- Silt fence flow limit
- Silt fence works only for sheet flow; concentrated flow overtops or bypasses it, so channels and swales need check dams, rock, or other measures instead.
- Silt fence installation specs
- Fabric buried at least 6 inches in a compacted trench, posts 6 to 8 feet on center on the downslope side, and the fence laid out on the contour.
- Check dam spacing rule
- In a swale, dams are spaced so the top of the downstream dam is level with the toe of the upstream dam, keeping pooled water shallow and velocity low.
- Sediment basin sizing
- A common rule provides 3,600 cubic feet of storage per acre drained, with a dewatering device such as a skimmer that draws water slowly from the surface.
- Construction entrance length
- At least 50 feet of coarse aggregate over a stable base, sized to shake mud from tires; wash racks are added where tracking onto public roads continues.
- Stabilization deadline
- Under the construction general permit, disturbed areas at final grade must be stabilized within 14 days; some states shorten this to 7 days, so check the permit.
- Treatment train order
- Sequence controls from the source outward: keep soil covered to prevent erosion, then trap moving sediment, then safely convey and manage runoff volume and velocity.
- Secondary containment sizing
- Containment around fuel or chemical storage must hold 110 percent of the largest container or 10 percent of total volume, whichever is greater, plus rainfall allowance.
- Concrete washout
- A lined, contained pit or bag for rinsing concrete equipment; the wash water is highly alkaline and must never reach a storm drain, ditch, or waterbody.
- Final stabilization definition
- All soil-disturbing activities are complete and disturbed areas carry uniform perennial vegetation or equivalent cover, commonly 70 percent, so erosion is effectively stopped.
- Notice of Intent
- The form submitted to the permitting authority to obtain NPDES construction stormwater coverage; it identifies the operator, the site, receiving waters, and the SWPPP.
- Notice of Termination
- The filing that ends permit coverage; it may be submitted only after final stabilization is achieved and temporary controls are removed or stabilized.
- Illicit discharge indicator
- Any dry-weather flow from an outfall, or stained or odorous water, suggests a non-stormwater connection and must be traced, documented, and reported.