Behavioral Health Conversion: Locking, Egress, and a Blocked Horizontal Exit

CHFM · Put your knowledge to work in context.

All case studies

Behavioral Health Conversion: Locking, Egress, and a Blocked Horizontal Exit

A 210-bed community hospital is converting a 24-bed medical/surgical unit on the third floor of a five-story patient tower into an 18-bed adult behavioral health unit. The unit has two means of egress: the main stair at the west end, and a horizontal exit through a two-hour smoke barrier into the adjoining medical unit. The design team proposes staff-controlled locked entry doors at the unit entrance, a 15-second delayed-egress release at the stair door, ligature-resistant hardware throughout, and removal of a 40-foot corridor wall to create a decentralized nurse station. During the 10-week construction phase, that corridor segment is the only access path to the horizontal exit. The local fire marshal has objected to both the locking strategy and the phasing plan, and the project is holding its building permit.

1. The architect argues the horizontal exit satisfies the second means of egress and asks you to defend the 15-second delayed-egress release at the stair. What is your response?

Read the worked answer

I would separate the two issues, because the architect is conflating them.

Horizontal exit. A horizontal exit is a legitimate means of egress only if it discharges into a refuge area that can hold the occupant load of the discharging side at the code-specified density, the barrier is properly rated and the doors self-close and latch, and the receiving space is not itself compromised. For 18 sleeping occupants this is usually achievable, but I would require a written capacity calculation for the receiving medical unit and confirmation that its own corridor is not counted twice. If those hold, I can defend the egress concept.

Delayed egress. A 15-second delay is not clinical security. A patient who is determined enough simply waits out the delay every time, and the arrangement depends on AHJ approval plus proper integration with the fire alarm. In a behavioral occupancy the right mechanism is the code-recognized special locking arrangement for such units: staff continually available, keys immediately at hand, release on alarm, and documented AHJ approval with a written staffing and training plan.

So: defend the horizontal exit with the capacity math, but replace the delayed-egress proposal with an approved special locking arrangement. Hardware must still be single-operation in the direction of egress.

2. What conditions would you require before the corridor wall comes down and the horizontal exit path is obstructed for 10 weeks?

Read the worked answer

The horizontal exit is a life safety feature, not a convenience path, so the default answer is that it stays usable. If the design genuinely cannot proceed without removing that segment, I require, in writing and before demolition:

  • An approved alternative egress analysis showing travel distance and clear width on the remaining path, signed by the design professional and accepted by the fire marshal.
  • Interim Life Safety Measures scoped to the actual risk: the fire alarm and sprinkler systems in the work area stay in service or a documented fire watch is implemented; combustibles removed and hot work permitted separately; temporary partitions and directional signage installed; staff briefed on the altered route and on assisting patients who cannot self-evacuate.
  • An ICRA for the demolition dust, with negative pressure and barriers, because the adjoining unit is occupied by potentially immunocompromised patients.
  • A daily walkthrough by facilities, logged, with authority to stop work if the corridor clear width or exit signage degrades.
  • Sequencing so demolition happens in the shortest window and the exit is never blocked overnight, and a costed contingency to re-route the nurse station if the AHJ refuses.

I would not sign a permit on the promise that 'it's only 10 weeks.'

3. The ligature risk assessment flags the corridor's sprinkler heads and fire alarm pull stations. The design team proposes enclosing the pull stations in locked cabinets and painting over the sprinkler heads. How do you rule?

Read the worked answer

I would reject both proposals, but not dismiss the underlying concern.

Pull stations. Locking a manual fire alarm box defeats its purpose and will not survive an AHJ review. The defensible options are institutional covers that remain operable without a key by anyone, or relocating the station to a supervised location outside the patient-accessible corridor with the AHJ's agreement. If neither works, the design changes, not the device.

Sprinkler heads. Painting a head voids its listing and is a straightforward code violation; covering one is worse because it delays operation. The correct answer is a listed institutional or recessed sprinkler head designed for the environment, or a concealed space arrangement with protective cage where the listing permits it.

My ruling: the ligature risk is real and must be engineered out, but the tools are listed institutional devices, design layout changes, and staff observation of high-risk points - never disabling, obstructing, or covering life safety equipment. I would require the design team to return with a device-by-device schedule showing the listed product for each location, and I would document the AHJ's concurrence before the fixtures are ordered.