Planning, Design, and Construction

  • FGI Guidelines establish minimum design standards for healthcare facilities, including space requirements, safety risk assessments, infection control, and functional relationships; many states adopt them by reference.

  • A pre-construction risk assessment (PCRA) is completed before construction or demolition and addresses infection control, utility interruptions, noise, vibration, air quality, and life safety impacts.

  • The Infection Control Risk Assessment (ICRA) classifies construction activity from Class I through Class IV; Class IV is the highest risk and requires critical barriers, HEPA filtration, and negative pressure where indicated.

  • Interim Life Safety Measures (ILSM) are implemented when construction, damage, or system impairment reduces normal life safety features; examples include fire watch, temporary barriers, and additional exit signage.

  • Typical design sequence: programming, schematic design, design development, construction documents, bidding/negotiation, construction administration, and commissioning.

  • Commissioning verifies that building systems meet the owner's project requirements through documented functional performance testing and issue resolution.

  • NFPA 101 governs life safety by occupancy classification; new and existing occupancies have different requirements, and sprinkler protection can affect allowable construction and exit requirements.

  • Accessible design under ADA/ABAAS requires accessible routes, clear floor space, accessible fixtures, and accessible patient and public areas.

Quick reference

Operations and Maintenance

  • PM completion rate = completed preventive maintenance work orders ÷ scheduled preventive maintenance work orders × 100.

  • MTTR = total repair time ÷ number of repairs; MTBF = operating time ÷ number of failures during the period.

  • NFPA 25 covers inspection, testing, and maintenance of water-based fire protection systems, including sprinklers, standpipes, valves, alarm devices, and fire pumps on defined frequencies.

  • NFPA 72 covers fire alarm inspection, testing, and maintenance; initiating devices, notification appliances, and system functions are tested on defined schedules.

  • NFPA 110 requires emergency power supply systems to be maintained and periodically exercised; Level 1 systems include monthly loaded exercise requirements.

  • ASHRAE 170 specifies ventilation, pressure relationships, and air-change rates for healthcare spaces; airborne infection isolation rooms are negative pressure relative to adjacent areas.

  • NFPA 99 governs medical gas and electrical systems; medical gas outlets, alarms, and source equipment require verification and ongoing maintenance documentation.

  • A CMMS tracks assets, work orders, PM schedules, labor, parts, and performance metrics such as backlog, PM completion, and downtime.

  • Work order priority: immediate life safety or clinical threat first, then critical clinical systems, then routine and cosmetic work.

Quick reference

Financial Management

  • The capital budget covers long-lived assets above a defined cost threshold; the operating budget covers recurring expenses within the current fiscal year.

  • NPV = present value of cash inflows − present value of cash outflows; an independent project with NPV greater than zero creates value at the chosen discount rate.

  • IRR is the discount rate that makes NPV equal zero; accept a project when IRR exceeds the organization's cost of capital or hurdle rate.

  • Payback period = initial investment ÷ annual net cash inflow; it ignores the time value of money and cash flows after the payback point.

  • Straight-line depreciation = (asset cost − salvage value) ÷ useful life.

  • Variance = actual − budget; for expenses, actual greater than budget is unfavorable; for revenue, actual less than budget is unfavorable.

  • Life-cycle cost includes acquisition, installation, operation, maintenance, energy, and disposal costs over the asset's useful life.

  • Cost per adjusted patient day and cost per square foot are common healthcare facility benchmarking metrics.

Quick reference

Regulatory Compliance

  • CMS Conditions of Participation set federal Medicare and Medicaid requirements; compliance is necessary for reimbursement and survey success.

  • Joint Commission Environment of Care standards address safety, security, hazardous materials, fire safety, medical equipment, utilities, and staff education.

  • The Statement of Conditions documents life safety compliance and deficiencies; Plans for Improvement track corrective actions and completion dates.

  • OSHA requires programs such as hazard communication, bloodborne pathogens, lockout/tagout, confined space, and asbestos awareness when applicable.

  • EPA regulates refrigerants, hazardous waste, and stormwater; permits, manifests, and disposal records must be maintained.

  • NFPA 101 and NFPA 99 are commonly adopted through state licensure, CMS, and Joint Commission standards; local codes may be stricter than national codes.

  • Joint Commission tracer methodology follows patient care processes across departments to evaluate standards compliance and system integration.

  • A utility system risk assessment identifies critical utilities, failure modes, redundancy needs, maintenance requirements, and emergency procedures.

Quick reference

Risk Management and Life Safety

  • RACE = Rescue, Alarm, Contain, Extinguish/Evacuate; it is the fire response sequence used in healthcare occupancies.

  • PASS = Pull, Aim, Squeeze, Sweep; it is the technique for using a portable fire extinguisher.

  • ILSM are required when fire safety features are impaired; examples include fire watch, temporary barriers, added exit signage, and enhanced surveillance.

  • Hot work requires a permit, area preparation, a fire extinguisher, and a fire watch during and after the work.

  • Defend-in-place uses smoke compartments and horizontal evacuation to protect occupants rather than immediate building evacuation.

  • A hazard vulnerability analysis (HVA) ranks hazards by probability, impact, and preparedness to prioritize emergency management planning.

  • A risk register records identified risks, likelihood, impact, owner, mitigation actions, and status.

  • Root cause analysis is used after sentinel events or major failures to identify system causes and prevent recurrence.