Mistake 1

Treating the Building and Personal Property Coverage Form's blanket limit as if it applied to every building separately, so the candidate answers that each location has its own full limit rather than one shared limit across all covered locations.

Candidates see a single limit of insurance on the declarations page and assume it is per-location, because most personal lines and many small commercial policies list a limit per building. The form's blanket treatment and the reporting-form alternative blur together in memory.

What to do instead

Drill the three limit structures side by side: specific (a limit per building at each location), scheduled (limits listed per item), and blanket (one limit applying to all covered property at all locations, subject to the coinsurance and value-reporting mechanics). For any scenario question, first identify which structure the declarations describe, then apply that structure before touching deductibles or causes of loss.

Mistake 2

Applying the coinsurance clause to the wrong base - using the limit of insurance rather than the actual replacement cost of the property at the time of loss - when computing a coinsurance penalty.

The formula has several moving parts (insurance carried divided by insurance required, times the loss, minus the deductible) and candidates memorize the shape of the equation without anchoring the denominator. They also forget that the requirement is a percentage of replacement cost, not of actual cash value.

What to do instead

Work at least a dozen penalty calculations by hand, always writing the denominator as the coinsurance percentage times the replacement cost at the time of loss. Practice with the 80%, 90%, and 100% options and with a loss that both does and does not exceed the required amount, so the 'no penalty if adequately insured' outcome is as familiar as the penalty outcome.

Mistake 3

Assuming the Commercial Property policy automatically covers newly acquired buildings and personal property at full replacement cost for an unlimited period, rather than recognizing the short automatic acquisition window and its sublimits.

Newly acquired property is genuinely covered automatically, so candidates stop reading once they see the coverage exists and never register the time limit (typically 30 days) or the requirement to report the acquisition and pay premium.

What to do instead

Memorize the newly acquired property provision as three facts: what is covered (buildings and personal property at new locations, plus property at existing locations), the time window, and the limit (a percentage of the policy limit or a stated amount, whichever is less). Then practice questions that place a loss on day 20 versus day 45 so the boundary becomes concrete.

Mistake 4

Confusing the Valuation condition's replacement cost option with actual cash value and applying the wrong one to partial losses, particularly forgetting that replacement cost settlement can require repair or replacement within a stated period and that ACV applies until that condition is met.

The policy grants replacement cost but conditions payment on actually repairing or replacing the property, and the loss payment provision allows a holdback. Candidates read 'replacement cost' on the declarations and assume settlement is unconditional.

What to do instead

Build a two-column table of replacement cost versus actual cash value outcomes for the same loss and add the repair-or-replace condition and the time limit as footnotes. Practice questions where the insured takes the ACV payment and does not rebuild, so the consequence (no additional payment) is learned as a behavior, not a phrase.

Mistake 5

Overlooking that the Causes of Loss - Special Form is subject to exclusions and limitations that operate differently from the Basic and Broad forms, and answering that 'special' means all risk with no exclusions.

The Special form is often described casually as all-risk, and candidates carry that shorthand into the exam. They also miss that the Special form does not use the same named-peril list, so they look for a peril list that is not there.

What to do instead

Learn the Special form as 'all risk of direct physical loss subject to exclusions,' then memorize the exclusion categories that exist across all three forms (ordinance or law, earth movement, water, governmental action, nuclear hazard, utility services, war, and the intentional loss and dishonest acts provisions). For each exclusion, note the difference between the anti-concurrent causation lead-in on the Special form and the named-peril structure of Basic and Broad.

Mistake 6

Missing the water damage exclusion's distinction between flood, surface water, and waves (excluded) and accidental discharge or leakage from a plumbing, heating, or sprinkler system (limited or covered), and answering that all water losses are excluded.

The exclusion is long and contains both excluded perils and an exception for discharge or leakage, plus a $2,500 limitation on the discharge exception in many editions. Candidates read the first line and stop.

What to do instead

Draw a decision tree: is the water from a natural body, surface runoff, or weather (excluded)? Is it from a plumbing, heating, air conditioning, or automatic sprinkler system (limited coverage, with the stated sublimit)? Is it from a roof drain or sump pump (excluded or limited depending on the edition)? Walk the tree for five fact patterns until the branches are automatic.

Mistake 7

Failing to recognize that the ordinance or law exclusion is partially bought back by the Ordinance or Law endorsement, and that the base policy pays nothing for the increased cost of complying with building codes after a covered loss.

Candidates conflate the exclusion with the endorsement and assume some code-upgrade coverage is built into the base form. They also do not distinguish the three separate coverages the endorsement can provide: undamaged portion, demolition, and increased cost of construction.

What to do instead

Memorize the three-part structure of the ordinance or law coverage endorsement and what each part pays for. Then practice questions that describe a total loss of an older building where the undamaged portion must be demolished under code - the answer turns on whether the undamaged-portion coverage was purchased, not on the property limit.

Mistake 8

Treating Business Income coverage as if it pays lost profits only, ignoring that it also pays continuing normal operating expenses including payroll, and misidentifying the period of restoration's start and end points.

Candidates analogize to personal lines loss-of-use coverage, which is framed around lost fair rental value or additional living expense, and they assume payroll is always excluded. They also assume the period of restoration ends when the business reopens rather than when the property could with reasonable speed be repaired or replaced.

What to do instead

Write out the Business Income formula explicitly: net income plus continuing normal operating expenses, including payroll, minus noncontinuing expenses. Then define the period of restoration with its two triggers (the date of direct physical loss and the date when the property should be repaired, rebuilt, or replaced with reasonable speed) and its two exclusions (the period before the loss and any increased period caused by enforcement of ordinance or law, unless endorsed).

Mistake 9

Confusing Extra Expense with Business Income and applying the wrong limit or the wrong trigger - for example, assuming Extra Expense requires a suspension of operations or that it shares the Business Income limit.

Both coverages respond to the same loss event and are often written together, so candidates merge them. Extra Expense is designed to fund expenses that keep the business running and does not require a suspension, which is the opposite of Business Income's trigger.

What to do instead

Contrast the two on three axes: trigger (necessary suspension of operations versus expenses incurred to continue operations), measure of loss (lost income plus continuing expenses versus reasonable and necessary extra costs, often capped by a monthly limit), and limit treatment (separate limit versus shared or combined limit). Practice a fact pattern where the insured rents temporary space and pays overtime - the answer is Extra Expense, not Business Income.

Mistake 10

Ignoring the waiting period and the extended period of indemnity when computing a Business Income loss, and assuming coverage begins the day of the loss and ends when the building is repaired.

The waiting period (commonly 72 hours for the Special form) and the extended period of indemnity are endorsement-level details that are easy to skip when the candidate focuses on the limit and the period of restoration. Candidates also forget that the waiting period functions like a deductible in time.

What to do instead

For every time-element question, build a timeline: loss date, waiting period expiration, period of restoration end, extended period of indemnity end. Compute the indemnity period as the overlap of the covered period and the actual loss of income. Practice with a 72-hour waiting period and a 30-day extension so both adjustments appear in the arithmetic rather than as abstract definitions.