CIPS Level 6 Professional Diploma · Put your knowledge to work in context.

All case studies

Port Closure and a Sole-Source Chassis Supplier

NorthBridge Medical manufactures mobile clinical carts in Leeds. Its only chassis supplier, based in Ningbo, produces 12,000 units a month; NorthBridge currently orders 10,500. The chassis is moulded to a proprietary design and the supplier owns the tooling. Ocean transit is six weeks, and NorthBridge holds four weeks of safety stock. A forecast for the next quarter shows demand rising 22% after a major hospital framework win. In week two of the quarter, a dockworkers' strike closes Ningbo for at least three weeks; the supplier says it can hold finished goods but cannot guarantee bookings. Airfreight would cost $18 a unit versus $2 by sea and add two weeks of internal validation for a new route. The company has a £4.5m revolving credit facility, with £1.2m headroom, and a covenant test in 60 days. The sales director wants to promise full delivery; operations wants to cut the forecast.

1. Recommend the immediate response for the next 72 hours. Show the trade-offs you would weigh and the decision criteria.

Read the worked answer

Decision criteria should be patient safety and contractual service, cash, total cost, and reversibility. Demand at +22% is about 12,810 units a month against 12,000 capacity, so there is already an 810-unit monthly gap before the strike. Four weeks' safety stock (about 10,500 units) covers roughly 3.3 weeks at the higher run-rate, but a three-week port closure plus six-week ocean transit creates a replenishment gap of around nine weeks. Do not promise full delivery.

In 72 hours: (1) freeze the unconstrained sales promise and segment orders by hospital go-live, penalty exposure and revenue; (2) instruct the supplier to hold and evidence finished goods, book the earliest alternate port or rail option, and provide daily booking proof; (3) authorise airfreight only for priority SKUs where stock-out cost clearly exceeds the $16-a-unit premium; (4) run a cash sensitivity with finance and pre-agree covenant headroom; (5) issue a customer communication with transparent allocation rules. Avoid airfreighting low-margin standard carts and avoid panic buying. Escalate to the framework customer if service levels are at risk. This is a risk-allocation decision, not a purchasing optimisation.

2. How should NorthBridge redesign its supply chain over 12 months? Specify sourcing, inventory, contract and metrics choices, and explain the risks of each.

Read the worked answer

Over 12 months, qualify a second source, ideally a UK or EU contract moulder, for 25-30% of volume. NorthBridge should own or control the tooling and have a licensing and access agreement. Keep Ningbo for scale but require capacity reservation and dual-port shipping. Change Incoterms where it improves control, for example from FOB to FCA or DAP, and add a port-disruption playbook, finished-goods buffer and pre-approved airfreight clause.

Inventory should be segmented by SKU margin and clinical criticality: perhaps six to eight weeks for critical components, two to three weeks for standard items, plus supplier-held buffer. Implement S&OP with forecast accuracy and capacity review. Metrics should include OTIF, days of supply, lead-time variability, airfreight as a percentage of COGS, supplier concentration and cash-to-cash cycle.

Risks: dual sourcing raises unit cost and duplicates tooling; buffers consume £1-2m of cash; a new supplier needs about six months of validation. Recommend stage-gated investment and a pilot, not a wholesale shift. The aim is resilience at a known cost, not zero risk.