The Sole Source That Stopped the Line Twice
Meridian Sterile Packaging builds single-use procedure kits. It has 220 suppliers. The sterilizable pouch film comes from one converter, sole-sourced, not audited in four years. Two late deliveries in the last six months each stopped the line for two days; contribution loss is about $45,000 per day. The supplier scorecard shows 88% on-time delivery and 1,200 PPM, and carries no process capability data. Purchasing wants to dual-source immediately. Engineering says qualifying a second converter takes nine months and triggers FDA change control on the sterile barrier. The supplier blames resin allocation and offers a 5% price increase in exchange for priority allocation. Incoming inspection moved to skip-lot eight months ago, based on twelve months of clean history.
1. What risk controls should be in place before the next build cycle, regardless of which sourcing strategy is chosen?
Read the worked answer
The exposure is concentrated in one sterile-barrier component with no audit history and a relaxed receiving gate. Controls that do not depend on the sourcing decision:
- Quantify the risk properly. Two stoppages in six months at two days each is roughly $180,000 in contribution loss, plus expedite freight and possible backorders. That number is the budget available for mitigation, and it dwarfs a 5% film price increase. Purchasing should be told this explicitly.
- Buffer strategically, not accidentally. Safety stock sized on the supplier's demonstrated lead-time variability, not on average lead time. If the supplier is the constraint, a bonded or segregated inventory of 6-8 weeks of film may be the cheapest insurance available - but only with shelf-life and storage controls validated for a sterile barrier.
- Put the supplier on a formal SCAR with a dated containment and corrective action: allocation agreement in writing, named resin source and sub-tier visibility, capacity commitment, and a delivery performance recovery plan with weekly reporting.
- Reinstate the audit - a focused process audit of the film extrusion and handling, plus change-control expectations, before any further volume commitment.
- Re-examine skip-lot. Reduced inspection was justified by 12 months of clean history; that history is now contradicted by two delivery failures and no capability evidence. Without process capability data, skip-lot is an assumption, not a conclusion. Tighten the gate and collect data to justify relaxing it again.
- Validate the 5% offer. Priority allocation sounds like a contractual priority, not a capacity one. Get it in writing with remedies.
2. Purchasing wants to dual-source now; engineering says nine months and FDA change control. How should the decision be made?
Read the worked answer
Both are right about their own constraint, and the decision is a risk-versus-time trade, not a vote.
Analysis to put in front of the decision-maker:
- Cost of the status quo: $180,000 in six months of stoppages, plus the tail risk of a missed sterile-barrier supply. Annualized, this is the number the dual-sourcing project must beat.
- Cost and time of dual sourcing: nine months, change control, validation of the sterile barrier (seal strength, integrity, aging), and a permanent split that reduces leverage and volume at the incumbent, possibly raising unit price on both.
- Total cost of ownership, not piece price. Include freight, buffer inventory carrying cost, expedite premium, quality risk, and the cost of regulatory revalidation. A 5% increase on film is likely a rounding error next to two days of line stoppage.
Recommendation shape:
- Do not dual-source as a panic move with a single unqualified alternative. Begin qualification now, phased - it is a nine-month insurance policy being written today for next year's risk.
- Simultaneously invest in the incumbent with a formal improvement plan and the allocation agreement. Supplier development is faster to first benefit than a new source.
- Split the strategy by purpose: the second source exists for resilience and surge, not to chase price. Expect to pay a premium for that resilience and budget it as insurance.
- Set decision gates at months 2, 4, and 6 on the incumbent's delivery and audit performance; if gates are missed, accelerate the second source.
Judgement point: the wrong answer is 'dual-source because sole source is bad.' The right answer is a risk-based, time-phased plan with explicit gates and a quantified cost of failure.
3. How should the supplier scorecard and receiving inspection be redesigned?
Read the worked answer
The scorecard is a lagging rear-view mirror with no predictive content. OTD 88% and 1,200 PPM tell you what happened; they do not tell you whether next month will be short.
Redesign:
- Add leading indicators: order confirmation accuracy, capacity utilization reported by the supplier, sub-tier resin allocation status, days of finished-goods inventory at the supplier, open corrective actions and their ageing, and process capability on the critical film attributes (thickness, seal strength) rather than PPM alone.
- Stratify by criticality. 220 suppliers should not be measured with one template. A sole-source sterile-barrier component deserves monthly review and a named relationship owner; a commodity carton supplier does not.
- Make the scorecard actionable. Every red metric needs an owner, a date, and a consequence - including, for chronic performers, a documented exit path.
- Tie it to the audit cycle. Four years without an audit of a sole-source critical supplier is the actual finding here. Audit frequency should be driven by risk, not by history.
Receiving inspection:
- Skip-lot is defensible only when the supplier's process is demonstrably capable and stable. With no capability data, revert to a tightened sampling plan and use the data collected to build the case for relaxing it again.
- Where skip-lot is retained, keep a periodic verification sample so the assumption is tested rather than assumed.
- Track escapes caught at receiving as a supplier metric, not just a quality department cost.
Test: can someone read the scorecard on Monday and know which supplier to call this week?