Registered Electrical Engineer (G&T) flashcards
Registered Electrical Engineer (G&T) · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Per-unit base change
- To convert an impedance from one base to another, multiply by the ratio of new to old MVA base and by the square of the old to new voltage base.
- Symmetrical components operator a
- The operator a equals one at 120 degrees. Positive sequence is a, negative is a squared, and zero sequence is unity; the three sequences sum to zero.
- Surge impedance loading
- SIL equals line-to-line voltage squared divided by surge impedance. For overhead lines it is roughly the natural loading at which reactive generation equals reactive absorption.
- Equal-area criterion
- For a single machine against an infinite bus, stability is maintained when the accelerating area equals the decelerating area on the power-angle curve.
- Zero-sequence current path
- Zero-sequence current flows only when a grounded neutral return path exists. Ungrounded systems have no zero-sequence current, so ground-fault current is limited to capacitive charging.
- GMD and GMR
- Geometric mean distance is the equivalent spacing between conductors; geometric mean radius is the equivalent conductor radius. Inductance depends on the ratio GMD/GMR.
- Subtransient reactance
- The subtransient reactance X-double-prime-d determines fault current in the first few cycles after a generator terminal short circuit, when the damper winding is active.
- Newton-Raphson load flow
- A load-flow method using the Jacobian matrix of power mismatches. It converges quadratically near the solution but requires a good initial guess and matrix inversion.
- Slack bus definition
- The slack bus fixes voltage magnitude and angle and supplies the difference between total generation and total load plus losses; it is the reference for all bus angles.
- Single line-to-ground fault
- Fault current equals three times phase voltage divided by the sum of positive, negative, and zero sequence impedances plus three times the fault impedance.
- Sequence network connection
- Positive, negative, and zero sequence networks connect in series for a line-to-ground fault, in parallel for a line-to-line fault, and in series-parallel for a double line-to-ground fault.
- Voltage drop formula
- For a lagging load, per-phase voltage drop approximates current times resistance times cosine phi plus current times reactance times sine phi.
- Motor starting voltage dip
- The voltage dip at the motor terminals during starting equals the motor starting kVA divided by the sum of source short-circuit kVA and motor starting kVA.
- Coordination time interval
- The minimum time margin between the operating curves of a downstream and an upstream protective device, typically 0.2 to 0.4 seconds, to preserve selectivity.
- Arc-flash boundary
- The distance from live equipment at which incident energy equals 1.2 calories per square centimeter, the threshold for a second-degree burn without protective equipment.
- Cable derating factors
- Ampacity is corrected by multiplying ambient temperature, soil thermal resistivity, grouping, and depth factors. Factors are multiplicative, not additive, and apply to tabulated ratings.
- TN-S earthing system
- A system in which the neutral and protective earth are separate conductors from the source to the installation, so the protective conductor carries no load current.
- TT system protection
- A system with a local earth electrode at the installation. Earth-fault loop impedance is high, so residual current devices are required for fault disconnection.
- RCD sensitivity classes
- Thirty milliampere devices protect people against electric shock; three hundred milliampere devices protect against fire; type S devices are time-delayed for selectivity.
- Disconnection time TN
- For final circuits not exceeding 32 amperes in TN systems, the maximum disconnection time is 0.4 seconds; distribution circuits allow 5 seconds.
- Cable sizing inequality
- Design current must not exceed the protective device rating, which must not exceed the cable current-carrying capacity, after all derating factors are applied.
- Indirect contact condition
- Disconnection is achieved when the earth-fault loop impedance does not exceed the nominal line-to-neutral voltage divided by the current that trips the device within the required time.
- IP rating digits
- The first digit indicates solid-particle protection from zero to six; the second indicates water protection from zero to eight. IP54 is dust-protected and splash-proof.
- Insulation resistance test
- A 500 volt DC test on low-voltage circuits must give at least one megohm, with values recorded on the installation certificate before energization.
- Earned value indices
- Cost performance index equals earned value divided by actual cost; schedule performance index equals earned value divided by planned value. Values below one indicate overrun or delay.
- Total float definition
- The amount of time an activity can slip without delaying the project finish date. Activities with zero total float lie on the critical path.
- Risk response hierarchy
- Risks are addressed by avoidance, reduction, transfer, or acceptance. Residual risk after treatment must be documented and owned.
- Contract type risk
- Lump-sum contracts place quantity risk on the contractor; unit-price contracts place it on the owner; cost-plus contracts place cost risk on the owner.
- Hold point definition
- A stage in the inspection and test plan where work cannot proceed until the client or inspector has been notified and has released the hold.
- Resource leveling
- A scheduling technique that adjusts activity start and finish dates to resolve resource over-allocation, potentially extending the project finish date.
- Sealing engineering work
- Only the engineer who prepared or directly supervised the design may seal and sign it; sealing unreviewed work is a professional practice violation.
- Conflict of interest duty
- An engineer must disclose in writing any financial interest in a supplier, contractor, or specified product before providing a professional opinion.