Registered Environmental Protection Engineer flashcards
Registered Environmental Protection Engineer · Build recall with a focused review session.
37 cards. Read the term and the definition here. The deck at the top of this page is optional.
- 按日计罚
- China's Environmental Protection Law allows daily continuous fines for persistent violations; the penalty accrues each day the violation continues after a correction order, calculated from the original fine base.
- Pollutant discharge permit
- A legal document issued under the 2021 Regulations authorizing a facility to discharge specified pollutants at defined points, concentrations, and total quantities; it is the sole legal basis for discharge.
- Three simultaneous rule
- The 三同时 requirement that pollution control facilities be designed, constructed, and put into operation simultaneously with the main construction project, verified before commissioning.
- Hazardous waste manifest
- A mandatory transfer document (转移联单) tracking hazardous waste from generator through licensed transporter to disposal facility; records must be retained for at least five years.
- Drinking water source zones
- First-grade protection zones prohibit discharge and new construction; second-grade zones restrict discharge and require treatment, safeguarding drinking water intakes under the Water Pollution Prevention and Control Law.
- Sludge volume index
- SVI = (SV30 × 1000) / MLSS in mL/g; values of 80-150 indicate good settling, while values above 200 indicate filamentous bulking and poor sludge settleability.
- Food-to-microorganism ratio
- F/M = Q·S0 / (V·X), the mass of BOD5 applied per mass of MLSS per day; conventional activated sludge operates at 0.2-0.4 kg BOD5/(kg MLSS·d).
- Solids retention time
- SRT = (V·X) / (Qw·Xr + Qe·Xe); it controls nitrifier population and must exceed 10-15 days at 15 °C for reliable nitrification in A/O processes.
- Monod equation
- μ = μmax·S/(Ks + S) relates specific microbial growth rate to substrate concentration, where Ks is the half-saturation constant at which μ equals half of μmax.
- GB 18918 Class 1-A
- China's municipal wastewater discharge standard limits COD to 50 mg/L, BOD5 to 10 mg/L, SS to 10 mg/L, NH3-N to 5 mg/L, and TP to 0.5 mg/L.
- Deutsch-Anderson equation
- ESP collection efficiency η = 1 - exp(-A·ω/Q), where A is total plate area, ω is particle migration velocity, and Q is gas flow rate; efficiency rises with larger area and higher ω.
- Air-to-cloth ratio
- The ratio of gas volumetric flow to filter cloth area in a baghouse, typically 0.6-1.2 m/min for pulse-jet cleaning; higher ratios increase pressure drop and reduce bag life.
- SCR NOx reaction
- Selective catalytic reduction uses NH3 over V2O5/TiO2 at 300-400 °C: 4NO + 4NH3 + O2 → 4N2 + 6H2O, with a near 1:1 molar NH3 to NO ratio.
- Gaussian plume model
- Predicts downwind concentration C = Q/(2π·u·σy·σz)·exp(-y²/2σy²)·[exp(-(z-H)²/2σz²) + exp(-(z+H)²/2σz²)], with H as effective stack height.
- AQI emergency threshold
- Under HJ 633-2012, an Air Quality Index above 200 indicates heavy pollution and triggers mandatory emergency response measures such as production restrictions and traffic controls.
- Cyclone cut diameter
- The particle size collected with 50% efficiency; it decreases with smaller cyclone diameter and higher inlet velocity, improving fine particulate capture.
- 3T incineration principle
- Complete combustion requires Temperature (≥850 °C municipal, ≥1100 °C hazardous waste), Time (≥2 s residence), and Turbulence, plus adequate excess air.
- Dioxin emission limit
- GB 18484-2020 and GB 18485-2014 limit dioxin emissions from hazardous and municipal waste incinerators to 0.1 ng TEQ/Nm³ at 11% O2 reference conditions.
- Landfill composite liner
- A barrier system combining an HDPE geomembrane with compacted clay and a leachate collection layer, designed to limit contaminant migration from sanitary landfills.
- Composting C:N ratio
- Optimal composting requires a carbon-to-nitrogen ratio of 25-35:1, moisture of 50-60%, and thermophilic temperatures of 55-65 °C for pathogen destruction.
- Hazardous waste identification
- Determined by the National Hazardous Waste List (2021) or by GB 5085.1-GB 5085.7 tests for corrosivity, toxicity, flammability, reactivity, and infectivity.
- EIA classification catalogue
- China's 建设项目环境影响评价分类管理名录 assigns projects to report (报告书), form (报告表), or registration (登记表) categories based on potential environmental impact severity.
- Strategic environmental assessment
- Plan-level assessment (规划环境影响评价) required for industry, energy, water, transport, and urban plans; it precedes and informs project-level EIA decisions.
- Leopold matrix
- An impact identification tool that crosses project actions with environmental components; each cell is scored for magnitude and importance to reveal significant interactions.
- Public participation requirement
- Report-level EIA projects must conduct public participation under the 公众参与办法, including two public notices and solicitation of opinions from affected residents.
- Method detection limit
- MDL = t(n-1, 0.99) × S, calculated from the standard deviation of at least seven replicate low-level spikes; it is the minimum concentration distinguishable from zero.
- Sample preservation
- Metals samples are acidified to pH < 2 with HNO3; BOD must be analyzed within 24 h and COD within 48 h at 4 °C to prevent biodegradation and volatilization losses.
- Duplicate RPD
- Relative percent difference = |C1 - C2| / ((C1 + C2)/2) × 100%; acceptance is typically ≤ 20% for water and ≤ 30% for soil samples.
- Matrix spike recovery
- Percent recovery = (Cspiked - Cnative) / Cadded × 100%; acceptance windows are typically 75-125% depending on analyte, matrix, and method.
- Darcy's law
- Groundwater discharge Q = K·i·A, where K is hydraulic conductivity, i is hydraulic gradient, and A is cross-sectional area; it underpins contaminant transport and pump-and-treat design.
- Retardation factor
- R = 1 + (ρb/θ)·Kd; it quantifies how sorption slows contaminant migration relative to groundwater seepage velocity, with higher R meaning slower transport.
- GB 36600-2018
- China's soil environmental quality standard for construction land sets risk screening and intervention values, distinguishing first-class (residential, school) from second-class (industrial) land use.
- In-situ chemical oxidation
- ISCO injects oxidants such as permanganate or persulfate to destroy contaminants in place; design requires oxidant demand testing and consideration of rebound and byproduct formation.
- LAeq,T
- The equivalent continuous A-weighted sound level over period T: LAeq,T = 10·log10[(1/T)·∫10^(LA/10)dt], the standard metric for environmental noise assessment.
- Point source distance attenuation
- For a point source in free field, Lp2 = Lp1 - 20·log10(r2/r1), giving a 6 dB decrease per doubling of distance from the source.
- GB 3096-2008 limits
- Acoustic environment quality standard: Category 1 residential 55/45 dB(A), Category 2 mixed 60/50, Category 3 industrial 65/55, Category 4 traffic 70/55 for day/night.
- Sound level addition
- Incoherent levels add logarithmically: L_total = 10·log10(Σ10^(Li/10)); two equal sources add 3 dB and ten equal sources add 10 dB.