Registered Environmental Protection Engineer: Environmental Impact Assessment and Permitting

Registered Environmental Protection Engineer · Work through your exam, one topic at a time.

All guide sections

Environmental Impact Assessment and Permitting

What this domain tests

Classification of a project into 报告书, 报告表 or 登记表, the procedural steps that follow from that classification, and the separate permit obligation that survives approval of the EIA.

Classification

建设项目环境影响评价分类管理名录 (2021 version) sets the category from industry, scale, process, and whether the site lies in or near an environmentally sensitive area (nature reserves, drinking-water source protection zones, and similar). Sensitive location can escalate a 报告表 project to 报告书.

Procedure for a 报告书

  • Drafting: since the 2018 amendment to 环评法, the drafting entity no longer needs a qualification certificate, but it bears legal responsibility and is managed through the credit platform.
  • Public participation: first notice, notice of the draft for comment (at least 10 working days), and pre-submission notice; the report must explain how comments were adopted or rejected.
  • Approval: the authority issues a decision within the statutory period; the project may not start construction before approval.
  • 重大变动 in nature, scale, location or process requires a fresh EIA submission, not merely a permit amendment.
  • 三同时 and self-acceptance: the constructor organises acceptance, publishes the acceptance report, and may only then move to full operation; commissioning is the narrow exception.

Pollutant discharge permitting

排污许可管理条例 (2021-03-01) splits sources into 重点管理, 简化管理 and 登记管理. A permit fixes outfalls, permitted quantities, self-monitoring, records, and execution reports. Holding an approved EIA does not authorise discharge; the permit must be in hand first.

Worked example

A new electroplating line is proposed in an industrial park.

  1. The 名录 entry for electroplating, a heavy-metal industry, calls for a 报告书.
  2. The 报告书 must include public participation, a risk assessment for the plating chemicals, and a groundwater chapter, because the effluent carries heavy metals.
  3. The permit category is 重点管理, with self-monitoring of nickel and chromium at the outfall.
  4. Because 重金属 are involved, the permit must show that any total-quantity or 特别排放限值 condition from the EIA is met; the EIA condition is enforceable even if the general standard is looser.

Traps

  • Treating 登记表 as no EIA at all; it is a filing, still an obligation.
  • Believing EIA approval authorises operation or discharge.
  • Handling a 重大变动 by amending the permit only.
  • Skipping self-acceptance or publishing the acceptance report late.
  • Confusing plan-level EIA (规划环评) with project-level EIA.