What this domain tests

The risk-based logic of 土壤污染防治法, the difference between screening values and cleanup targets, and matching a contaminant and a geological setting to a remediation technology.

Regulatory framework

  • 土壤污染防治法 (2019-01-01) is risk-based: prevent first, then investigate, assess risk, and apply risk control or remediation. Farmland is split into priority protection, safe utilisation and strict control; construction land passes through suspected-site listing, investigation, risk assessment, control or remediation, and post-remediation assessment.
  • GB 36600-2018 gives screening values and control values separately for Category 1 land (residential, schools, medical, social welfare) and Category 2 land (industrial, commercial). Category 1 is stricter.
  • GB 15618-2018 covers agricultural land, banded by pH.
  • The HJ 25 series sets the sequence: investigation (25.1), monitoring (25.2), risk assessment (25.3), remediation plan (25.4), post-remediation assessment (25.5).

Remediation technologies

  • Soil: solidification and stabilisation for metals; soil vapour extraction for volatile organics in the vadose zone; thermal desorption; in-situ chemical oxidation with persulfate, permanganate or Fenton reagents; chemical reduction with zero-valent iron; bioremediation and biopiles; soil washing; phytoremediation; soil replacement.
  • Groundwater: pump-and-treat for plume containment; permeable reactive barriers for dissolved plumes; in-situ chemical oxidation; air sparging; monitored natural attenuation where the plume is stable.
  • Core concept: source, pathway, receptor. Break any one leg to remove the risk, and note that institutional controls can be a legitimate risk-control measure instead of excavation.

Worked example

A site planned for housing shows benzo[a]pyrene at 0.8 mg/kg. Category 1 screening value is 0.55 mg/kg and the control value is 5.5 mg/kg.

  1. 0.8 exceeds the screening value but stays below the control value.
  2. That combination triggers risk assessment, not automatic excavation. The assessment determines whether risk is acceptable for the planned residential use.
  3. If risk is unacceptable, the remediation target is derived from the risk assessment and may not exceed the control value.
  4. Had the result been above 5.5 mg/kg, remediation or a change of land use would be mandatory before residential use.

Traps

  • Treating the screening value as the cleanup target.
  • Mixing the two land categories; schools and hospitals are Category 1, not Category 2.
  • Siting a monitoring well upgradient of the source and concluding the site is clean.
  • Calling a single post-remediation sampling round an adequate effectiveness assessment.
  • Forgetting that a change of land use can be a valid alternative to remediation.