General Plumbing Knowledge and Safety

  • Static pressure conversion: 1 foot of water column = 0.433 psi; 1 psi = 2.31 feet of water column.

  • Drainage slope: 1/4 inch per foot for pipe 2-1/2 inches and smaller; 1/8 inch per foot for 3-inch and larger horizontal drainage pipe.

  • Fixture trap seal must be a minimum of 2 inches and a maximum of 4 inches of water depth.

  • Air gap = unobstructed vertical distance through free atmosphere between the lowest supply opening and the flood level rim; never less than 1 inch and at least twice the effective pipe opening.

  • Backflow occurs by backsiphonage (negative supply pressure) or backpressure; protection is by air gap, vacuum breaker, or testable backflow preventer.

  • Excavations 5 feet deep or more require a protective system (slope, shore, or shield); trenches 4 feet or deeper need a ladder within 25 feet of travel.

  • Confined space entry requires atmospheric testing: oxygen between 19.5% and 23.5%, and no flammable or toxic gas above exposure limits.

  • DWV water test: 10-foot head of water held for at least 15 minutes with no drop in level; an approved air test may be substituted where allowed.

Quick reference

Piping Systems, Materials, and Joints

  • Copper tube wall thickness: Type K heaviest (green), Type L intermediate (blue), Type M lightest (red); Type M is restricted in some underground and high-pressure uses.

  • Solder and flux for potable water must be lead-free, meaning not more than 0.2% lead, and labeled as such.

  • PVC is joined with PVC solvent cement plus listed primer (purple); CPVC requires cement and primer listed for CPVC and is rated for hot water distribution.

  • PEX is joined only with mechanical insert fittings (copper crimp rings, stainless clamp rings, or compression) and must be protected from sunlight and freezing.

  • A dielectric union or dielectric nipple is installed between copper and steel or galvanized pipe to break the electrical path and prevent galvanic corrosion.

  • Support spacing: copper 1-1/4 inch and smaller every 6 feet, 1-1/2 inch and larger every 10 feet; PVC 1/2 to 1 inch every 3 feet, 1-1/4 to 2 inch every 4 feet.

  • Hubless cast iron soil pipe is joined with a neoprene gasket sleeve compressed by a stainless steel band clamp (no-hub coupling).

  • Buried pressure pipe needs thrust blocks at bends, tees, and reducers, or restrained joints, to resist the thrust of flowing water.

  • Minimum sizes: building water service 3/4 inch; fixture supply tube 3/8 inch; building drain 3 inch where the code permits.

Quick reference

Fixtures, Appliances, and Water Heaters

  • Temperature and pressure relief valve opens at 210 degrees F or 150 psi, whichever occurs first, and must be rated to match the heater's input.

  • T&P discharge must be full size, gravity-flow, without valves or traps, terminate unthreaded no more than 6 inches above the floor or outside above grade.

  • A water heater in a closed system (check valve, pressure-reducing valve, or backflow preventer) requires an expansion tank or other approved thermal expansion control.

  • Gas-fired water heaters must be listed as flammable vapor ignition resistant (FVIR) with a sealed burner compartment and flame arrestor.

  • A sediment trap (drip leg) is required on the gas line at each appliance, downstream of the appliance shutoff valve and as close as practical to the inlet.

  • Minimum flowing pressure: 8 psi at a fixture outlet; 15 psi for flushometer (flush valve) water closets and urinals.

  • Water closet clearance: at least 15 inches from bowl centerline to any sidewall and at least 21 inches of clear space in front of the bowl.

  • Shower control valves must be pressure-balancing or thermostatic mixing type to limit temperature swings and reduce scald risk.

  • Dishwasher discharge must connect through an air gap or air break; floor drains subject to evaporation need an approved trap primer.

Quick reference

Colorado Plumbing Code, Permits, and Inspection

  • A permit is required before installing, altering, or replacing plumbing piping, fixtures, or water heaters, subject to the exemptions listed in the code.

  • Rough-in inspection is requested after DWV and water piping are installed and tested, and must occur before the work is covered or concealed.

  • Final inspection is requested after fixtures are set, appliances are connected, and the system has been tested and is ready for use.

  • Colorado adopts the International Plumbing Code with state amendments as the Colorado Plumbing Code, administered through the State Plumbing Board.

  • Testing before inspection: drainage and vent piping with a 10-foot head of water for at least 15 minutes; building sewer tested separately.

  • The State Plumbing Board, within the Department of Regulatory Agencies, licenses master, journeyman, and residential plumbers.

  • A master plumber is the licensee authorized to contract for plumbing work, take out permits, and supervise journeymen and apprentices.

  • Work concealed before inspection may be ordered exposed by the code official so that it can be examined and tested.

  • The code official may approve materials or methods not specifically named in the code when evidence shows they are equivalent in quality, strength, and safety.