CSI CCCA study materials
CSI CCCA study resources

CSI CCCA cheat sheet

CSI CCCA · Keep the key ideas within reach.

Quick reference

Quality Assurance / Quality Control

  • QA = process-oriented (procedures, submittals, testing plans); QC = product-oriented (inspection, sampling, testing to verify compliance). CSI defines QA as actions by the owner/designer and QC as contractor actions.

  • Three-point control: preparatory (before work), initial (first work in place), and follow-up (ongoing) phases; each phase includes a meeting, a checklist, and documented sign-off.

  • Testing frequency is governed by the specification's sampling rate (e.g., one test per 500 sq ft or per lot); failed tests trigger retesting at contractor cost unless the specification states otherwise.

  • Statistical acceptance uses a defined lot, sample size, and acceptance number; a lot is accepted when the number of defects is at or below the acceptance number.

  • Total Quality Management (TQM) principles: customer focus, continuous improvement (Plan-Do-Check-Act), fact-based decisions, and workforce involvement.

  • A nonconformance report (NCR) records the deficiency, location, specification reference, disposition (rework, repair, use-as-is, reject), and closure verification.

  • A root cause analysis tool: 5 Whys and fishbone (Ishikawa) diagrams separate cause categories into man, machine, material, method, measurement, and environment.

  • Quality costs: prevention + appraisal = cost of conformance; internal + external failure = cost of nonconformance. Prevention spending typically yields the highest return.

Quick reference

Bidding and Negotiating Procedures

  • Bid opening: bids are publicly opened and read aloud at the time and place stated in the advertisement; late bids are returned unopened. Bid security is checked for form and amount at opening.

  • Competitive sealed bidding requires adequate competition, a firm fixed price basis, and award to the lowest responsive and responsible bidder without negotiation.

  • Responsiveness = compliance with material solicitation requirements (bid form, security, addenda acknowledgment). Responsibility = capacity, integrity, and past performance.

  • Negotiated procurement is used when sealed bidding is impractical: sole source, urgency, or when price and technical factors must be traded off. Discussions must be held with all competitive range offerors.

  • Bid shopping and bid peddling are prohibited; disclosure of one bidder's price to another to obtain a lower price is an ethics violation.

  • Addenda: issued to all plan holders in writing; bidders must acknowledge each addendum on the bid form. An addendum that materially changes scope may extend the bid period.

  • Two-envelope (technical/price) evaluation separates technical qualification from price; technical envelopes are scored before price envelopes are opened.

  • Bid protest grounds commonly include defective specifications, improper evaluation, and failure to follow stated award criteria; deadlines are short and strictly enforced.

Quick reference

Observation and Inspection

  • Observation is passive watching for conformance; inspection is an active, documented verification against a specified criterion. Neither transfers responsibility for means and methods from the contractor.

  • Inspection levels: 100% inspection, sampling inspection, and first-article inspection. Sampling risk is covered by the operating characteristic (OC) curve.

  • The contractor's quality control plan defines hold points (work cannot proceed without inspector sign-off) and witness points (notification required, work may proceed).

  • A punch list (deficiency list) is issued at substantial completion; items are corrected before final completion and final payment. Substantial completion starts warranty and time-related provisions.

  • Documentation elements: date, time, location, personnel present, work observed, specification reference, and photographic record. Notes are contemporaneous and factual, not conclusory.

  • The three phases of field inspection: preparatory meeting and submittal review, initial inspection of first work, and follow-up inspections at defined frequency.

  • Testing must be performed by an approved independent agency when specified; the contractor typically schedules and pays for testing but the owner may retain the agency directly.

  • Defective work discovered after acceptance does not relieve the contractor of latent defect liability; the warranty or correction period governs the remedy.

Quick reference

Division 01 - General Requirements

  • Division 01 governs the administrative and procedural requirements for all technical sections; where Division 01 conflicts with a technical section, the more stringent or specific requirement governs as stated in the supplementary conditions.

  • Submittal types: shop drawings, product data, samples, mockups, and sustainable design reports. Each is marked approved, approved as noted, revise and resubmit, or rejected.

  • Submittal review is for conformance with the design concept only; contractor remains responsible for dimensions, quantities, and field fit. A 'no exception taken' action does not waive contract requirements.

  • Unit prices and alternates: alternates are accepted in the order listed in the bid form; unit prices apply to changes in quantity and are priced at the bid unit price.

  • Substitution requests must be submitted within the time stated (often 10 days after award) with data showing equivalence; the designer's decision is final and does not create a basis for claim.

  • Closeout submittals: record documents (as-builts), warranty and O&M manuals, attic stock, spare parts, and final cleaning; final payment is contingent on their acceptance.

  • Construction schedules: baseline schedule is submitted for approval within a stated period after notice to proceed; time extensions require written notice within the contract notice period.

  • Allowances and contingency: cash allowances are part of the contract sum and adjusted by change order; owner contingency is not part of the contract sum.

Quick reference

General and Supplemental Conditions

  • Order of precedence (typical AIA A201): agreement, general conditions, supplementary conditions, drawings, specifications, addenda, then other documents. Modifications take precedence over the original documents.

  • Differing site conditions: Type I (subsurface or latent physical conditions materially different from those indicated) and Type II (unknown physical conditions of an unusual nature). Notice is required before disturbing the condition.

  • Suspension and time extensions: contractor is entitled to an extension of time, not additional cost, for excusable but non-compensable delays (weather, owner-caused without cost).

  • Owner's right to stop work and to correct defective work: the owner may withhold payment for deficient work and may perform correction after notice if the contractor fails to act.

  • Claims and disputes: initial decision by the architect/owner, mediation, then arbitration or litigation per the dispute resolution clause; notice of claim deadlines are conditions precedent.

  • Indemnification and insurance: contractor indemnifies for its negligence; additional insured status and waiver of subrogation are common requirements. Limits are stated in the supplementary conditions.

  • Retainage: a percentage (commonly 5-10%) withheld from each payment; many jurisdictions require reduction to a lower rate at substantial completion.

  • Hazardous materials discovered on site are typically the owner's responsibility; contractor must stop work in the affected area and notify the owner in writing.

Quick reference

Agreements and Project Documents

  • AIA A101 (fixed price), A102 (cost plus), A103 (cost plus with GMP), B101 (owner-architect), A201 (general conditions), A701 (instructions to bidders), and A305 (contractor qualification statement) are the core document family.

  • Contract types: lump sum (fixed price), unit price (measured quantities), cost plus fixed fee, cost plus percentage (discouraged), and GMP with shared savings.

  • A GMP contract sets a guaranteed maximum price; savings below GMP are shared per a stated ratio; costs above GMP are the contractor's risk unless caused by owner changes.

  • Change order (CO) modifies the contract sum or time and is signed by owner and contractor; a construction change directive (CCD) directs work before price agreement and is later converted to a CO.

  • The agreement states the contract sum, date of commencement, contract time, liquidated damages rate, and lists the contract documents by name and date.

  • Bonds: bid bond (5-10% of bid), performance bond (100% of contract sum), and payment bond (100%) protect the owner and subcontractors respectively.

  • Notice to proceed establishes the start of the contract time; the date of substantial completion triggers warranty, retainage reduction, and liquidated damages cutoff.

  • Liquidated damages are a pre-estimated sum per day for late completion and must be a reasonable forecast of actual damages to be enforceable as a penalty.