EXIN Dynamic Project Management Method Foundation study materials
EXIN Dynamic Project Management Method Foundation study resources

EXIN Dynamic Project Management Method Foundation cheat sheet

EXIN Dynamic Project Management Method Foundation · Keep the key ideas within reach.

Quick reference

Project Goals

  • A project goal states the intended end result (output and outcome), while a project result is the tangible deliverable that contributes to it.

  • The project objective is expressed in scope, time, cost and quality; these four are the classic constraints that DPMM treats as interdependent.

  • A goal must be justified by a business case: the expected benefits must outweigh the estimated costs and risks.

  • SMART is the standard test for goal formulation: Specific, Measurable, Acceptable, Realistic, Time-bound.

  • Output is what the project delivers; outcome (effect) is the change the output produces in the user organization, usually realized after handover.

  • Project success is judged on three levels: result (did we deliver), goal (did the effect occur) and process (did we work effectively).

  • Scope creep is uncontrolled growth of deliverables; it is detected by comparing baseline scope with requested changes.

  • If the client cannot state a measurable goal, the project manager records it as an assumption and escalates it as a decision point before planning is baselined.

Quick reference

Project Context

  • The project context covers stakeholders, the parent organization, the environment (market, law, technology) and the project's own history.

  • A stakeholder is anyone who can affect or is affected by the project; DPMM distinguishes internal (team, sponsor) from external (client, supplier, regulator).

  • The sponsor (client/principal) owns the business case and approves the project mandate; the project manager owns the delivery.

  • A project exists inside a permanent organization; the project organization is temporary and dissolves at handover.

  • Environmental factors (PEST: political, economic, social, technological) can invalidate the business case and must be reassessed at phase boundaries.

  • The business case is a living document: review it at each decision point, not only at the start.

  • A program is a set of related projects steered for shared benefit; a portfolio is the total set of investments of the organization.

  • Context analysis output feeds the risk register and the stakeholder list, so both are updated whenever the context changes.

Quick reference

DPMM® Principles

  • DPMM is process- and people-oriented: it prescribes what to decide and when, not a rigid sequence of technical steps.

  • Principles apply at any scale; the method is tailorable, so a small project can use a lighter set of products and roles.

  • Decision points are mandatory: the project may not pass a phase boundary without an explicit go/no-go decision by the authorized role.

  • Roles and responsibilities are separated from persons; one person may hold several roles in a small project, but accountability must be explicit.

  • The method is result-driven: every activity must be traceable to a product or decision that adds value.

  • Working agreements and transparency are principles, not optional extras: information is shared with those entitled to it.

  • Continuous improvement (plan-do-check-act) applies to the method itself: evaluate the process at the end of each phase.

  • Deviation is managed by exception: report only when tolerances are exceeded, so management attention stays focused.

Quick reference

Agility

  • Agility is the ability to respond to change while keeping the goal in view; it is a mindset supported by short cycles, not a synonym for Scrum.

  • Iterative delivery produces increments; each increment is inspected and adapted, so feedback replaces prediction where uncertainty is high.

  • Empirical control rests on three pillars: transparency, inspection and adaptation.

  • A timebox is a fixed maximum duration; if the work is not finished, scope is reduced, not the timebox extended.

  • Agile and plan-driven approaches are a continuum; DPMM allows hybrid tailoring, e.g. phase-based governance with iterative execution.

  • Self-organizing teams decide how to do the work; the project manager guards the boundary and removes impediments.

  • Value is delivered early and incrementally; prioritize backlog items by business value and risk, not by ease.

  • Retrospectives close each cycle: identify what to keep, what to change, and assign a concrete action with an owner.

Quick reference

Organization

  • Core DPMM roles: client/sponsor, project manager, team members, and where applicable a steering group and quality assurance.

  • The steering group (project board) takes decisions at decision points and is accountable for the business case.

  • The project manager is accountable for the project result, the plan, progress reporting and issue and risk management.

  • The team member is accountable for delivering the assigned products to the agreed quality within the agreed time.

  • Quality assurance is independent of the project manager; it checks that the method and agreements are followed.

  • A RACI matrix maps roles to activities: exactly one Accountable per activity, at least one Responsible, and Consulted/Informed as needed.

  • Line management supplies people and maintains the permanent competencies; the project borrows capacity for a limited period.

  • Escalation path: team member to project manager, project manager to steering group; escalation occurs when tolerances are threatened.

Quick reference

Planning

  • Plan hierarchically: project plan (phases, decision points, products) then phase plan, then detailed activity or sprint plan.

  • Product breakdown first, activity planning second: define what must be delivered, then how.

  • A milestone has zero duration and marks a verifiable state or decision point; it is not an activity.

  • Critical path is the longest chain of dependent activities; its length equals the shortest possible project duration, and slack on it is zero.

  • Estimate with at least one technique (analogy, expert judgment, three-point/PERT, or parametric); document the basis of the estimate.

  • PERT expected duration = (optimistic + 4 x most likely + pessimistic) / 6.

  • Rolling-wave planning: detail is planned only for the near phase; later phases stay at a coarse level until more is known.

  • The baseline is the approved plan; changes to it go through change control, and actual-versus-baseline variance is reported.

Quick reference

Quality Management

  • Quality is fitness for purpose as defined by agreed requirements, not the highest possible specification.

  • Quality assurance is process-oriented and preventive; quality control is product-oriented and detective (tests, reviews, inspections).

  • The quality plan names each product, its quality criteria, the review technique and the responsible role.

  • Review types by formality: peer review, walkthrough, technical review, formal inspection; formality rises with product risk.

  • A review is only effective if the reviewer is independent of the author and works against explicit criteria.

  • Cost of quality = prevention + appraisal + internal failure + external failure; external failure is the most expensive category.

  • Definition of Done: a product is complete only when it meets its agreed criteria and is accepted by the authorized role.

  • Quality findings are recorded as issues and closed only after verification; unverified fixes count as open.

Quick reference

Issue Management

  • An issue is a problem that has already occurred and needs action now; a risk is an uncertain future event.

  • Issue log fields: identifier, description, raised by, date, owner, priority, action, status, closure date.

  • Priority is set by impact on goal, time, cost and quality, not by who raised the issue.

  • Every issue has exactly one owner and a target resolution date; unowned issues stay open indefinitely.

  • Escalate an issue to the steering group when resolving it exceeds the project manager's mandate or tolerances.

  • Change requests are a category of issue: assess impact on scope, time, cost and risk before approval.

  • Close an issue only after the resolution is verified and affected stakeholders are informed.

  • Trend analysis of the issue log (count and category over time) is a leading indicator of quality problems.

Quick reference

Risk Management

  • Risk = probability x impact (qualitative score); expected monetary value = probability x monetary impact (quantitative).

  • Risk process: identify, analyze, plan response, implement, monitor and control; repeat it at every phase boundary.

  • Response strategies for threats: avoid, transfer, mitigate, accept; for opportunities: exploit, share, enhance, accept.

  • A risk owner is accountable for the response; a risk actionee executes it. Both are named in the risk log.

  • Residual risk remains after the response; secondary risk is created by the response itself. Both must be logged.

  • Risk appetite is the willingness to accept risk; risk tolerance is the measurable deviation allowed before escalation.

  • Risk triggers (early warning indicators) are defined in advance so the response can start before the risk occurs.

  • A risk becomes an issue when it materializes; it then moves to the issue log and is managed there.

Quick reference

DPMM® Processes

  • Phases run: initiation, definition/planning, execution, closure; each boundary is a decision point with a go/no-go.

  • Initiation output: project mandate, business case, global project plan and the project organization.

  • Definition output: detailed phase plan, product specifications, quality plan, risk and issue logs, stakeholder analysis.

  • Execution is steered by progress reports against the baseline; exceptions are reported only when tolerances are exceeded.

  • Closure includes product acceptance by the client, a final report, lessons learned and release of resources.

  • Each process has defined inputs, activities, outputs and the role accountable for the output.

  • Products are the backbone: a process is complete when its required products exist, are reviewed and are approved.

  • Tailoring is itself a documented process step: record which products and roles are combined or omitted and why.