EXIN Dynamic Project Management Method Foundation flashcards
EXIN Dynamic Project Management Method Foundation · Build recall with a focused review session.
35 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Project goal
- The measurable intended effect of the project in the user organization, justified by the business case and distinct from the deliverables that produce it.
- Project result vs goal
- The result is the deliverable the project hands over; the goal is the effect that deliverable creates after it is put into use.
- SMART goal test
- A criterion requiring goals to be Specific, Measurable, Acceptable, Realistic and Time-bound so that achievement can be verified objectively.
- Scope creep
- Uncontrolled accumulation of small unapproved additions to deliverables, detected by comparing requested work with the approved baseline scope.
- Business case
- The documented justification of the project in terms of expected benefits against costs and risks; the sponsor owns it and it is reviewed at decision points.
- Project mandate
- The formal authorization to start the project, naming the goal, the sponsor and the project manager and releasing initial resources.
- Stakeholder analysis
- Identifying everyone affected by or able to affect the project and assessing their interest and influence to plan engagement.
- Program versus portfolio
- A program groups related projects steered for shared benefit; a portfolio is the organization's complete set of projects and programs.
- Decision point
- A mandatory go/no-go moment at a phase boundary where the authorized role judges results, business case and risks before releasing the next phase.
- Management by exception
- Reporting upward only when agreed tolerances are exceeded, so steering attention is spent on real deviations rather than routine progress.
- Tailoring the method
- Adapting which products, roles and decision points are applied to a project's size and risk, with the choices documented and justified.
- Role versus person
- Roles carry defined accountabilities independent of who fills them; one person may hold several roles but accountability stays explicit.
- Empirical control pillars
- Transparency, inspection and adaptation: the three conditions that let a team steer by observed results instead of by prediction alone.
- Timebox
- A fixed maximum duration for a cycle; if work remains unfinished, scope is reduced rather than the timebox being extended.
- Increment
- A potentially usable addition to the product produced within one cycle, inspected by stakeholders so feedback can steer the next cycle.
- Hybrid delivery
- Combining phase-based governance and decision points with iterative execution, a tailoring option DPMM permits where uncertainty is uneven.
- Steering group
- The decision-making body of the project, accountable for the business case, that takes go/no-go decisions and resolves escalated issues.
- RACI matrix
- A chart assigning Responsible, Accountable, Consulted and Informed status per activity, with exactly one accountable role per activity.
- Quality assurance role
- An independent function checking that the project follows agreed method, standards and procedures; it reports outside the project manager's line.
- Escalation path
- The defined route for raising decisions upward, typically team member to project manager to steering group, triggered when tolerances are threatened.
- Product breakdown
- Decomposing the project result into deliverable components before planning activities, so that planning follows what must be produced.
- Milestone
- A zero-duration marker of a verifiable state or decision, used to track progress; it consumes no effort and has no duration.
- Critical path
- The longest chain of dependent activities through the network; its length sets the minimum project duration and it carries zero slack.
- PERT estimate
- Expected duration computed as (optimistic + 4 x most likely + pessimistic) divided by six, weighting the most likely value most heavily.
- Rolling-wave planning
- Planning near-term work in detail while leaving later phases coarse until more information is available at the next decision point.
- Quality assurance vs control
- Assurance is preventive and process-focused; control is detective and product-focused through tests, reviews and inspections.
- Definition of Done
- The agreed criteria a product must satisfy, and the acceptance it must receive, before it counts as complete rather than in progress.
- Formal inspection
- The most formal review type, with defined roles, entry criteria, recorded findings and follow-up verification, used for high-risk products.
- Cost of quality
- The sum of prevention, appraisal, internal failure and external failure costs; external failure is usually the most expensive category.
- Issue versus risk
- An issue is a problem that has already occurred and needs action now; a risk is an uncertain future event that may or may not occur.
- Issue log fields
- Identifier, description, raiser, date, owner, priority, planned action, status and closure date, forming the record of all open problems.
- Risk response strategies
- For threats: avoid, transfer, mitigate, accept. For opportunities: exploit, share, enhance, accept. Each response names an owner.
- Residual and secondary risk
- Residual risk remains after a response is applied; secondary risk is a new risk created by the response itself. Both stay in the risk log.
- Risk appetite versus tolerance
- Appetite is the willingness to accept risk in pursuit of benefit; tolerance is the measurable deviation allowed before escalation is required.
- Project closure process
- Acceptance of products by the client, final report, lessons learned and release of people and resources, ending the temporary organization.