EPI Data Centre Foundation study materials
EPI Data Centre Foundation study resources

EPI Data Centre Foundation study plan

EPI Data Centre Foundation · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Data Centre Design and Infrastructure

  • Map the power path from utility entry through MV switchgear, transformer, UPS and PDU to the rack, and label every conversion and redundancy point on a one-page diagram

  • Distinguish N, N+1, 2N and 2(N+1) topologies and state the failure each tolerates and the capacity cost each imposes

  • Explain UPS types (static double-conversion, line-interactive, rotary) and match each to a load profile with justification

  • Calculate runtime for a given load and battery bank using a simple derating method, and state the assumptions behind the result

Your checkpoint

A one-page annotated power single-line diagram plus a 300-word note comparing N+1 and 2N for a 500 kW hall, including cost and availability trade-offs

Week 2

Data Centre Design and Infrastructure

  • Describe air-cooled and liquid-cooled heat rejection paths and identify where each becomes the practical choice by rack density

  • Compute sensible heat load from IT load, lighting, people and envelope gains, and size cooling capacity from that total

  • Compare containment strategies (hot aisle, cold aisle, full, partial) by their effect on supply air temperature and mixing

  • Explain psychrometric limits in the ASHRAE recommended and allowable envelopes and the risk of running outside them

  • Identify fire detection and suppression approaches for white space and the interaction with airflow and egress

Your checkpoint

A cooling load calculation for a 200 kW hall with a containment recommendation and a psychrometric justification of the chosen setpoints

Week 3

Data Centre Design and Infrastructure & Data Centre Operations and Maintenance

  • Specify redundancy and diversity requirements for dual-corded IT loads, including which single points of failure remain after full A/B distribution

  • Draft a preventive maintenance calendar for UPS, generators, chillers and switchgear, giving interval, task and owner for each item

  • Explain generator testing under load, fuel quality management and the failure modes that appear only during a real transfer

  • Describe battery monitoring and the end-of-life indicators that trigger replacement before capacity falls below design

Your checkpoint

A 12-month preventive maintenance schedule covering four major plant items, with acceptance criteria for each task

Week 4

Data Centre Operations and Maintenance

  • Write change management steps for a live electrical or cooling intervention, including risk assessment, method statement and rollback

  • Define permit-to-work and lockout/tagout controls and the point at which they apply in a data centre

  • Distinguish incident, problem and change processes and assign severity levels with response targets

  • Explain how to run a failover test without breaching the service level, including pre-checks and abort criteria

Your checkpoint

A method statement and risk assessment for replacing one UPS module in a live 2N hall, with abort criteria and rollback steps

Week 5

Data Centre Standards, Compliance and Audit

  • Map the scope of the ANSI/TIA-942, ISO/IEC 22237, EN 50600 and Uptime Institute tier frameworks, and state what each certifies and what it does not

  • Compare the four tier topologies by fault tolerance and concurrent maintainability, and identify which claims require a specific configuration

  • Interpret the intent of key clauses on redundancy, physical security and documentation without quoting them

  • Explain the audit evidence types that satisfy an assessor: design documents, commissioning records, test logs and live observations

Your checkpoint

A comparison table of four standards frameworks against twelve criteria including redundancy, maintainability, security and certification route

Week 6

Data Centre Standards, Compliance and Audit & Data Centre Governance, Risk and Professional Competence

  • Assemble a documentation set that would survive a design review: single-line diagrams, floor plans, commissioning scripts and as-built records

  • Plan a commissioning sequence from factory acceptance through site acceptance to integrated systems test, and state the pass criteria for each stage

  • Explain how to prepare for a tier or certification audit, including evidence gaps that commonly cause findings

  • Identify the record-keeping needed for maintenance, training and change history to support an audit trail

Your checkpoint

A commissioning and audit-readiness checklist of at least 25 evidence items mapped to the lifecycle stage that produces them

Week 7

Data Centre Governance, Risk and Professional Competence

  • Build a risk register for a data centre covering power, cooling, security, people and supplier dependencies, scoring likelihood and impact

  • Explain business impact analysis and how recovery time and recovery point objectives drive infrastructure design

  • Describe the governance roles and the separation between the operator, the owner and the auditor, and why independence matters

  • Outline competence requirements for authorised persons, including training, assessment and re-authorisation cycles

  • Explain how to report risk to senior management in business terms rather than technical ones

Your checkpoint

A ten-item risk register with scored likelihood and impact, plus a one-page briefing note translating the top three risks into business consequences

Week 8

Data Centre Design and Infrastructure & Data Centre Operations and Maintenance & Data Centre Standards, Compliance and Audit & Data Centre Governance, Risk and Professional Competence

  • Consolidate weak areas by re-testing the two domains with the lowest practice scores and logging every missed concept

  • Rehearse calculations under time pressure: runtime, cooling load, redundancy cost and availability

  • Practise explaining a standard's scope and an audit finding in plain language, as required by scenario questions

  • Review the risk register and maintenance schedule against each other to confirm controls map to identified risks

Your checkpoint

A one-page personal weak-area sheet listing every missed concept with a corrected one-line definition, plus a timed 40-question mock scored and reviewed

Milestones

Week 2: Can draw the power path and the cooling path from memory, and compute runtime and cooling load without notes, scoring at least 80% on a self-made 20-question set covering domain 1

Week 4: Can write a method statement for a live intervention and list the permits and controls required, and has completed a full pass over domains 1 and 2 with logged weak areas

Week 6: Can state the scope and limits of four standards frameworks and produce an audit evidence list from memory, with domain 3 practice scores at or above 75%

Week 8: Timed mock of 40 questions across all four domains scored at or above 80%, with every missed item converted into a corrected one-line definition