FE Industrial & Systems flashcards
FE Industrial & Systems · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Central Limit Theorem
- For independent samples of size n ≥ 30, the sample mean is approximately normally distributed with mean μ and standard error σ/√n, regardless of the population's shape.
- Poisson distribution
- Models counts of rare events in a fixed interval when events are independent, with P(X = k) = e^(−λ)·λ^k/k!; the mean and variance both equal λ.
- Coefficient of determination
- R², the proportion of total variation in the response explained by the regression model; it equals SSR/SST and ranges from 0 to 1.
- Type I error
- Rejecting a true null hypothesis, which occurs with probability α, the significance level; it corresponds to producer's risk in acceptance sampling.
- Capital recovery factor
- (A/P, i, n) = i(1+i)^n/[(1+i)^n − 1]; it converts a present sum into an equivalent uniform annual series over n periods at rate i.
- Internal rate of return
- The interest rate that makes a project's net present worth equal zero; the project is acceptable when the IRR is at least the MARR.
- Straight-line depreciation
- Annual depreciation equals (first cost − salvage value)/useful life, so book value decreases by a constant amount each year of the asset's life.
- Public welfare paramount
- The fundamental canon of engineering ethics: engineers shall hold the safety, health, and welfare of the public paramount in all professional activities.
- Conflict of interest
- A circumstance in which professional judgment could be swayed by personal gain; engineers must disclose it and avoid serving two parties on the same matter.
- Seal and signature
- Engineers may seal or sign only documents prepared by them or under their direct supervisory control, never work they have not reviewed.
- Little's Law
- Work-in-process equals throughput multiplied by flow time; it holds for any steady-state system, so reducing flow time lowers WIP at constant throughput.
- Overall equipment effectiveness
- OEE = availability × performance × quality, where each factor is the actual value divided by the ideal value; world-class performance is often cited near 85%.
- Takt time
- Available production time divided by customer demand over the same period; it sets the pace a line must meet to satisfy demand exactly.
- Economic order quantity
- EOQ = √(2DS/H), the order size that minimizes the sum of ordering and holding costs; at the optimum the two cost components are equal.
- Reorder point
- The inventory level at which a replenishment order is placed: demand rate times lead time, plus safety stock when demand or lead time is uncertain.
- Johnson's rule
- A sequencing rule minimizing makespan for jobs run through two machines in the same order: take the shortest time, schedule early if on machine one, late if on machine two.
- Systematic Layout Planning
- Muther's procedure: analyze flow and activity relationships, build a relationship diagram, determine space requirements, then generate and evaluate block layouts.
- Line balancing cycle time
- Available time per period divided by required output; no workstation may be assigned a combination of tasks whose total time exceeds this cycle time.
- Center-of-gravity method
- A facility location technique weighting each existing site by its volume: x* = Σwᵢxᵢ/Σwᵢ, with y* computed the same way.
- NIOSH lifting equation
- Recommended weight limit = LC × HM × VM × DM × AM × FM × CM; the lifting index is the load divided by the RWL, and values above 1 signal increased risk.
- Fitts' law
- Movement time to a target follows MT = a + b·log₂(2D/W), so larger targets and shorter distances produce faster and more accurate pointing.
- Anthropometric percentile design
- Design to the 5th percentile where reach is the limiting factor and to the 95th percentile where clearance is limiting, so most users are accommodated.
- Process capability index Cpk
- Cpk = min[(USL − μ)/3σ, (μ − LSL)/3σ]; it accounts for process centering and should reach at least 1.33 for a capable process.
- Taguchi loss function
- L(x) = k(x − T)², expressing that any deviation from the target value T incurs a cost that grows quadratically with the size of the deviation.
- Average outgoing quality limit
- The maximum average fraction nonconforming that leaves inspection, taken over all possible incoming quality levels, for a given sampling plan.
- M/M/1 queue length
- For one server with Poisson arrivals and exponential service, L = ρ/(1−ρ) and Lq = ρ²/(1−ρ), where utilization ρ = λ/μ.
- Shadow price
- The marginal change in the optimal objective value per unit increase in a constraint's right-hand side; it is zero when the constraint has slack.
- Critical path
- The longest path through the project network; its length determines the project duration, and activities on it have zero total slack.
- Expected value of perfect information
- The expected payoff with perfect information minus the best expected monetary value without it; the maximum a decision maker should pay for that information.
- Earned value cost performance index
- CPI = earned value / actual cost; a value below 1 means the project has spent more money than the value of work completed.
- Series system reliability
- For independent components arranged in series, R = R₁ × R₂ × … × Rₙ, so system reliability is always lower than the weakest single component.
- Functional baseline
- The approved requirements and performance specification established at the end of concept development; changes to it require formal configuration control.