FE Industrial & Systems: Production Planning and Control

FE Industrial & Systems · Work through your exam, one topic at a time.

All guide sections

Production Planning and Control

What to master

Follow the planning hierarchy: demand forecasting, aggregate planning (level, chase, mixed), master production schedule, material requirements planning (BOM explosion, gross-to-net, lot sizing, lead-time offsetting), capacity requirements planning, then shop-floor scheduling and control. Know forecasting accuracy measures (MAD, MSE, MAPE, tracking signal), moving averages, and exponential smoothing (F_next = alpha x A_actual + (1 - alpha) x F_current; a higher alpha tracks change faster). For inventory, know EOQ = sqrt(2DS/H), reorder point with safety stock, quantity-discount logic, and ABC classification. For scheduling, know SPT (minimizes average flow time), EDD (minimizes maximum lateness), Johnson's rule for two machines, and Gantt/priority rules.

Traps

  • Applying EOQ where demand is lumpy or price breaks apply.
  • Netting errors in MRP: net requirement = gross - on hand - scheduled receipts, then rounded to the lot size.
  • Omitting safety stock: ROP = d-bar x L + z x sigma_L.
  • Confusing forward with backward scheduling.
  • Mixing holding cost units (dollars per unit-year vs percent of unit cost).
  • Believing SPT optimizes due-date performance - it does not.

Worked example

Annual demand 12,000 units, order cost $50, holding cost $3 per unit-year: EOQ = sqrt(2 x 12,000 x 50 / 3) = sqrt(400,000) = 632 units.

Rule of thumb

For two-machine sequencing, find the smallest time in the table; if it is on machine 1, schedule that job earliest; if on machine 2, schedule it latest. Repeat.