Scheduling Fundamentals, Terminology, and Standards

  • A schedule is a project model of activities, logic, durations, and dates; a schedule model plus the reporting/use process constitutes the project schedule.

  • AACE International Recommended Practice 29R-03 defines schedule classifications by maturity; the CAPES exam references the AACE 29R-03 schedule classification framework for schedule development maturity.

  • AACE International Recommended Practice 29R-03 defines schedule classifications by maturity; the CAPES exam references the AACE 29R-03 schedule classification framework for schedule development maturity.

  • Activity: a discrete, measurable unit of work with defined start and finish; an event/milestone has zero duration and marks a point in time.

  • Mandatory constraint (e.g., Must Finish On, Must Start On) overrides logic and can create negative float; soft constraints (Start No Earlier Than, Finish No Later Than) restrict without breaking logic.

  • Open end: an activity lacking a predecessor or successor; dangling logic reduces schedule quality and is flagged in DCMA-style checks.

  • Lags add wait time between activities; leads overlap them. Both are logic links in CPM and must be justified and minimized.

  • Float (total float) = late finish - early finish = late start - early start; free float = early start of successor - early finish of activity.

  • The critical path is the longest path through the network; its total float equals zero (or the minimum value if negative float exists).

Quick reference

Schedule Development and Work Breakdown Structure

  • WBS decomposes scope hierarchically into deliverable-oriented work packages; activities are assigned to the lowest-level work package.

  • A work package is the lowest WBS level at which cost and schedule can be managed; it should map one-to-one with schedule activities or activity groups.

  • AACE 29R-03 schedule classification levels: Class 5 (0-2% definition) through Class 1 (50-100% definition); higher class = more mature schedule.

  • Schedule basis document records assumptions, calendars, constraints, coding, and exclusions used to build the schedule.

  • Activity coding (phase, area, discipline, responsible party) enables filtering, grouping, and earned value rollups.

  • Calendars define working days, shifts, and holidays; mismatched calendars between linked activities cause logic gaps or unexpected float.

  • Rolling wave planning progressively elaborates near-term activities in detail while far-term work remains at summary level.

  • A milestone schedule (Level 1) shows key dates only; a Level 3 control schedule shows detailed activities and logic for execution.

Quick reference

Activity Sequencing, Durations, and Logic Relationships

  • Finish-to-Start (FS): successor starts after predecessor finishes; most common and preferred relationship.

  • Start-to-Start (SS): successor starts after predecessor starts; requires a lag to be meaningful.

  • Finish-to-Finish (FF): successor finishes after predecessor finishes; common for overlapping finish-driven work.

  • Start-to-Finish (SF): successor finishes after predecessor starts; rare, used for just-in-time handoffs.

  • Duration estimating methods: analogous (top-down, historical), parametric (unit rate x quantity), three-point (PERT: (O+4M+P)/6), and bottom-up.

  • PERT standard deviation = (P - O)/6; variance = ((P - O)/6)^2.

  • Productivity-based duration = quantity / (crew size x productivity rate), adjusted for calendar and weather factors.

  • Hard logic (mandatory) reflects physical/technical sequence; soft logic (discretionary) reflects preference and can be resequenced.

Quick reference

Critical Path Method and Schedule Calculation

  • Forward pass: ES = max(EF of predecessors + lag); EF = ES + duration. Backward pass: LF = min(LS of successors - lag); LS = LF - duration.

  • Total float = LS - ES = LF - EF. Free float = min(ES of successors) - EF.

  • Critical path = path with minimum total float (usually zero); multiple critical paths can exist.

  • Negative float indicates a constraint or imposed date that cannot be met with current logic and durations.

  • A hammock activity summarizes work between two dates or activities and does not drive logic; its duration is derived, not estimated.

  • Near-critical path has low total float (commonly <= 10-20% of remaining duration) and should be monitored for risk.

  • Total float is shared along a path; its consumption by one activity reduces float available to others on that path.

  • Longest path method (as used with multiple calendars and lags) identifies the driving path more accurately than float alone.

Quick reference

Resource Planning, Loading, and Leveling

  • Resource histogram plots demand per period against available capacity; over-allocation appears as peaks above the capacity line.

  • Resource leveling adjusts start/finish within available float to smooth demand; it may extend the project duration.

  • Resource smoothing (time-limited) shifts work within float without changing the critical path or end date.

  • Resource loading assigns quantities and cost rates to activities; loading precedes leveling.

  • Resource-constrained schedule: logic plus resource limits determine dates; float may be consumed or negative.

  • Peak resource demand drives cost and risk; leveling targets reduce peaks and idle time.

  • Crew balance and continuity of work reduce mobilization/demobilization costs on linear and repetitive projects.

Quick reference

Cost Loading and Schedule-Cost Integration

  • Cost-loaded schedule assigns budgeted cost to activities; total cost-loaded value should reconcile to the project budget.

  • Earned Value: PV = planned % complete x BAC; EV = actual % complete x BAC; AC = actual cost incurred.

  • SV = EV - PV; CV = EV - AC; SPI = EV/PV; CPI = EV/AC.

  • EAC = BAC / CPI (typical variance); EAC = AC + (BAC - EV) (atypical).

  • Schedule-cost integration requires consistent WBS/cost account coding between schedule and cost system.

  • Time-phased cost (cash flow) curve derives from cost-loaded schedule; S-curve compares planned vs. earned vs. actual.

  • Cost loading should not distort logic; costs assigned to summary levels cannot be earned at activity level.

Quick reference

Schedule Risk Analysis and Contingency

  • Schedule risk analysis (QSRA) uses Monte Carlo simulation of activity duration ranges to produce a distribution of completion dates.

  • Three-point estimates feed simulation: optimistic, most likely, pessimistic per activity.

  • P-level dates (e.g., P50, P80) express confidence: P80 means 80% probability of finishing by that date.

  • Contingency (schedule reserve) = P-level date - deterministic date; held at project level, not baked into activity durations.

  • Risk drivers: critical/near-critical activities, long-duration activities, open ends, lags, and constraints.

  • Correlation between activity durations in simulation reflects common-cause risk and increases the spread of results.

  • Risk register links threats/opportunities to activities for targeted mitigation and analysis.

Quick reference

Progress Measurement, Performance Analysis, and Forecasting

  • % complete methods: duration-based, units completed, milestones, weighted steps, and physical measurement; choose per activity type.

  • Earned schedule: ES = period where PV equals current EV; SPI(t) = ES / AT; SV(t) = ES - AT (time units).

  • To-complete performance index: TCPI = (BAC - EV)/(BAC - AC) for budget; (BAC - EV)/(EAC - AC) for EAC.

  • Forecast completion date = data date + (remaining duration / SPI) or via earned schedule projection.

  • Progress must be measured objectively; subjective % complete inflates EV and distorts forecasts.

  • Out-of-sequence progress (work started before predecessors finish) must be identified and corrected in updates.

  • Performance analysis compares planned vs. actual at activity, WBS, and project levels; variances drive corrective action.

Quick reference

Schedule Change Control and Baseline Management

  • Baseline schedule is the approved, time-phased plan against which performance is measured; changes require formal approval.

  • Change control process: identify, evaluate impact (scope, cost, schedule), approve/reject, document, and re-baseline if approved.

  • Re-baselining resets the performance measurement baseline; should be rare and formally authorized.

  • Schedule revisions (updates) record progress without changing the baseline; re-baselining changes the baseline itself.

  • Change log tracks all schedule changes, rationale, approver, and date.

  • Impact analysis uses CPM to determine effect on critical path, float, and completion date before approval.

  • Baseline integrity requires version control and traceability of approved changes.

Quick reference

Schedule Quality, Validation, and Reporting

  • DCMA 14-point assessment checks logic, leads/lags, hard constraints, high float, negative float, high duration, invalid dates, resources, and missed activities.

  • Common DCMA thresholds: no more than 5% of activities with lags; no more than 5% with hard constraints; no more than 5% with total float > 44 days (high float).

  • Open ends: every activity except start/finish should have at least one predecessor and one successor.

  • Schedule health checks include logic density, critical path continuity, and duration outliers.

  • Reporting: Gantt, network diagram, resource histogram, S-curve, and earned value reports tailored to audience.

  • Data date (status date) is the point through which progress is recorded; all actuals must be current to that date.

  • Validation confirms the schedule reflects the plan, is logically sound, and reconciles to cost and scope.