CAPES key terms
CAPES · Get comfortable with the vocabulary.
- Work Breakdown Structure (WBS)
- Related: Work Package, Activity, Control Account
A hierarchical decomposition of the total project scope into progressively smaller, deliverable-oriented components. Each descending level represents increasingly detailed definition of the work, ending at work packages that can be estimated, scheduled, and controlled.
- Work Package
- Related: Work Breakdown Structure (WBS), Activity, Control Account
The lowest level of the WBS, a discrete scope element that can be realistically estimated, scheduled, assigned to a responsible person, and measured for progress. It is the basis for defining activities and control accounts.
- Activity
- Related: Work Package, Logic Relationship, Duration
A distinct, identifiable unit of work performed during the project that consumes time and usually resources. Activities have defined start and finish points and form the building blocks of the schedule network.
- Control Account
- Related: Work Package, Earned Value Management (EVM), Cost Loading
A management control point in a work breakdown structure where scope, schedule, and cost are integrated and compared against earned value. It sits above work packages and is assigned to a single accountable manager.
- Activity-on-Node (AON)
- Related: Precedence Diagramming Method (PDM), Logic Relationship, Network Diagram
A network diagramming method where each activity is drawn as a node or box, and arrows represent the logical relationships between activities. It is the basis for most modern scheduling software and the precedence diagramming method.
- Precedence Diagramming Method (PDM)
- Related: Activity-on-Node (AON), Finish-to-Start (FS), Lag
A scheduling technique that uses nodes to represent activities and arrows to show dependencies. It supports four relationship types: finish-to-start, start-to-start, finish-to-finish, and start-to-finish, and is the dominant method in critical path scheduling.
- Finish-to-Start (FS)
- Related: Precedence Diagramming Method (PDM), Start-to-Start (SS), Lag
A logical relationship in which the successor activity cannot start until the predecessor activity has finished. It is the most common dependency type in construction and engineering schedules and carries the least ambiguity.
- Start-to-Start (SS)
- Related: Finish-to-Start (FS), Finish-to-Finish (FF), Lag
A logical relationship in which the successor activity cannot begin until the predecessor activity has begun. It is typically paired with a lag to express overlapping work, such as starting inspection a set time after installation starts.
- Finish-to-Finish (FF)
- Related: Start-to-Start (SS), Lag, Precedence Diagramming Method (PDM)
A logical relationship in which the successor activity cannot finish until the predecessor activity has finished. It is used where completion of one work item governs completion of another, often with a lag to allow trailing work.
- Lag
- Related: Lead, Float (Slack), Finish-to-Start (FS)
A deliberate, quantified delay inserted between a predecessor and successor activity to reflect real-world constraints such as curing time, approval periods, or delivery lead time. Lag is not the same as float and is not consumption of slack.
- Lead
- Related: Lag, Schedule Quality Check, Logic Relationship
A negative lag that allows a successor activity to begin before the predecessor has completed its required portion. Excessive use of lead can obscure logic and is often flagged in schedule quality reviews.
- Critical Path Method (CPM)
- Related: Critical Path, Total Float, Forward Pass
A deterministic scheduling technique that calculates the longest path through the network, which determines the shortest possible project duration. Activities on that path have zero or minimal total float and drive the project completion date.
- Critical Path
- Related: Critical Path Method (CPM), Total Float, Near-Critical Path
The sequence of logically connected activities with the longest total duration through the network, which establishes the project finish date. Any delay on this path delays project completion unless the path is compressed or logic changes.
- Total Float
- Related: Free Float, Critical Path, Forward Pass
The amount of time an activity can be delayed from its early start without delaying the project finish date or violating a schedule constraint. It is calculated as late start minus early start, or late finish minus early finish.
- Free Float
- Related: Total Float, Logic Relationship, Critical Path
The amount of time an activity can be delayed without delaying the early start of any immediate successor activity. Unlike total float, free float is a property of the relationship to successors rather than the whole project.
- Forward Pass
- Related: Backward Pass, Total Float, Critical Path Method (CPM)
A network calculation that moves from project start to finish to determine each activity's early start and early finish dates, based on durations and logic. Its results define the earliest possible project completion.
- Backward Pass
- Related: Forward Pass, Total Float, Critical Path
A network calculation that moves from project finish to start to determine each activity's late finish and late start dates. Combined with forward pass results, it yields total float and identifies the critical path.
- Near-Critical Path
- Related: Critical Path, Total Float, Schedule Risk Analysis
A path through the network whose total float is small but greater than zero, often within a defined threshold of the critical path. Monitoring near-critical paths helps anticipate emerging risks before they affect completion.
- Resource Leveling
- Related: Resource Smoothing, Resource Histogram, Resource-Constrained Schedule
A scheduling technique that adjusts activity start and finish dates to resolve resource over-allocation or to smooth resource demand, often extending the project duration. It changes logic or dates rather than just shifting non-critical work within float.
- Resource Smoothing
- Related: Resource Leveling, Total Float, Resource Histogram
A technique that shifts activities within their available float to reduce peaks and valleys in resource demand without changing the project completion date or the critical path. It cannot resolve a genuine resource shortage.
- Resource Histogram
- Related: Resource Leveling, Resource Smoothing, Resource-Constrained Schedule
A bar chart showing the quantity of a resource required per time period across the project. It is used to identify over-allocation, peak demand, and the effect of leveling or smoothing decisions.
- Resource-Constrained Schedule
- Related: Resource Leveling, Critical Path, Schedule Basis
A schedule in which activity timing is limited by the availability of resources rather than by logic alone. It typically results from resource leveling and may have a later completion date than the logic-driven schedule.
- Cost Loading
- Related: Control Account, Earned Value Management (EVM), Time-Phased Budget
The assignment of planned cost values to schedule activities or work packages so that cost and time can be tracked together. It enables time-phased budgets, cash flow forecasting, and earned value measurement.
- Time-Phased Budget
- Related: Cost Loading, Earned Value Management (EVM), Performance Measurement Baseline (PMB)
A distribution of the approved project budget across the schedule timeline, showing planned expenditure per period. It is the baseline against which earned value and actual costs are compared over time.
- Earned Value Management (EVM)
- Related: Planned Value (PV), Schedule Performance Index (SPI), Estimate at Completion (EAC)
A performance measurement method that integrates scope, schedule, and cost by comparing planned value, earned value, and actual cost. It produces variance and index metrics that indicate cost and schedule performance and forecast outcomes.
- Planned Value (PV)
- Related: Earned Value (EV), Earned Value Management (EVM), Schedule Variance (SV)
The authorized budget assigned to scheduled work for a given period, sometimes called budgeted cost of work scheduled. It represents what the project planned to have accomplished and spent by a point in time.
- Earned Value (EV)
- Related: Planned Value (PV), Percent Complete, Earned Value Management (EVM)
The value of work actually completed, measured as the budgeted cost of work performed. It converts physical progress into budget terms so that accomplishment can be compared with plan and actual cost.
- Schedule Performance Index (SPI)
- Related: Schedule Variance (SV), Earned Value Management (EVM), Estimate at Completion (EAC)
A ratio of earned value to planned value that indicates schedule efficiency. A value below one means less work was accomplished than planned; the index is often used to forecast schedule outcomes.
- Schedule Variance (SV)
- Related: Schedule Performance Index (SPI), Earned Value (EV), Planned Value (PV)
The difference between earned value and planned value, expressed in cost or work units rather than time. A negative value indicates work is behind plan; it must be interpreted carefully because it is not a duration measure.
- Estimate at Completion (EAC)
- Related: Earned Value Management (EVM), Schedule Performance Index (SPI), Forecast
A forecast of the total cost of the project based on performance to date and expected future conditions. It can be calculated several ways, including budget divided by cost performance index or actual cost plus a bottom-up estimate to complete.
- Percent Complete
- Related: Earned Value (EV), Progress Measurement, S-Curve
A measure of work accomplished expressed as a proportion of the total. It can be based on duration, cost, units installed, or milestone weighting, and the chosen method must be documented and applied consistently.
- S-Curve
- Related: Time-Phased Budget, Percent Complete, Forecast
A graph of cumulative cost, progress, or resource usage over time, typically S-shaped because expenditure and accomplishment start slowly, accelerate, then taper. It is used to compare planned, earned, and actual performance visually.
- Schedule Risk Analysis
- Related: Monte Carlo Simulation, Contingency, Near-Critical Path
A quantitative or qualitative assessment of uncertainty in activity durations and logic to estimate the probability of meeting schedule targets. It often uses Monte Carlo simulation to produce confidence levels for completion dates.
- Monte Carlo Simulation
- Related: Schedule Risk Analysis, Contingency, Three-Point Estimate
A probabilistic technique that runs many iterations of the schedule using sampled duration and cost ranges to produce a distribution of possible completion dates or costs. It supports confidence-based contingency setting.
- Contingency
- Related: Schedule Risk Analysis, Management Reserve, Buffer
Time or money reserved to address known risks and uncertainties that remain after planning. Schedule contingency is often expressed as a buffer on the critical path or as a confidence-based allowance beyond the deterministic finish date.
- Management Reserve
- Related: Contingency, Performance Measurement Baseline (PMB), Change Control
An amount of time or budget held by senior management for unanticipated work within the project scope but outside the performance measurement baseline. It is not allocated to activities unless formally authorized through change control.
- Performance Measurement Baseline (PMB)
- Related: Baseline, Change Control, Time-Phased Budget
The approved, time-phased plan against which project performance is measured, formed by the scope, schedule, and cost baselines. Changes to it require formal change control and are documented as baseline revisions.
- Baseline
- Related: Performance Measurement Baseline (PMB), Change Control, Schedule Variance (SV)
An approved, frozen version of the schedule, cost, or scope plan used to compare actual performance and to control change. The schedule baseline is the reference for measuring variance and for approving revisions.
- Change Control
- Related: Baseline, Performance Measurement Baseline (PMB), Trend Analysis
A formal process for identifying, evaluating, approving or rejecting, and documenting changes to the baseline. It ensures that modifications are justified, authorized, and reflected consistently in scope, schedule, and cost.
- Schedule Quality Check
- Related: Logic Relationship, Lead, Schedule Validation
A structured review of a schedule against defined criteria such as logic density, missing predecessors or successors, excessive lags, hard constraints, and negative float. It reveals defects that undermine the schedule's reliability for forecasting.
- Schedule Validation
- Related: Schedule Quality Check, Schedule Basis, Baseline
The process of confirming that a schedule is complete, logically sound, resource- and cost-loaded as required, and consistent with the project plan. It differs from quality checking by focusing on fitness for the intended use.
- Schedule Basis
- Related: Schedule Validation, Resource-Constrained Schedule, Baseline
A documented record of the assumptions, constraints, calendars, logic, and estimating methods used to build the schedule. It allows reviewers to understand and validate the schedule and supports later change control.
- Trend Analysis
- Related: Forecast, Schedule Variance (SV), Change Control
The examination of schedule or cost performance over successive reporting periods to identify patterns and forecast likely outcomes. It can reveal deteriorating performance earlier than a single-period variance analysis.