A Fixed-Price Portal and the 'It's Already in Scope' Request
Northwind Credit Union has a fixed-price contract of $600,000 and 12 two-week sprints to deliver a member portal. The baseline covers 180 story points; the team's demonstrated velocity is 18 points per sprint. At the end of sprint 6, 108 points are complete and 112 remain, including 10 points of carryover. The client's marketing director now demands a real-time promotions banner and Spanish-language support, which the team estimates at 34 points, arguing the statement of work already lists 'marketing content' and 'member communications.' The vendor's contract has a formal change-control clause requiring written approval and priced change orders. The client has paid 55% of the contract value to date. The vendor's account manager wants to absorb the work to protect the relationship; the delivery lead warns the team is already at capacity and two senior developers have booked vacation in sprints 9–10.
1. Is the new request in scope? What process governs it?
Read the worked answer
Not in scope on the evidence given. Three tests:
- Size against the baseline. The baseline is 180 points and the request is estimated at 34 - nearly 19% of the whole project. Work of that magnitude is not a clarification of an existing line item.
- Specificity of the SOW. 'Marketing content' and 'member communications' describe a category, not a real-time promotions engine or a second language. A vague category name does not transfer 34 points of new build to a fixed-price vendor.
- Contract mechanism. The contract has a written change-control clause and priced change orders. Absorbing the work outside that clause sets a precedent and erodes protection for every later request.
Process to apply: log the request in the change-control system, perform an impact analysis (effort, cost, schedule, risk, quality), and take it to the change board and the client's authorised representative for a written decision. Even if the answer is 'do it,' it must be a priced, signed change order that moves the baseline and the contract value.
If the client genuinely believes it is in scope, resolve that through the contract's ambiguity or dispute step - not through silent absorption by the delivery team.
2. Quantify the schedule impact of adding the 34 points and set out the options for the client.
Read the worked answer
Capacity check first.
- Remaining work at end of sprint 6: 112 points, including 10 of carryover.
- Sprints remaining: 6. At the demonstrated 18 points/sprint the team can deliver ~108 points - already about 4 points short of the outstanding work.
- Sprints 9–10 lose two senior developers, so a realistic velocity for those sprints is closer to 12–14. Blended velocity over the remaining six sprints is more like 16.
Adding 34 points takes remaining work to 146 points. At ~16 points/sprint that is about 9 sprints - roughly 3 sprints (6 weeks) late, before allowing for further vacation effects.
Options to table:
- Change order with a 3-sprint extension - priced at the team's run rate plus the 34 points of build; protects quality and the date commitment elsewhere.
- Change order with a scope swap - trade ~34 points of lower-value baseline features for the banner and Spanish support, keeping the date. Requires the client to rank its backlog in writing.
- Phased delivery - banner in the current release, Spanish support in a separately funded follow-on release.
- Absorb - not recommended: the team has no spare capacity, so the realistic outcome is overtime, defects, and a late date anyway.
Recommend option 2 or 3 and let the client choose. The PM's job is to make the trade-off explicit and priced, not to absorb it.
3. The client refuses a change order and the account manager instructs the team to 'just build it.' What do you do?
Read the worked answer
Hold the line, but make yes easy.
- Put the facts in writing. A short note: 34 points, ~6 weeks of schedule at current velocity, 10 points of carryover already, two senior developers on leave in sprints 9–10. Attach the number to the decision, not the relationship.
- Do not let work start without a disposition. Unauthorised build is scope creep; once started, the vendor loses the leverage to price it and the date commitment moves silently.
- Escalate internally, not at the client. The account manager is making a commercial promise delivery cannot keep - that is a line-management issue. Frame it as: 'We can absorb this only if you also accept the date slip or the scope swap. Which do you authorise?'
- Offer a face-saving route: a paid discovery spike, a fixed-price change order at modest margin, or the phased release, so the client gets a visible win without 34 unfunded points.
- Document the risk. Record the instruction and your objection in the risk register and decision log. If the account manager overrides in writing, that becomes an accepted risk with a named owner and a stated consequence.
- Check the contract's escalation clause. Many fixed-price contracts define a dispute path that protects both parties and cools the commercial pressure.
The PM protects the baseline and team capacity; the account manager protects the relationship. Resolve the conflict above both roles, with data.