32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Project
A temporary endeavor undertaken to create a unique product, service, or result, with a defined start and finish and constrained by scope, time, and cost.
Program
A group of related projects and subsidiary activities managed in a coordinated way to obtain benefits not available from managing them individually.
Portfolio
A collection of projects, programs, and operations managed together to achieve strategic objectives; projects within it may be unrelated to each other.
Project charter
A document issued by the sponsor that formally authorizes the project, names the project manager, and records high-level scope, objectives, and constraints.
Stakeholder register
An artifact identifying stakeholders, their roles, interests, expectations, influence, and communication needs, used to plan engagement throughout the project.
Work breakdown structure
A hierarchical decomposition of total project scope into deliverables and work packages; the 100% rule requires child elements to sum to the parent.
Critical path
The longest sequence of dependent activities through the schedule network, determining the shortest possible project duration; activities on it have zero total float.
Total float
The amount of time an activity can be delayed without delaying the project finish date, calculated as late start minus early start or late finish minus early finish.
Free float
The time an activity can be delayed without delaying the early start of any successor; it is always less than or equal to total float.
Lead and lag
Lead is time by which a successor may start before its predecessor finishes; lag is a waiting period added between dependent activities in the network.
Crashing
Schedule compression by adding resources to critical-path activities to shorten duration, usually increasing cost and requiring consideration of diminishing returns.
Fast tracking
Schedule compression by performing activities in parallel that were originally planned sequentially, which raises risk of rework and coordination problems.
Three-point estimating
An estimating technique using optimistic, most likely, and pessimistic values; the PERT weighted average is (optimistic + 4×most likely + pessimistic) divided by six.
Analogous estimating
Estimating duration or cost using historical data from a similar past project; fast and low-cost but less accurate, and relies on genuine similarity.
Parametric estimating
Estimating using a statistical relationship between historical data and variables, such as cost per square meter multiplied by the quantity of work.
Bottom-up estimating
Estimating individual work packages or activities in detail and aggregating them upward; most accurate and most time-consuming of the estimating techniques.
Contingency reserve
A budget or time reserve allocated for identified risks that have been accepted; it is part of the performance measurement baseline and controlled by the project manager.
Management reserve
A reserve for unidentified scope or unforeseen work, held outside the performance measurement baseline and typically requiring sponsor or senior management approval to use.
Planned value
The authorized budget assigned to scheduled work at a point in time; it is the baseline against which schedule and cost performance are measured.
Earned value
The value of work actually completed, measured as budgeted cost of that work; it combines scope, schedule, and cost into one performance indicator.
Cost performance index
Earned value divided by actual cost; a value below 1.0 means the project is spending more than planned for the work accomplished.
Schedule performance index
Earned value divided by planned value; a value below 1.0 means less work has been accomplished than planned at that point in the schedule.
Estimate at completion
The forecast total cost of the project when complete; commonly actual cost plus estimate to complete, or budget at completion divided by cost performance index.
Budget at completion
The total approved budget for the work described in the scope baseline, used as the reference point for earned value cost forecasting.
Risk register
A living document recording identified risks with their causes, probability, impact, risk score, owner, planned responses, and current status.
Expected monetary value
The probability of a risk event multiplied by its financial impact; used to compare risks and choose between alternative responses in decision trees.
Quality assurance
The process of auditing quality requirements and results to ensure appropriate quality standards and operational definitions are being used; it is prevention-oriented.
Control chart
A statistical tool plotting process data over time against upper and lower control limits to detect special-cause variation and signal when a process is out of control.
Change control board
A formally constituted group that reviews change requests, assesses their impact, and approves, rejects, or defers them according to delegated authority.
Scope creep
Uncontrolled expansion of project scope without corresponding adjustments to time, cost, and resources, usually from unmanaged change requests.
Lessons learned
Knowledge captured during and after the project about what worked and what did not, stored in organizational process assets for future project use.
Project management office
An organizational unit providing project support; it may be supportive, controlling, or directive depending on how much authority it holds over project work.