ICAG Paper 1.4 Cost & Management Accounting flashcards
ICAG Paper 1.4 Cost & Management Accounting · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Cost object
- Any activity, product, service, department or customer for which a separate measurement of cost is required. It determines what costs are collected and how they are assigned.
- Prime cost
- The total of direct materials, direct labour and direct expenses. It excludes all production overhead and is the first block in building up the full production cost of a product.
- Conversion cost
- The sum of direct labour and production overhead incurred to convert raw materials into finished output. It is used in process costing to value equivalent units of work done.
- High-low method
- Technique separating mixed cost into fixed and variable elements using the highest and lowest activity levels. Variable rate equals the change in cost divided by the change in activity.
- Relevant range
- The band of activity over which the assumed fixed cost total and variable cost per unit remain valid. Outside it, step-fixed costs and efficiency changes break the cost behaviour assumptions.
- Overhead absorption rate
- Budgeted production overhead divided by a budgeted activity base such as labour hours, machine hours or units. It allocates indirect cost to products using a predetermined basis.
- Job costing
- A costing method where costs are collected for each separately identifiable job or customer order. It suits bespoke, low-volume production such as construction, printing or custom machinery.
- Batch costing
- A costing method treating a group of identical units produced together as one cost unit. Unit cost equals total batch cost divided by the number of good units in the batch.
- Notional profit
- In contract costing, the value of work certified plus work in progress less costs incurred to date. It is the basis for deciding how much contract profit to recognise prudently.
- Normal loss
- Expected, unavoidable process loss expressed as a percentage of input. It is valued at scrap value only, so its cost is absorbed by the good output of the process.
- Abnormal gain
- Output exceeding the expected level after allowing for normal loss. It is valued at full cost per good unit and credited to the process account and to profit.
- Equivalent units
- A conversion of partly finished output into the number of fully complete units it represents. Used in process costing to spread costs fairly across completed and closing work in progress.
- Marginal costing
- A costing system valuing inventory at variable production cost only. Fixed production overhead is treated as a period cost, so profit moves directly with sales volume.
- Absorption costing
- A costing system including fixed production overhead in product cost. Profit differs from marginal costing by the change in inventory multiplied by the fixed overhead absorption rate.
- Flexed budget
- A budget restated for the actual activity level achieved using standard variable cost per unit. Fixed costs remain at budget, allowing fair comparison of actual and expected cost.
- Material price variance
- Standard price minus actual price, multiplied by actual quantity purchased. A positive figure is favourable; it is usually the purchasing manager's responsibility and is measured at point of purchase.
- Labour efficiency variance
- Standard hours for actual output minus actual hours worked, multiplied by standard rate. It measures productivity against the standard allowance and is normally the production manager's responsibility.
- Fixed overhead volume variance
- Budgeted hours minus standard hours for actual output, multiplied by the standard fixed overhead rate. It splits into capacity and efficiency components under absorption costing.
- Sales volume variance
- Actual units sold minus budgeted units, multiplied by standard contribution per unit under marginal costing, or standard profit per unit under absorption costing.
- Operating statement
- A report reconciling budgeted profit to actual profit by listing favourable and adverse variances in order. It explains the causes of the difference rather than just stating it.
- Relevant cost
- A future, incremental cash flow that differs between the alternatives being considered. Sunk costs, committed costs and non-cash book values are excluded from the decision.
- Opportunity cost
- The contribution or benefit forgone from the next best alternative use of a scarce resource. It is a relevant cost even though no cash is paid for it.
- Limiting factor ranking
- Rank products by contribution per unit of the scarce resource, not by contribution per unit. This maximises total contribution when a single resource constrains output.
- Shut-down decision
- A segment is closed only if its contribution is less than the specific fixed costs avoided by closing. Unavoidable allocated fixed costs are irrelevant to the decision.
- Throughput accounting
- A technique measuring throughput as sales less material cost, ranking products by throughput per unit of bottleneck time. It focuses improvement effort on the binding constraint.
- Return on investment
- Controllable divisional profit divided by capital employed, expressed as a percentage. It links profit to the assets used but can discourage managers from accepting profitable projects.
- Residual income
- Controllable profit less an imputed interest charge on capital employed. It encourages investment-centre managers to accept projects earning above the cost of capital.
- Balanced scorecard
- A performance framework using financial, customer, internal process, and learning and growth perspectives. It links measures to strategy and balances lagging with leading indicators.
- Minimum transfer price
- Variable cost of the transferred unit plus the opportunity cost of transferring it internally. Where spare capacity exists, opportunity cost is nil and the minimum equals variable cost.
- Responsibility centre
- A unit of an organisation whose manager is accountable for defined outputs: cost, revenue, profit or investment centre. Controllable items only should be used to judge the manager.
- Goal congruence
- The condition where individual managers' objectives align with those of the organisation. Budgets, performance measures and incentives are designed to encourage congruent behaviour.
- Variance investigation rule
- Investigate a variance when the expected benefit of correcting the cause exceeds the cost of investigation. Control limits and standard error help separate random from systematic variation.