HI Plumber study materials
HI Plumber study resources

HI Plumber flashcards

HI Plumber · Build recall with a focused review session.

32 cards. Read the term and the definition here. The deck at the top of this page is optional.

Trap seal depth
A water seal of 2 to 4 inches (51–102 mm) in a trap prevents sewer gas from entering a building; the maximum permitted depth is 4 inches.
Confined space oxygen level
Safe entry requires oxygen between 19.5% and 23.5%; test before entry and ventilate continuously to avoid asphyxiation or explosion.
DWV air test pressure
A DWV system air test uses 5 psi (34.5 kPa) held for 15 minutes with no pressure drop; water test uses 10 feet (3 m) of head.
Hot water scald limit
Domestic hot water at fixture outlets must not exceed 120°F (49°C); public facilities require scald protection such as thermostatic mixing valves.
Pipe support spacing
Copper horizontal pipe must be supported at intervals not exceeding 6 feet (1.8 m); PEX horizontal at 32 inches (813 mm) and vertical at 10 feet (3 m).
Backflow preventer testing
A reduced-pressure zone (RPZ) backflow assembly must be tested annually by a certified tester to confirm proper operation and protect potable water.
Water closet flush volume
New water closets must not exceed 1.6 gallons per flush (6 Lpf); urinals must not exceed 1.0 gallon per flush (3.8 Lpf).
Lavatory faucet flow rate
Lavatory and kitchen faucets are limited to a maximum flow rate of 2.2 gallons per minute (8.3 L/min) at 60 psi.
Water closet clearance
A water closet requires at least 15 inches (381 mm) from centerline to side wall and 21 inches (533 mm) of clear space in front.
Shower valve temperature limit
Shower valves must be pressure-balancing or thermostatic and limit outlet temperature to 120°F (49°C) to prevent scalding.
Fixture unit (FU)
A fixture unit is a measure of load on the plumbing system; a water closet counts as 3 FU drainage and 10 FU supply for private use.
Floor drain trap primer
A trap primer or trap seal protection device is required where a floor drain trap may evaporate, maintaining the 2-inch (51 mm) minimum seal.
Drainage pipe slope
Drainage pipe must slope 2% (1/4 inch per foot) for 2-inch (50 mm) and smaller pipe; 1% (1/8 inch per foot) for 3-inch (80 mm) and larger.
Vent stack roof extension
A vent stack must extend at least 6 inches (152 mm) above the roof, or 12 inches (305 mm) where snow accumulation is expected.
Maximum trap arm length
A 2-inch (50 mm) trap arm may be up to 5 feet (1.5 m) long; a 3-inch (80 mm) trap arm may be up to 6 feet (1.8 m) long.
Building drain cleanout
A cleanout is required at the junction of the building drain and building sewer and at intervals not exceeding 100 feet (30.5 m).
Horizontal drainage support
Horizontal drainage pipe must be supported at intervals not exceeding 4 feet (1.2 m) for 2-inch and smaller, and 10 feet (3 m) for larger pipe.
Vent vertical rise
A vent must rise vertically at least 6 inches (152 mm) above the fixture before any horizontal offset to prevent clogging.
Minimum fixture water pressure
The minimum static water pressure at a fixture is 8 psi (55 kPa); the maximum static pressure is 80 psi (552 kPa).
Pressure-reducing valve setting
A pressure-reducing valve is required when street pressure exceeds 80 psi (552 kPa) and is typically set to 50–60 psi (345–414 kPa).
Water supply fixture units
Water supply pipe sizing uses fixture units (WSFU) and equivalent length; a 1/2-inch tube supplies up to 6 WSFU at 60 psi.
Thermal expansion control
A closed water system requires an expansion tank sized to system volume to prevent excessive pressure from thermal expansion.
Backflow prevention hierarchy
An air gap provides the highest protection; an RPZ is used for high hazard; a double check valve is used for low hazard.
TPR discharge pipe termination
A water heater temperature and pressure relief valve discharge pipe must terminate 6–24 inches (152–610 mm) above the floor and not be trapped.
Plumbing permit requirement
A plumbing permit is required before installing, altering, or repairing a plumbing system; exemptions vary by jurisdiction and must be verified with the AHJ.
Model plumbing codes
The IPC and UPC are model codes; local amendments govern. Always confirm the adopted edition with the authority having jurisdiction (AHJ).
Rough-in inspection
A plumbing inspector must inspect rough-in, water test, and final work; approval must be obtained before concealing any piping.
Backwater valve requirement
A backwater valve is required on a building sewer subject to backflow; it must be accessible for maintenance and testing.
Plumbing license requirement
A plumbing contractor license is required for contracting; a journeyman license is required for individuals performing plumbing work under supervision.
Labor burden multiplier
Labor cost equals hourly wage times labor burden (typically 1.25–1.65) times hours; burden includes taxes, insurance, and benefits.
Change order
A change order is a written, signed document stating scope, price, and schedule impact; work proceeds only after authorization.
Retainage
Retainage is a percentage (typically 5–10%) withheld from payments until substantial completion; it is tracked as accounts receivable.