HK Crane Operator (CIC) study materials
HK Crane Operator (CIC) study resources

HK Crane Operator (CIC) cheat sheet

HK Crane Operator (CIC) · Keep the key ideas within reach.

Quick reference

Machineries and Crane Operation (CIC Construction Crane Operator)

  • Load moment = load weight × operating radius measured horizontally from the slewing centre to the load's centre of gravity; capacity charts are valid only for the radius actually measured, not the boom length.

  • Rated capacity already includes the deduction for hook block, slings and other lifting gear only where the chart states 'gross' values; where charts give 'net' capacity, add rigging weight to the load before comparing with the rating.

  • Telescopic boom capacity falls with boom extension as well as radius: for the same radius, a longer boom with a heavier boom section gives a lower rating, so the chart column for the actual boom length must be used.

  • Tower crane rated capacity is limited by the jib-end (tip) load and by the maximum load near the tower; the load moment limiter must be set so that neither the moment curve nor the tip-load limit is exceeded.

  • Slewing and travel brakes, outrigger beams, level indicators and the rated capacity limiter/indicator are pre-use checks; the RCI must be calibrated and must not be overridden to lift beyond the chart.

  • Stability rule: mobile cranes on outriggers require fully extended beams and pads on ground able to carry the outrigger load; the chart assumes the crane is level within the manufacturer's tolerance (commonly about 1%).

  • Wind limits: stop lifting when wind speed exceeds the manufacturer's figure for the boom/jib configuration in use, and remember that a large sail-area load increases the effect well before the crane's own limit is reached.

  • Two-crane (tandem) lifts require a written plan, a designated lift supervisor, load share kept within each crane's chart at all times, and radio contact between operators; each crane must be rated for at least its planned share plus a margin.

  • Hand signals follow the standard set: raise/lower, slew left/right (from the operator's seat), extend/retract boom, raise/lower boom, stop, and emergency stop - one signalman only, and any person may give the emergency stop.

Quick reference

Machineries and Crane Operation (CIC Construction Crane Operator)

  • Sling angle factor: tension in each leg = load / (number of legs × cos of the angle from vertical); at 60° from vertical the factor is 2.0, at 45° it is 1.41, at 30° it is 1.15 - never exceed the sling's WLL.

  • Wire rope inspection rejection criteria include broken wires in a specified length, kinking, bird-caging, corrosion, and reduction in diameter beyond the manufacturer's limit; discard rather than re-reeve damaged rope.

  • Rigging hardware: shackles must be rated and pin-loaded correctly, hooks need a functioning safety latch, and the SWL/WLL marking must be legible; never side-load a hook beyond its rated angle.

  • Outrigger ground pressure: use spreader mats sized so the pressure under the pad stays below the ground's bearing capacity; hidden voids, drains, backfilled trenches and suspended slabs are common causes of overturning.

  • Signals and communication: if radio fails, stop the lift; the operator must stop on any unclear signal, and a suspended load must never be left unattended or slewed over people.

  • Daily and statutory examination: pre-use checks by the operator, and thorough examination by a competent examiner at the interval set by local law (commonly 12 months, or 6 months for lifting people/equipment) with a report before return to service.

  • Load charts are configuration-specific: counterweight, outrigger spread, boom/jib combination, tyre pressure and pick-and-carry vs stationary all change the rating; the correct chart page must be identified before the lift.

  • Pick-and-carry capacity is far lower than stationary capacity because tyre deflection and suspension travel affect stability; travel with the load low, boom short, and a banksman guiding.

Quick reference

Machineries and Crane Operation (CIC Construction Crane Operator)

  • Boom deflection and radius growth: as the boom deflects under load, the actual radius increases and capacity falls, so the load must be lifted slightly and the radius re-checked before hoisting to full height.

  • Shock loading is multiplied by dynamic factors; snatching a load, rapid slewing with a swinging load, or dragging a load sideways all produce forces beyond the static weight and are prohibited.

  • Tower crane climbing and erection, and mobile crane boom assembly, are planned operations requiring the manufacturer's procedures, a method statement, exclusion zones and wind monitoring.

  • Electrical safety: keep the manufacturer's minimum clearance from overhead lines (commonly 3 m for lines up to 66 kV, more for higher voltages); use goal posts or a permit-to-work and a banksman when clearance cannot be kept.

  • Rope reeving and parts of line: the hook block's number of falls sets the line pull and the load on each rope part; the drum must retain the manufacturer's minimum number of dead wraps at all times.

  • Crane types and duties: tower cranes for high reach on site, crawler cranes for soft ground and travel with load, all-terrain mobiles for road travel, and lorry loaders for transport duties - duty cycle and utilisation class must match the work.

  • Emergency procedures: lower the load if possible, stop all motions, keep the area clear, and never attempt to catch or manually steady a swinging load; report any limit-switch or brake fault immediately.

  • Personnel lifting is a separate category with its own rules: a certified man-riding basket, reduced capacity, secondary retention, and a specific risk assessment are required - general lift plans do not cover it.