CPIT APM case studies
CPIT APM · Put your knowledge to work in context.
The CPIT APM credential is a project management certification offered within the Global Association for Quality Management (GAQM) portfolio. GAQM describes itself as an organisation focused on educating, empowering and certifying individuals and corporates globally, and it lists Project Management Certifications as one of its certification families, noting a "3 level multi-level certification system" that attracts project professionals. This page is an independent study resource: it is not affiliated with, endorsed by, or operated by GAQM, and it does not reproduce any official exam content. The candidate this credential suits is a practising or aspiring project professional, including IT staff moving into delivery roles, who needs working command of project fundamentals, initiation and planning, execution with monitoring and control, and closure with stakeholder communication. The CPIT APM case studies are 5 cases and about 3,678 words.
1The nominal 20% DBA in a weak matrix
Northbridge Retail has run IT as a functional department for nine years. You are the newly appointed project manager for a 26-week migration of the merchandising data warehouse to a cloud platform.
630 words, about 3 min2Fixed price, ten-week promise, fourteen-week estimate
You are the project manager for a fixed-price £480,000 CRM implementation for a client with 300 users. Sales has committed to a 10-week go-live with 3 weeks of parallel running.
865 words, about 4 min3Payment API fails under load and the vendor submits a change order
A 14-person distributed team is building a payment API for six downstream systems. The vendor is in a timezone 7 hours behind you.
797 words, about 4 min4Earned value, a mandatory patch and a request to cut testing
You are managing a 20-week platform upgrade with a budget at completion (BAC) of £800,000. At the end of week 8, planned value (PV) is £320,000, earned value (EV) is £260,000, and actual cost (AC) is £300,000.
607 words, about 3 min5Low adoption, open defects and pressure to close
A 9-month HR self-service portal went live 6 weeks ago for 1,200 employees. Only 35 unique users are active weekly, against a benefits case that assumed 60% adoption by month 3.
779 words, about 4 min