CPIT APM study materials
CPIT APM study resources

CPIT APM study plan

CPIT APM · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Project Management Fundamentals

  • Define the project, program, and portfolio relationship in your own words and map three real workplace examples to each level

  • Explain how the triple constraint and competing constraints interact, using one worked example where a scope change forces a schedule and cost trade-off

  • Distinguish predictive, iterative, incremental, and agile delivery approaches and select the best fit for two short scenario descriptions

  • List the key responsibilities of a project manager versus a project sponsor and a functional manager

  • Build a one-page glossary of 20 core terms (stakeholder, deliverable, baseline, WBS, RACI) with definitions you wrote yourself

Your checkpoint

A one-page glossary plus a 300-word written comparison of the four delivery approaches, scored against a self-made 10-point checklist

Week 2

Project Management Fundamentals

  • Walk through the five process groups and assign at least two concrete activities to each group

  • Explain how the ten knowledge areas map onto the process groups and identify which areas dominate planning versus monitoring

  • Describe organizational structures (functional, matrix, projectized) and predict where authority and communication friction will appear in each

  • Identify the inputs, tools and techniques, and outputs pattern that recurs across processes and apply it to one process of your choice

  • Complete 40 practice questions on fundamentals and log every miss with the reason it was missed

Your checkpoint

A process-group and knowledge-area matrix with your own example activities filled in, plus an error log covering 40 practice questions

Week 3

Project Initiation and Planning

  • Draft a project charter for a realistic scenario, covering purpose, measurable objectives, high-level scope, success criteria, and named sponsor authority

  • Identify stakeholders using a power-interest grid and classify at least eight stakeholders from your scenario

  • Produce a stakeholder engagement plan that assigns an engagement level (unaware, resistant, neutral, supportive, leading) and a tailored action to each key stakeholder

  • Write three SMART objectives and test each one against a measurable acceptance criterion

  • Explain the difference between a business case and a benefits management plan and state who owns each

Your checkpoint

A complete project initiation pack for one scenario: charter, stakeholder register, power-interest grid, and engagement plan

Week 4

Project Initiation and Planning

  • Decompose your scenario scope into a work breakdown structure to at least three levels with a work package dictionary for five packages

  • Estimate duration and cost for each work package using two different techniques and explain when each technique is appropriate

  • Sequence activities into a network diagram and calculate the critical path, total float, and free float by hand

  • Build a resource-loaded schedule and identify at least one over-allocation and your resolution

  • Draft a risk register with eight risks, each with probability, impact, score, response strategy, and an owner

Your checkpoint

A planning baseline for the scenario: WBS, activity list, network diagram with critical path and float values, cost estimate, and risk register

Week 5

Project Initiation and Planning & Project Execution, Monitoring and Control

  • Assemble a cost baseline with a contingency reserve and a management reserve, and justify each reserve amount

  • Write a quality management plan naming two quality metrics, the measurement method, and the tolerance threshold

  • Draft a communications management plan that specifies audience, message, channel, frequency, and owner for at least six communication events

  • Explain how the baseline is set and what formal change control is required once it exists

  • Complete 40 practice questions spanning initiation and planning and update your error log

Your checkpoint

A consolidated project management plan covering scope, schedule, cost, quality, risk, and communications, with a change control procedure section

Week 6

Project Execution, Monitoring and Control

  • Calculate schedule variance, cost variance, SPI, CPI, EAC, and ETC from a supplied set of earned value figures and interpret each result in plain language

  • Apply the critical path method to a scenario where an activity slips and determine the schedule impact, including float consumption

  • Perform a quality control review using a control chart or checklist and decide whether the process is in control

  • Run a risk reassessment and record two risks that changed status, with the response you would trigger

  • Describe how issue logs, change requests, and lessons learned feed back into the plan

Your checkpoint

An earned value analysis worksheet with at least six worked calculations, interpretations, and a one-paragraph status report written for a sponsor

Week 7

Project Execution, Monitoring and Control & Project Closure and Stakeholder Communication

  • Evaluate a change request end to end: impact on scope, schedule, cost, risk, and quality, plus the approve, reject, or defer recommendation

  • Design a stakeholder communication for a bad-news scenario (schedule slip or budget overrun) that states facts, impact, options, and a recommendation

  • Distinguish formal written, formal verbal, informal written, and informal verbal communication and match each to an appropriate situation

  • Prepare for closure by listing the acceptance criteria, transition activities, and documentation required to close the project

  • Complete 40 practice questions on execution, monitoring, control, and communication and review every logged error

Your checkpoint

A change request impact assessment plus a bad-news stakeholder communication package, each reviewed against a self-made rubric

Week 8

Project Closure and Stakeholder Communication

  • Produce a final project report covering objectives achieved, scope delivered, schedule and cost performance against baseline, and outstanding items

  • Write a lessons learned register with at least six entries classified by knowledge area and a recommended process improvement for each

  • Explain the difference between administrative closure and contract closure and list the inputs to each

  • Create a benefits realization handover note identifying who measures each benefit, when, and with what metric

  • Take two full-length timed practice exams and build a final review sheet of the 15 concepts you missed most often

Your checkpoint

A closure pack: final report, lessons learned register, benefits handover note, and a one-page personal weak-spot review sheet

Milestones

Week 2: Score at least 70% on a 40-question fundamentals set and show that every missed item has a written reason in the error log

Week 4: Produce a network diagram with a correct critical path and float values, verified by recalculating the path lengths independently

Week 6: Calculate all six earned value measures correctly on a fresh practice set with no reference to notes

Week 8: Score at least 75% on both timed full-length practice exams and show a shrinking error-log list compared with week 2