CIC Grade A Electrical Trade Test flashcards
CIC Grade A Electrical Trade Test · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Grade A scope
- Covers general-use electrical work up to 600 V plus special high-voltage work up to 7,000 V for certain installations; Grade B is limited to 600 V or less general-use work.
- Insulation resistance limit
- A 300 V or less circuit must read 0.1 MΩ or more with a 500 V insulation tester; 300 V to 750 V circuits require 0.2 MΩ or more.
- Voltage drop single-phase
- e = 2 × L × I × r, where L is one-way length in meters, I is current, and r is conductor resistance per meter; keep branch drop within 2%.
- Conduit fill 40% rule
- For three or more conductors, total conductor cross-sectional area must not exceed 40% of the conduit internal area; two conductors 33%, one conductor 53%.
- Three-way switch wiring
- A 3-way switch has a common terminal and two traveler terminals; the common connects to the source or load, and travelers run between the two switches.
- Grounding classes A C D
- A-class grounding applies to 400 V circuits and requires 10 Ω or less; C-class 100 Ω or less for 200 V; D-class 500 Ω or less for low-current 300 V circuits.
- Leakage breaker sensitivity
- Select 30 mA or less sensitivity for human protection on wet-location and outdoor circuits, and 200 mA or less for fire protection of circuits.
- Cable derating factors
- Multiply the base ampacity by the ambient temperature correction factor and the grouping factor for the number of circuits in the same raceway; never add them.
- Practical exam time limits
- The practical exam allows 40 minutes for the standard problem and 60 minutes for the composite problem; unfinished work is scored as incomplete.
- VVF cable ampacity
- A 2.0 mm² VVF cable in conduit carries about 24 A at 30 °C; a 1.6 mm² cable carries about 17 A; apply derating for higher ambient and grouping.
- Pilot lamp connection
- Connect the pilot lamp in parallel with the load so it indicates whether the load is energized; never connect it in series with the load.
- Firestop penetration rule
- Seal every penetration of a fire-rated wall or floor with a material rated for the same fire resistance as the wall or floor.
- Power factor correction formula
- Required capacitor kvar = P × (tan θ1 − tan θ2), where θ1 is the original angle and θ2 is the target angle.
- Cable bending radius
- For fixed low-voltage cable, keep the inner radius at 6 times the cable diameter or more; for movable or flexible cable, 4 times or more.
- Single-phase load current
- I = P / (V × power factor); for a 100 V, 1 kW load at unity power factor, the current is 10 A.
- Cable support spacing
- Support VVF cable at intervals of 2 m or less, and within 1 m of each box or fitting; in a vertical shaft, support at every floor.
- Grounding conductor sizing
- The grounding conductor must be at least the phase conductor up to 16 mm², and at least half the phase conductor for larger sizes, per the 内線規程.
- Switch height residential
- In Japanese residential practice, switches are about 1,200 mm above floor, outlets about 300 mm, and kitchen counter outlets about 1,000 mm above the counter.
- Three-phase load current
- I = P / (√3 × V × power factor); for a 200 V, 5 kW load at 0.8 power factor, the current is about 18 A.
- Conduit bend limit
- The total bend between pull points must not exceed 360 degrees, and every bend must be made with a bender to avoid kinking.
- Neutral and ground bars
- In a subpanel, the neutral bar and ground bar must be separate; they are bonded only at the main service panel.
- Cable tray fill limits
- The total cable cross-section must not exceed 40% of the tray's usable cross-section for power cables, and 50% for control cables.
- Transformer efficiency
- η = output / input × 100%; losses are copper loss, proportional to current squared, plus iron loss, which is constant.
- Emergency lighting duration
- Emergency lighting must maintain 30 minutes of illumination at 1 lx or more on the floor of the evacuation route, per the 消防法.
- Cable stripping lengths
- Strip about 15 mm for a ring sleeve and 10 mm for a push-in connector; exposed copper strands after termination are a defect.
- Switchboard working space
- Maintain at least 1.2 m of working space in front of a switchboard, and 0.8 m at the sides and rear where access is required.
- Motor overload relay setting
- A thermal overload relay in a magnetic contactor provides overload protection; set it to the motor's rated current.
- Grounding resistance measurement
- Use the fall-of-potential method with two auxiliary electrodes spaced at least 20 m apart for accurate results.
- Illuminance targets
- Required illuminance is about 100 lx for a living room, about 300 lx for a kitchen, and about 500 lx for an office.
- Cable color code
- In a three-phase system, black, red, and blue are the three phases, white is neutral, and green is ground; green is never a live conductor.
- Breaker coordination rule
- The breaker rating must be less than or equal to the cable's allowable current after derating, and greater than the load current.
- Insulation test voltage
- Use 500 V for 300 V or less circuits and 1000 V for 300 V to 750 V circuits; never use a higher voltage than the circuit rating.