CIC Grade A Electrical Trade Test study plan
CIC Grade A Electrical Trade Test · Give each week a clear focus.
8 weeks · About 7 hours per week
Construction-related E&M Trades
List every construction-related E&M trade discipline covered by the syllabus (conduit and trunking, cable tray, busbar, earthing, wiring accessories, lighting and power installation, cable jointing) and write a one-line scope note for each
Map each discipline to the Hong Kong wiring regulation clauses and code-of-practice sections that govern it, citing clause numbers from memory then verifying
Build a personal glossary of 60 trade terms in English with Chinese equivalents where the exam paper uses them
Solve 20 recall questions on trade scope and terminology and log wrong answers with the reason
Your checkpoint
A one-page discipline-to-regulation map plus a 60-term bilingual glossary file
Construction-related E&M Trades
Calculate conduit and trunking sizing for mixed power and final-circuit loads using the factor-of-fill rules
Compute voltage drop for single-phase and three-phase final circuits and select conductor sizes that satisfy the 4% and 2.5% limits
Size protective devices against cable current-carrying capacity after applying grouping, ambient temperature, and thermal insulation correction factors
Work 15 numerical installation-design problems under timed conditions and mark them against the worked method
Your checkpoint
A worked solutions booklet of 15 cable-sizing and voltage-drop problems with correction factors shown line by line
Construction-related E&M Trades
Draft a method statement and risk assessment for a live-testing and cable-pulling activity on a construction site
Sequence a typical ceiling-void containment and containment-to-equipment wiring installation from first fix to testing
Identify coordination points between electrical, HVAC, plumbing, and fire services trades in a shared ceiling void and state who moves first and why
Explain permit-to-work, isolation, and lockout-tagout steps for working near existing live installations
Your checkpoint
A two-page method statement with risk assessment and trade-coordination sequence chart for one installation activity
Construction-related E&M Trades & Trade Test for Grade A Electrical Work
Review weeks 1-3 notes and re-solve every previously missed calculation without reference to the answers
List the statutory and regulatory framework for Grade A electrical work, including the registration categories and the scope each category permits
State the duties of the registered electrical worker and contractor for design, installation, inspection, testing, and certification
Complete a 40-question mixed mock on Domain 1 plus regulatory basics and score it
Your checkpoint
A mid-point mock score report showing per-topic accuracy and a list of the three weakest topics to carry forward
Trade Test for Grade A Electrical Work
Describe the inspection and testing sequence for a new installation from visual inspection through to certification, naming each test in order
Explain insulation resistance, earth continuity, polarity, ring-circuit continuity, and earth fault loop impedance tests, including instrument type, test voltage, and pass criteria
Perform and record a full set of test results for a simulated single-phase and three-phase board on paper
Interpret residual current device trip times and explain when a test result requires investigation
Your checkpoint
A completed test certificate and schedule of test results for a simulated installation, with pass or fail verdicts on every reading
Trade Test for Grade A Electrical Work
Apply the requirements for earthing and bonding, including main equipotential bonding sizing and supplementary bonding conditions
Specify protective device types and ratings for given loads and justify discrimination and backup protection choices
Explain the classification of hazardous areas and the equipment selection rules that follow from each zone
Answer 20 scenario questions on protection, earthing, and special installations and justify each answer in two sentences
Your checkpoint
A justification sheet for 20 protection and earthing scenarios, each with the governing requirement cited
Trade Test for Grade A Electrical Work
Diagnose ten written fault scenarios (nuisance tripping, high loop impedance, reversed polarity, lost neutral, overheating joint) and state the test that confirms each diagnosis
Summarise periodic inspection requirements, sampling rates, and the categories of observation codes used in reports
Explain the documentation set required on completion: certificate, test schedule, as-installed drawings, and operation and maintenance manual
Complete a 40-question mock weighted 50/50 across both domains under exam timing
Your checkpoint
A fault-diagnosis table of ten scenarios plus a timed mock score with a written review of every error
Construction-related E&M Trades & Trade Test for Grade A Electrical Work
Re-drill all flagged weak topics from weeks 4 and 7 using short focused question sets until accuracy exceeds 80%
Recite the key regulation limits, correction factor tables, and test pass criteria from memory in a single self-written one-page crib sheet
Sit two full-length timed papers under exam conditions and compare scores for consistency
Finalise an exam-day plan covering time allocation per section, question-skipping rules, and calculation checking routine
Your checkpoint
Two full-length timed mock scores plus a one-page handwritten crib sheet covering all memorised limits and criteria
Milestones
Week 2: Score at least 70% on the 15 timed cable-sizing and voltage-drop problems, with every correction factor correctly applied
Week 4: Score at least 65% on the 40-question mixed mock and name the three weakest topics with evidence from the score report
Week 6: Produce a complete test certificate with correct pass or fail verdicts on all readings and cite the governing requirement for all 20 protection scenarios
Week 8: Score at least 75% on both full-length timed papers and reproduce the crib sheet from memory with no more than three omissions