ICBB · Keep the key ideas within reach.

Quick reference

Define

  • Project charter scope: a Six Sigma project addresses one problem, one metric (Y), and a bounded process; multi-Y charters are split before Measure begins.

  • Voice of the Customer translates to Critical to Quality (CTQ) requirements; each CTQ needs an operational definition, a metric type (continuous, discrete), and a specification limit or target.

  • SIPOC maps Suppliers, Inputs, Process (4-7 high-level steps), Outputs, Customers; it defines project boundaries and is not a detailed process map.

  • Cost of Poor Quality categories: internal failure, external failure, appraisal, prevention; COPQ is used to justify project selection and prioritize improvement.

  • SMART goal test: Specific, Measurable, Achievable, Relevant, Time-bound; the goal states the baseline, target, and date (e.g., reduce defects from 8% to 2% by Q4).

  • Pareto principle (80/20): a small set of causes produces most defects; Pareto charts rank categories descending and drive project focus.

  • Kano model classifies features as must-be, performance, and delighter; must-be features are unspoken and cause dissatisfaction only when missing.

  • Team roles: Champion sponsors and removes barriers, Black Belt leads the DMAIC project, Green Belt supports part-time, Process Owner sustains the control plan after handover.

  • Project financials: hard savings are measurable budget or cost reductions; soft savings are avoided costs or capacity gains and require finance sign-off.

Quick reference

Measure

  • Data types: continuous (variable) data uses Xbar-R, Xbar-S, I-MR charts; discrete (attribute) data uses p, np, c, u charts.

  • p chart plots proportion defective with varying subgroup size; np chart plots number defective with constant subgroup size; c chart counts defects per unit with constant opportunity; u chart counts defects per unit with varying opportunity.

  • MSA for continuous data: Gage R&R reports %Study Variation and %Tolerance; under 10% acceptable, 10-30% conditional, over 30% unacceptable.

  • Attribute agreement analysis reports within-appraiser and between-appraiser agreement; kappa below 0.70 indicates weak agreement beyond chance.

  • Process capability: Cp = (USL - LSL) / 6s measures potential; Cpk = min((USL - mean), (mean - LSL)) / 3s measures actual centering; Cpk is always less than or equal to Cp.

  • Pp and Ppk use the overall standard deviation; Cp and Cpk use within-subgroup sigma; Ppk is generally lower than Cpk when the process drifts.

  • Sigma level from DPMO: 1.5 sigma shift convention means 3.4 DPMO equals 6 sigma; 66,807 DPMO equals 4 sigma; 6,210 DPMO equals 4.5 sigma.

  • Sample size for a mean: n = (z * s / E)^2, where E is the desired margin of error; doubling precision requires four times the sample.

  • Measurement system resolution must be at most one-tenth of the tolerance range (10:1 rule) or the system cannot detect process variation.

Quick reference

Analyze

  • Hypothesis test decision rule: p-value less than alpha rejects the null hypothesis; alpha is the Type I error rate (false alarm), beta is the Type II error rate (missed effect).

  • Power = 1 - beta; power increases with larger effect size, larger sample size, and lower alpha; 80% power is a common planning minimum.

  • Test selection: 1-sample t for one mean, 2-sample t for two independent means, paired t for before/after on the same units, 1-proportion test for one defect rate.

  • ANOVA tests equality of three or more means; F = between-group variance / within-group variance; a significant F requires post-hoc comparison (Tukey) to find which groups differ.

  • Chi-square tests association between two categorical variables; expected cell counts should be at least 5 for validity.

  • Regression: R-squared is the proportion of variation explained; check residual plots for randomness, and inspect p-values of individual predictors for significance.

  • Correlation coefficient r ranges from -1 to 1; correlation does not establish causation, and a lurking variable can drive both variables.

  • Multi-Vari study stratifies variation into within-unit, between-unit, and temporal (lot-to-lot, shift) components to locate dominant variation sources.

  • FMEA: Risk Priority Number = Severity x Occurrence x Detection; act first on high-severity items regardless of RPN ranking.

Quick reference

Improve

  • DOE screening designs: full factorial runs 2^k; fractional factorial 2^(k-p) reduces runs at the cost of confounding (aliasing) main effects with interactions.

  • Resolution III designs confound main effects with two-factor interactions; Resolution IV confound two-factor interactions with each other; Resolution V confound two-factor interactions with three-factor interactions.

  • PDCA (Plan-Do-Check-Act) is the Deming cycle; in DMAIC, Improve pilots the change (Do) and verifies results before Control standardizes it.

  • Lean waste categories: overproduction, waiting, transport, overprocessing, inventory, motion, defects, plus unused talent.

  • 5S sequence: Sort, Set in order, Shine, Standardize, Sustain; it is a workplace organization method applied to stabilize the improved process.

  • Poka-yoke is error-proofing that prevents or detects defects at the source; devices can be prevention-based (contact, fixed-value) or detection-based.

  • Kaizen is continuous incremental improvement by the people doing the work; kaizen events are short, focused, cross-functional workshops.

  • Pilot selection: run the improvement on a limited scope with measurable baseline and exit criteria before full deployment to limit risk.

Quick reference

Control

  • Control plan elements: process step, characteristic and specification, measurement method, sample size and frequency, control method, and reaction plan with owner.

  • SPC chart selection: use I-MR for individual measurements, Xbar-R for subgroups of 2-9, Xbar-S for subgroups of 10 or more, p or u for attribute data.

  • Control limits are set at mean plus or minus 3 sigma from process data, not from specification limits; specification limits belong to the customer.

  • Western Electric rules: 1 point beyond 3 sigma, 2 of 3 beyond 2 sigma, 4 of 5 beyond 1 sigma, 8 consecutive points on one side of the centerline signal special cause.

  • Process behavior: a process in statistical control with Cpk below 1.0 requires fundamental process change, not tighter monitoring.

  • Standardization documents: updated work instructions, control charts, reaction plans, and a response owner are required for handover to the process owner.

  • Ongoing verification uses audits, control chart review, and periodic capability re-checks (Cpk, Ppk) to confirm gains are sustained.

  • Mistake-proofing in Control: add detection or prevention devices so the failure mode cannot recur without operator vigilance.

  • Project closure requires documented savings verified by finance, lessons learned, and transfer of the control plan to the process owner.