ICC E3 study plan
ICC E3 · Give each week a clear focus.
8 weeks · About 7 hours per week
Electrical Code and Plan Review Fundamentals
Map the code book structure: locate chapters, article numbering, and the difference between mandatory and permissive rules
Practice navigating to 10 randomly chosen articles within 90 seconds each using only the index and table of contents
Distinguish wiring methods, conductor types, and standard plan-sheet symbols by writing definitions in your own words
Identify the plan-review sequence: scope, occupancy classification, load assumptions, then compliance checks
Your checkpoint
A one-page code-navigation cheat sheet listing chapter topics plus 10 timed lookup results
Electrical Code and Plan Review Fundamentals & Branch Circuits, Feeders, and Service Calculations
Translate a simple floor plan into a branch-circuit layout with receptacle and lighting outlet placements
Apply general-purpose receptacle spacing and small-appliance circuit rules to two sample rooms
Compute demand factors for general lighting loads using the standard table method
Explain when a plan reviewer would reject a layout and cite the governing rule category
Your checkpoint
A marked-up sample floor plan with circuit assignments and a written justification memo for each circuit
Branch Circuits, Feeders, and Service Calculations
Calculate branch-circuit conductor sizing for continuous and noncontinuous loads
Size overcurrent devices for a feeder serving mixed loads using demand factors
Perform a full single-dwelling service calculation from a load inventory sheet
Check voltage-drop implications for a long feeder run and document the method
Your checkpoint
A completed service-calculation worksheet for a sample dwelling with every step shown
Branch Circuits, Feeders, and Service Calculations & Grounding, Bonding, and Overcurrent Protection
Size equipment grounding conductors and grounding electrode conductors for three sample services
Select overcurrent protection ratings that satisfy conductor ampacity and load requirements simultaneously
Identify the correct bonding points for service equipment, panels, and metallic piping systems
Distinguish grounding from bonding in written explanations for five scenarios
Your checkpoint
A grounding-and-bonding diagram for a sample service with conductor sizes labeled and a short rationale for each choice
Grounding, Bonding, and Overcurrent Protection
Apply overcurrent protection coordination concepts to a feeder-and-panel arrangement
Determine when ground-fault and arc-fault protection is required for given occupancies
Evaluate a plan reviewer's rejection of a grounding detail and write the corrected detail
Size and locate a grounding electrode system for a structure with multiple electrodes
Your checkpoint
A written review of three flawed grounding/OCPD details with corrected drawings and code-category citations
Special Occupancies, Equipment, and Plan Review Administrative Provisions
Classify occupancies and identify the special rules that change wiring requirements for each
List the extra requirements for hazardous locations, healthcare, and assembly occupancies at a survey level
Apply plan-review administrative provisions: submittal completeness, revision tracking, and approval conditions
Draft a deficiency notice that is specific, actionable, and references the applicable rule category
Your checkpoint
A deficiency-notice template plus three completed notices for a sample special-occupancy submittal
Electrical Code and Plan Review Fundamentals & Special Occupancies, Equipment, and Plan Review Administrative Provisions
Run a full plan review of a multi-page sample set from intake to written findings
Prioritize deficiencies by safety severity and document the reasoning
Reconcile conflicting details between architectural and electrical sheets
Verify that special-occupancy requirements are reflected in the submitted drawings
Your checkpoint
A complete plan-review report on a sample drawing set with prioritized findings and a pass/conditional/fail recommendation
Branch Circuits, Feeders, and Service Calculations & Grounding, Bonding, and Overcurrent Protection & Special Occupancies, Equipment, and Plan Review Administrative Provisions
Complete timed practice sets across all four domains and log error patterns by category
Re-derive the two most error-prone calculations from memory without notes
Review every missed item and write the underlying rule in your own words
Build a final one-page summary of the highest-yield rules per domain
Your checkpoint
A scored practice-exam log with an error-pattern analysis and a personal one-page high-yield summary
Milestones
Week 2: Can locate any requested article within 90 seconds and correctly assign circuits on a sample plan without notes
Week 4: Completes a full dwelling service calculation and a grounding/bonding diagram with no more than one arithmetic error
Week 6: Writes three deficiency notices that each name the rule category and a specific corrective action
Week 8: Scores at or above 75% on a timed mixed-domain practice set with every missed item re-explained in writing