ICC Masonry Inspector S2 · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Masonry Materials and Construction Practices

  • Map the masonry materials landscape: list mortar types (M, S, N, O, K) with their cement-lime proportions and typical compressive strengths from memory

  • Explain the difference between Type N and Type S mortar and state where each is required or prohibited for structural and veneer applications

  • Describe the properties and permitted uses of clay brick, concrete masonry units (CMU), and natural stone, including absorption and compressive strength ranges

  • Identify mortar ingredients (portland cement, lime, sand, water, admixtures) and state the code limits on admixture use

Your checkpoint

A one-page mortar and unit reference table (type, proportion, strength, permitted use) written from memory, then corrected against your study sources

Week 2

Masonry Materials and Construction Practices

  • Sequence a typical masonry wall assembly from foundation to flashing to veneer, naming each component and its function

  • Explain the purpose and placement of flashing, weeps, and the air/moisture barrier in cavity and veneer walls

  • Describe anchor, tie, and reinforcement types (joint reinforcement, wall ties, anchors) and state spacing rules you can recall

  • Distinguish reinforced, unreinforced, and veneer wall behavior under lateral load

Your checkpoint

A hand-drawn cross-section of a cavity wall labeled with at least 12 components and their code-referenced spacing or placement rules

Week 3

Masonry Materials and Construction Practices & Inspection Procedures and Testing

  • List the field tests and inspections that occur before, during, and after masonry placement (prism tests, mortar/grout sampling, slump, and compressive strength)

  • Explain how mortar and grout specimens are prepared, cured, and evaluated against acceptance criteria

  • Describe prism testing versus unit-and-mortar testing and when each is used

  • Identify common workmanship defects (poor bed joints, inadequate overlap, missing weeps) and how an inspector documents them

Your checkpoint

A testing matrix listing each test, when it is performed, the specimen type, and the acceptance basis, with at least 8 rows

Week 4

Plan Review and Permits & Inspection Procedures and Testing

  • Read a set of masonry construction documents and identify the structural drawings, architectural drawings, and specifications that govern masonry

  • Trace how a plan reviewer confirms that masonry details match the code requirements for the occupancy and construction type

  • Explain the permit application process: what submittals are required, who reviews them, and what triggers a resubmittal

  • Describe how inspection records, special inspection reports, and final approvals feed back into the permit file

Your checkpoint

A mock plan-review checklist covering at least 15 items an inspector would verify before issuing a masonry permit

Week 5

Plan Review and Permits & Code Administration and Enforcement

  • Explain the role of the building official and the inspector in code administration, including authority to approve, condition, or deny permits

  • Describe the inspection request, notification, and sign-off workflow from footing to final

  • Identify the difference between a code violation, a plan deficiency, and a construction defect and how each is handled

  • Outline the process for stop-work orders, notices of violation, and appeals

Your checkpoint

A one-page flowchart of the permit-to-certificate-of-occupancy workflow with the inspector's decision points marked

Week 6

Code Administration and Enforcement

  • Summarize the administrative provisions that govern enforcement: permit validity, expiration, revocation, and re-inspection fees

  • Explain how referenced standards (masonry materials, testing, and construction standards) are adopted by reference into the code

  • Distinguish the inspector's authority from the contractor's responsibility for means and methods

  • Describe documentation practices for inspection reports, corrections, and follow-up verification

Your checkpoint

A written scenario response (250+ words) describing how you would handle a noncompliant mortar mix found mid-project, from observation to closure

Week 7

Masonry Materials and Construction Practices & Plan Review and Permits & Inspection Procedures and Testing & Code Administration and Enforcement

  • Work through mixed-topic practice questions across all four domains and log every miss by domain and reason

  • Re-study your two weakest subtopics using targeted notes rather than full rereads

  • Practice explaining a masonry detail aloud as if briefing a contractor, in under two minutes

  • Review code-administration definitions and terms you have been guessing at

Your checkpoint

A scored 60-question practice set with a written error log identifying the domain and root cause for each miss

Week 8

Masonry Materials and Construction Practices & Plan Review and Permits & Inspection Procedures and Testing & Code Administration and Enforcement

  • Re-take a full-length timed practice exam and compare domain scores to week 7

  • Drill the highest-frequency misses from your error log until you can answer without hesitation

  • Recite the key numeric thresholds (mortar strengths, tie spacing, test frequencies) from memory

  • Finalize a one-page personal cheat sheet limited to facts you repeatedly missed

Your checkpoint

A timed full-length practice exam score report plus a finalized one-page cheat sheet of your remaining weak facts

Milestones

Week 2: Can label a cavity wall cross-section with 12+ components and state the placement rule for each without notes

Week 4: Can walk through a permit submittal and name the review checkpoints and required documents from memory

Week 6: Can explain the enforcement workflow for a violation, including stop-work, notice, and appeal, in under five minutes

Week 8: Timed practice exam score is at or above your target passing margin, with no single domain below 70%