ICC Reinforced Concrete SI flashcards
ICC Reinforced Concrete SI · Build recall with a focused review session.
32 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Purpose of concrete inspection
- To observe materials, placement, and workmanship and judge whether the work conforms to the plans and specifications. It supplements, but does not replace, the contractor's own quality control program.
- Minimum clear bar spacing
- For parallel bars in a layer, clear spacing must be at least the larger of one bar diameter, 1.33 times the maximum coarse aggregate size, or 25 mm.
- Cover measurement
- Cover is the clear distance from the concrete surface to the outermost reinforcement. Measure to the bar or stirrup closest to the surface, not to an inner bar.
- Formwork pre-pour check
- Verify line, grade, dimensions, tight joints, release agent, ties, and shores. Forms must be clean and free of debris and standing water before placement begins.
- Cold-weather placement
- Concrete should be placed at a temperature specified for the project, commonly at least 10 °C, and protected until it reaches specified strength. Never place on frozen subgrade.
- Hot-weather concrete limits
- Concrete temperature as placed is commonly limited to about 35 °C. Cooling ingredients, set retarders, and immediate curing reduce plastic shrinkage cracking and rapid moisture loss.
- Slump test (ASTM C143)
- Measures consistency of fresh concrete. A collapsed or sheared slump is invalid and the sample must be retested. Slump is not a measure of strength or durability.
- Air content by pressure method
- ASTM C231 measures entrained air in fresh concrete. Freeze-thaw exposure typically requires about 5–7 percent air with 20 mm aggregate, adjusted for the exposure class.
- Water-cementitious materials ratio
- The ratio of water to cementitious material by mass. Lower w/cm increases strength and reduces permeability; it is the primary control on concrete quality.
- Cylinder curing per ASTM C31
- Standard-cured cylinders are moist cured at controlled temperature and represent the mix. Field-cured cylinders are stored near the structure and represent in-place strength.
- Strength test sampling frequency
- Take a test set at least once per day of placement, once per 110 m³ or fraction, and once per 460 m² of slab or wall. Each set consists of two cylinders.
- Consolidation with vibrator
- Insert the vibrator vertically at regular spacing and hold until air bubbles cease, then withdraw slowly. Never use vibration to move concrete laterally in the form.
- Curing duration
- Maintain moisture and temperature for the specified period, commonly 7 days for Type I cement and 3 days for high-early-strength cement, unless the specification states otherwise.
- Construction joint preparation
- Planned joints must be cleaned, roughened, and often fitted with shear keys or dowels. Unplanned cold joints from interruptions are defects and should be reported.
- Free fall limit
- Concrete should be placed near its final position; free fall is commonly limited to about 1.5 m to prevent segregation. Use chutes or drop pipes for deeper placements.
- Bar number to diameter
- For metric deformed bars, the bar number times 3 gives nominal diameter in mm. No. 20 is 20 mm diameter; No. 25 is 25 mm diameter.
- Bar number to area
- For metric deformed bars, the bar number times 100 gives nominal area in mm². No. 20 has about 300 mm²; No. 25 has about 500 mm².
- Common bar grade
- Grade 420 MPa (formerly Grade 60) is the common deformed bar grade. Grade 550 MPa (Grade 80) is used where higher strength is specified.
- Class A and Class B splices
- Tension lap splices are Class A (1.0 times development length) or Class B (1.3 times development length). The class depends on the fraction of steel spliced and the stress level.
- Minimum development length
- Tension development length depends on bar size, cover, spacing, transverse reinforcement, and concrete strength. It is never less than 300 mm.
- Standard 90-degree hook
- A standard 90° hook has a minimum extension of 12 bar diameters beyond the bend. Hook geometry and bend diameter vary with bar size.
- Mechanical and welded splices
- Mechanical splices must be qualified by test. Welded splices require a qualified welding procedure and welder, and are not permitted for all bar grades.
- Post-tensioning
- Strands in ducts are stressed after the concrete hardens and the force is transferred through anchorages. Ducts are grouted after stressing to protect the steel.
- Pretensioning
- Strands are stressed before concrete is placed and force is transferred to the concrete by bond when the strands are released. Used mainly in precast members.
- Stressing force verification
- Tendon force is checked by both elongation and gauge pressure; the two must agree within a specified tolerance, commonly about 5 percent. Discrepancies are investigated before grouting.
- Duct grouting
- Post-tensioning ducts are grouted promptly after stressing with an approved grout. Vents at high points ensure complete filling; incomplete grouting is a corrosion risk.
- Bar schedule on drawings
- The bar schedule lists bar marks, sizes, shapes, lengths, and quantities. The inspector checks field placement and splices against the approved placing drawings.
- Cover for exposed members
- Cast-in-place beams and columns exposed to earth or weather commonly require at least 40 mm cover. Verify the exact value against the project specification and exposure class.
- Two-layer bar arrangement
- When bars are placed in two or more layers, bars in the upper layer are placed directly above those in the lower layer, with the required clear spacing maintained.
- Strength acceptance criteria
- The average of three consecutive strength tests must equal or exceed the specified strength, and no single test may fall below a specified lower threshold. Failing results trigger investigation.
- Core testing after failure
- When cylinder tests fail, the engineer may require cores per ASTM C42 from representative locations. Core results are evaluated against specified acceptance criteria.
- Governing code documents
- ACI 318 covers structural design and detailing; ACI 301 covers construction specifications; ACI 302 covers slabs on grade. Project specifications govern where they conflict with general references.