ICC Reinforced Concrete SI study materials
ICC Reinforced Concrete SI study resources

ICC Reinforced Concrete SI study plan

ICC Reinforced Concrete SI · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Reinforced Concrete Inspection & Concrete Materials and Placement

  • Map the four exam domains to the inspection tasks you already perform on site, and list which tasks belong to each domain

  • Define the inspector's role and authority limits before and during concrete placement, including stop-work triggers

  • Identify the standard test methods for fresh concrete (slump, air content, temperature, unit weight, strength specimens) and state what each one verifies

  • Read the acceptance criteria for each fresh-concrete test and explain what happens when a result falls outside tolerance

Your checkpoint

A one-page table listing each fresh-concrete field test, its standard designation, sampling frequency, acceptance limit, and the inspector action when the limit is exceeded

Week 2

Concrete Materials and Placement & Reinforced Concrete Inspection

  • Sequence the pre-placement checklist: formwork, embedded items, reinforcement cover, joint preparation, and placement readiness sign-off

  • Describe proper consolidation technique with internal vibrators and identify the defects caused by under- and over-vibration

  • Explain curing methods, curing duration requirements, and how to verify curing is being maintained in the field

  • Distinguish hot-weather and cold-weather placement precautions and the conditions that require suspension of placement

Your checkpoint

A completed pre-placement inspection checklist applied to one real or realistic placement scenario, with each item marked pass, fail, or not applicable and a note on the corrective action for any fail

Week 3

Concrete Materials and Placement & Reinforced Concrete Inspection

  • Classify concrete deterioration mechanisms (freeze-thaw, sulfate attack, alkali-silica reaction, carbonation, chloride ingress) and match each to its visible field symptom

  • Explain the purpose of air entrainment, water-cementitious ratio limits, and supplementary cementitious materials in durability performance

  • Evaluate sampling and testing frequency requirements against a given pour volume and produce the required number of specimens

  • Interpret cylinder break results against specified compressive strength and identify when low-strength investigation is triggered

Your checkpoint

A worked strength-test evaluation for a pour of at least 100 cubic yards, showing required specimen count, test ages, and a written pass/fail determination with justification

Week 4

Reinforced Concrete Inspection & Code Compliance and Plan Reading

  • Locate and interpret the general notes, specifications, and structural drawings that govern reinforcement placement on a project

  • Verify bar size, bar spacing, bar count, and lap splice length against the placing drawings and the governing code provisions

  • Check cover requirements for cast-in-place members exposed to different conditions and confirm cover with a cover meter or physical measurement

  • Explain the inspector's documentation duties: daily reports, nonconformance reports, and photo records

Your checkpoint

A reinforcement verification log for one beam and one column, recording specified versus observed bar size, spacing, count, lap length, and cover, with every discrepancy flagged

Week 5

Reinforcement and Prestressing & Code Compliance and Plan Reading

  • Identify standard bar markings, bar sizes, and grades, and verify mill certificates against delivered reinforcement

  • Describe handling, storage, and protection requirements for reinforcement and the conditions that require rejection of delivered material

  • Explain the difference between development length, lap splice, and mechanical splice requirements and where each applies

  • Describe the inspection points for post-tensioning: tendon placement, anchorage zone reinforcement, stressing records, and grouting

Your checkpoint

A reinforcement receiving and placement inspection procedure covering delivery verification through final pre-pour sign-off, with the specific check at each step

Week 6

Reinforcement and Prestressing & Concrete Materials and Placement

  • Explain prestressing fundamentals: pre-tensioning versus post-tensioning, and the role of prestress in controlling deflection and cracking

  • Verify tendon profile, drape, and anchorage locations against the shop drawings and identify common placement errors

  • Describe concrete requirements specific to prestressed members, including strength at transfer and elongation tolerance

  • Interpret stressing records and elongation measurements and determine whether the results fall within acceptable range

Your checkpoint

A written review of a stressing record and elongation calculation showing measured versus calculated elongation, percent deviation, and a recommendation to accept or investigate

Week 7

Code Compliance and Plan Reading & Reinforced Concrete Inspection

  • Read a reinforced concrete framing plan and identify member sizes, reinforcement callouts, and section references without assistance

  • Cross-check a detail section against the plan callout and identify conflicting or missing information

  • Apply code provisions on lap splices, cover, and bar spacing to a specific member and document the code basis for each determination

  • Produce a nonconformance report for a code violation found on a drawing or in the field, including the code reference and required corrective action

Your checkpoint

A plan-reading exercise on one framing plan and two detail sections, producing a list of every reinforcement callout with its code basis and at least one documented discrepancy

Week 8

Reinforced Concrete Inspection & Concrete Materials and Placement & Reinforcement and Prestressing & Code Compliance and Plan Reading

  • Complete timed practice sets across all four domains and score each domain separately

  • Identify the two weakest domains from practice scores and re-study only those topics

  • Recall from memory the key acceptance limits, test frequencies, and code thresholds without reference material

  • Build a personal one-page reference sheet of the facts you most often miss

Your checkpoint

A full-length timed practice exam with a domain-by-domain score breakdown and a written remediation list for any domain scoring below 75 percent

Milestones

Week 2: Can list every fresh-concrete field test with its acceptance limit and explain the inspector's action when a limit is exceeded, without notes

Week 4: Can verify bar size, spacing, lap length, and cover on a beam and column from drawings and record discrepancies in a proper log format

Week 6: Can explain pre-tensioning versus post-tensioning and evaluate a stressing record for elongation tolerance

Week 8: Scores at least 75 percent in every domain on a full-length timed practice exam and has a written remediation list for remaining gaps