Health, Safety and Welfare in Roof Felting Work

  • Work at height hierarchy: avoid work at height, prevent falls using collective measures, then mitigate residual risk with personal protective equipment.

  • The Work at Height Regulations require a risk assessment and a written plan for every roof felting job; rescue and emergency arrangements must be planned before work starts.

  • Hot-works control: gas torch work needs a permit, a fire watch during work and a minimum 60-minute post-work fire watch, with two suitable extinguishers on the roof.

  • Liquid petroleum gas cylinders must be stored upright, secured, away from ignition sources and never inside a building or below ground level.

  • Bitumen fume is a respiratory and skin sensitiser; local exhaust ventilation, cooler torch settings and correct RPE reduce exposure.

  • Welfare facilities on site: drinking water, washing facilities, sanitary conveniences and a means of drying wet clothing must be provided.

  • A 2-metre fall can cause fatal head injury; edge protection or a fall-arrest system is required where a person could fall 2 m or more.

  • Manual handling: two-person lifts for rolls over 20 kg; rolls should be carried on a barrow or hoist, not shoulder-carried up ladders.

Quick reference

Roof Felting Materials, Components and Specifications

  • Membrane types: BS EN 13707 reinforced bitumen membranes; torch-on APP (plasticised) and SBS (elastomeric) are the two main polymer-modified bitumen classes.

  • APP membranes resist high temperatures and UV better than SBS; SBS is more flexible at low temperature and better for cold or movement-prone roofs.

  • Membrane designation uses a letter code: e.g. a 4 mm SBS torch-on cap sheet is often specified as a two-layer system with a base sheet beneath.

  • Mineral-surfaced cap sheets provide UV resistance and slip resistance; sanded or foil finishes are used for underlays or reflective detail work.

  • Vapour control layers (VCL) are specified where warm-roof construction requires control of interstitial condensation; a typical VCL is a bitumen or polyethylene membrane.

  • Insulation for warm roofs: PIR or PUR boards typically laid over the deck, with a separate VCL below and membrane above.

  • Fasteners and accessories: membrane-lined edge trims, drip trims, upstand termination bars, outlet and penetration collars, and adhesive or torch-bonded laps.

  • Lap widths: side laps typically 80–100 mm and end laps 100–150 mm for torch-on reinforced membranes, unless the manufacturer states otherwise.

Quick reference

Preparation, Substrate and Surface Assessment

  • Substrate moisture content must be checked before felting; trapped moisture causes blistering and premature failure of torch-on membranes.

  • Timber decking: boards should be close-butted, fixed to joists, free from deflection and have a maximum gap per specification (commonly 3–6 mm).

  • Concrete decks must be dry, sound and free of laitance; a primer or bonding agent is applied before the first layer.

  • Metal decking requires a suitable deck profile and a separating or vapour-control layer before the membrane is applied.

  • Existing felt removal: strip back to a sound substrate unless an overlay system is specified; overlay requires a mechanically fixed or bonded carrier board.

  • Surface preparation includes cleaning, degreasing and removing loose aggregate; primers cure before the membrane is laid.

  • Fall assessment: check the finished fall (typically 1:40 to 1:80 for flat roofs) and confirm ponding risk before work starts.

  • Roof edge and upstand dimensions are checked against drawings before setting out the membrane layout.

Quick reference

Installation of Felting Systems and Waterproofing Layers

  • Torch-on technique: heat the membrane underside and substrate together until the bitumen is molten, then roll and press to expel air and achieve a continuous 10–20 mm bleed at laps.

  • Lap sequence: side laps should face the direction of water flow and be laid so water runs over, not into, the lap.

  • Stagger end laps of adjacent rolls; end laps of successive layers must be offset to avoid aligned joints.

  • Two-layer systems: base sheet is laid first (often partially bonded or mechanically fixed), then the cap sheet fully bonded over it.

  • Mechanical fixing of the base sheet uses washers and screws at the specified density; the cap sheet is then torch-bonded over the fixings.

  • Membrane should be laid at right angles to the fall on flat roofs, starting at the lowest point, so water flows over laps.

  • Avoid over-torching: scorched or burnt-through membrane and exposed reinforcement are defects that must be cut out and replaced.

  • Ambient temperature and wind affect torch work; membrane should not be applied in wet conditions or below the manufacturer's minimum temperature.

Quick reference

Detail Work: Edges, Upstands, Outlets and Penetrations

  • Upstands: membrane should turn up a minimum of 150 mm above the finished roof surface, with a termination bar or chased-in edge fixing.

  • Upstand height above finished surface must also account for any insulation, screed and paving; check the drawing detail, not just the deck.

  • Edge details: drip trims or edge trims are fixed before the membrane is dressed over and bonded to the trim.

  • Rainwater outlets: outlet collars and outlets are installed before the main membrane so the membrane can be dressed into the outlet flange.

  • Penetrations: pipes and flues require a collar or sleeve with a minimum 150 mm upstand and a weathertight seal at the top of the collar.

  • Internal corners and changes of direction need a reinforcement layer or a preformed angle piece before the cap sheet is applied.

  • Parapet and wall abutments: use a chased-in edge or a termination bar with a sealant bead at the top edge to prevent water tracking behind the membrane.

  • Expansion joints and movement joints require a movement-joint detail with a compatible flexible membrane, not a rigid lap.

Quick reference

Tools, Equipment and Safe Working at Height

  • Core tools: gas torch with regulator and hose, seam roller, trowel, knife, chalk line, measuring tape, and a nail or screw gun for fixing.

  • Gas torch safety: check hoses and regulators before use, use a flashback arrestor, and never leave a lit torch unattended.

  • Edge protection: guardrails at 950 mm and 470 mm heights with toe boards are typical collective fall-prevention measures.

  • Fall-arrest systems must be anchored to a suitable anchor point and used with a rescue plan; a harness is a last line of defence, not primary protection.

  • Roof ladders and crawl boards: ladders must be secured, extend 1 m above the landing point, and be used at the correct 1-in-4 angle.

  • Fragile roof surfaces (roof lights, asbestos cement sheets) require a risk assessment and suitable crawling boards or staging.

  • Hot-works equipment should be inspected and PAT tested; extension leads and transformers must be kept clear of the torch and water.

  • Weather monitoring: stop work in high winds, heavy rain or lightning; wind can lift membrane and torch flames are a fire hazard.

Quick reference

Inspection, Testing, Defects and Repair

  • Visual inspection: check for blisters, wrinkling, fishmouths, open laps, exposed reinforcement, and insufficient or excessive bleed at laps.

  • Lap integrity testing: probe or peel tests on sample laps confirm bonding; open laps are re-heated, pressed and re-rolled.

  • Water test: flood test or hose test on completed areas before handover; ponding indicates inadequate fall or a low point.

  • Blistering causes: trapped moisture, insufficient priming, or over-heating; repair by cutting out and patching with a lapped patch.

  • Wrinkling causes: membrane laid too loosely, uneven substrate, or thermal movement; repair by cutting and re-laying if structural.

  • Ponding water in excess of 5 mm after 24 hours of drying is a defect; the fall or outlet should be investigated.

  • Repair method: cut back to sound membrane, clean and prime, then apply a patch extending at least 100 mm beyond the defect, fully bonded and lapped.

  • Record inspection results with photographs, location references and dates; the handover pack should include guarantees and maintenance instructions.