CSCS Mobile Tower study materials
CSCS Mobile Tower study resources

CSCS Mobile Tower cheat sheet

CSCS Mobile Tower · Keep the key ideas within reach.

Quick reference

Site Safety and Risk Assessment for Tower Operations

  • Risk assessment must be completed before any tower assembly, use, or dismantling; it must identify hazards, assess risks, and define control measures.

  • Exclusion zones must be established around the tower base and any area where loads may fall; zone radius is typically at least 1.5 times the tower height unless a documented engineering assessment specifies otherwise.

  • Ground conditions must be verified by a competent person to ensure the tower foundation can support the maximum load, including wind loading; soft ground requires spreader plates or concrete foundations.

  • Wind speed must be monitored; operations must stop when wind speed exceeds the manufacturer's limit (often 20 mph or 8.9 m/s for assembly/dismantling, and 28 mph or 12.5 m/s for operation).

  • Overhead power lines must be identified; minimum safe distances are 3 m for voltages up to 66 kV, 4.5 m for 132 kV, and 6 m for 275/400 kV, or as specified by the electricity supplier.

  • A daily pre-use inspection and a weekly documented inspection are required; the weekly inspection must be recorded and kept for at least 3 months.

  • Personnel must wear appropriate PPE: hard hat, safety footwear, high-visibility clothing, and fall protection when working at height.

  • Emergency rescue plan must be in place before anyone works at height on the tower; rescue equipment and trained personnel must be available on site.

Quick reference

Tower Assembly, Erection and Dismantling Procedures

  • Only trained and competent personnel may assemble, erect, or dismantle a tower; a supervisor must be appointed and present.

  • Manufacturer's instructions must be followed exactly; no modifications or substitutions of parts are allowed without written approval from the manufacturer.

  • Tower must be built on a firm, level base; base plates and adjustable legs must be fully supported and secured; never use bricks or blocks to level.

  • Stabilisers or guy ropes must be fitted as specified in the manufacturer's manual; they must be anchored to suitable points and tensioned correctly.

  • During assembly, the tower must not exceed a height ratio of 3:1 (height to base width) unless stabilisers are fitted; with stabilisers, the ratio may increase as per manufacturer's instructions.

  • Platforms must be fully decked and fitted with guardrails and toe boards; guardrail height must be between 0.95 m and 1.15 m, with an intermediate rail and toe board at least 150 mm high.

  • Dismantling must follow the reverse of the assembly sequence; never remove stabilisers or ties until the tower is stable.

  • All tools and materials must be tether ed or removed from the platform before moving or dismantling; never throw equipment from height.

Quick reference

Tower Inspection, Maintenance and Defect Reporting

  • Pre-use inspection: check for damaged or missing components, corrosion, cracks, bent tubes, and insecure fittings; confirm all braces and pins are in place.

  • Weekly inspection: a competent person must inspect the tower and record findings; include checking foundation, stabilisers, ties, guardrails, and toe boards.

  • Inspection after any event: tower must be inspected after high winds, accidental impact, or any modification; do not use until cleared.

  • Defects must be reported immediately to the supervisor; any tower with a defect that affects safety must be taken out of service and tagged 'Do Not Use'.

  • Maintenance: only original manufacturer's parts may be used; lubricate adjustable legs and fittings as per manufacturer's schedule; store components to prevent damage.

  • Inspection records must be kept for at least 3 months and made available for review; include date, inspector name, findings, and actions taken.

  • Mobile towers must be inspected before every use and after being moved; check wheels are locked and brakes applied before use.

  • Damaged components must be segregated and clearly labelled; never use damaged parts even if they appear minor.

Quick reference

Operating Procedures and Load/Operational Limits

  • Never exceed the manufacturer's safe working load (SWL) for the platform; typical SWL is 200 kg per platform, but always check the manufacturer's data plate.

  • Loads must be evenly distributed; do not concentrate loads at one end or on one platform level.

  • Maximum platform height depends on tower configuration; never exceed the height specified in the manufacturer's manual for the given base dimensions and stabiliser setup.

  • Mobile towers must not be moved while personnel or materials are on the platform; lower the platform, secure all equipment, and check the route before moving.

  • Wheels must be locked and brakes applied before climbing the tower; never use the tower on sloping ground without additional measures.

  • Access must be via internal ladders or stairs; never climb on the outside of the tower or use the guardrails as a ladder.

  • Do not use the tower as a crane or to support other equipment; no attachments unless approved by the manufacturer.

  • Operatives must maintain three points of contact when climbing; use fall protection if required by site rules.

Quick reference

Emergency Procedures and Incident Response

  • A rescue plan must be in place before work at height begins; it must include methods for rescuing a fallen worker and trained personnel available.

  • If a fall occurs, do not attempt to move the casualty unless there is immediate danger; call emergency services and administer first aid if trained.

  • In case of high winds, stop work, secure the tower, and evacuate the platform; do not attempt to dismantle in high winds.

  • If the tower becomes unstable, evacuate immediately and do not attempt to correct the instability; cordon off the area and seek expert advice.

  • Emergency contact numbers must be displayed on site; ensure all personnel know the emergency procedures and location of first aid kit.

  • Report all incidents, including near misses, to the supervisor and record in the accident book; serious incidents must be reported to the relevant authority (e.g., HSE under RIDDOR).

  • Fire: raise the alarm, evacuate to assembly point, and call fire services; do not use water on electrical fires.

  • After an emergency, the tower must be inspected by a competent person before re-use.

Quick reference

Legislation, Regulations and Personal Responsibilities

  • Health and Safety at Work etc. Act 1974: employers must ensure safe systems of work; employees must take reasonable care of themselves and others.

  • Work at Height Regulations 2005: requires risk assessment, avoidance of work at height where possible, and measures to prevent falls; also requires rescue planning.

  • Provision and Use of Work Equipment Regulations 1998 (PUWER): requires equipment to be suitable, maintained, and inspected; includes mobile towers.

  • Lifting Operations and Lifting Equipment Regulations 1998 (LOLER): applies if the tower is used as lifting equipment; requires thorough examination.

  • Personal Protective Equipment at Work Regulations 1992: PPE must be provided and used; employees must wear and report defects.

  • Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013 (RIDDOR): requires reporting of certain incidents, including falls from height.

  • Employees have a duty to cooperate with employers on health and safety matters and not to interfere with safety devices.

  • All personnel must be competent for the task; training records must be kept and refresher training undertaken as required.