LC Construction Studies · Give each week a clear focus.

8 weeks · About 6 hours per week

Week 1

Construction Technology and Building Elements & Drawing, Graphical Communication and Applied Design Project

  • Redraw a simple two-storey domestic wall/floor junction from memory and label every layer in correct sequence from foundation to roof finish

  • Build a one-page glossary of 40 construction-technology terms (strip foundation, DPC, wall tie, lintel, sleeper wall, party wall) with a one-line definition each

  • Set up a scaled drawing sheet template with title block, north point, scale bar and three line weights, and reproduce one existing detail at 1:5

  • List the six building elements (substructure, external envelope, internal divisions, primary structure, services, finishes) and assign each glossary term to one element

Your checkpoint

A single A3 sheet containing one hand-drafted 1:5 wall/floor detail with every layer labelled plus a 40-term glossary on the reverse

Week 2

Construction Technology and Building Elements & Building Materials and Their Properties

  • Compare timber-frame, cavity-wall masonry and structural insulated panel wall build-ups across six criteria: speed, thermal bridging, weathertightness, cost, site skill and fire performance

  • Produce labelled 1:10 sections through a strip footing, a raft foundation and a suspended timber ground floor

  • Match ten common materials (concrete, mild steel, softwood, hardwood, fired clay brick, aerated concrete block, glass, gypsum plasterboard, OSB, EPDM) to their primary properties and one typical application each

  • Explain how moisture movement, thermal expansion and creep differ between timber, steel and concrete, and state one design consequence of each

Your checkpoint

A comparison matrix of three wall systems across six criteria plus three labelled 1:10 foundation/floor sections

Week 3

Building Materials and Their Properties & Structural Principles and Building Stability

  • Describe the manufacturing route and resulting property differences for at least four masonry units (clay brick, calcium silicate, aerated block, dense concrete block)

  • Calculate dead and imposed loads for a simple one-way floor slab using given unit weights and a stated imposed load, and show the load path to the foundations

  • Sketch and annotate five structural forms (post-and-beam, loadbearing wall, portal frame, truss, cantilever) and state where each resists or transfers load

  • Identify the four stability mechanisms (shear walls, cross-walls, moment connections, diagonal bracing) in a plan drawing and mark where each is needed

Your checkpoint

A worked load-takedown calculation for one floor and roof, one page long, with a supporting load-path sketch

Week 4

Structural Principles and Building Stability & Construction Technology and Building Elements

  • Solve six short structural problems covering bending moment, shear force, deflection limits and slenderness of a masonry wall

  • Draft a 1:20 roof section showing insulation position, ventilation path, vapour control layer and eaves detail for a cold-deck pitched roof

  • Explain why disproportionate collapse provisions matter and list three tying or integrity measures used in low-rise construction

  • Review a set of three of your own drawings and annotate every missing dimension, level or specification note

Your checkpoint

A self-marked 20-question structural-principles test scoring at least 16/20, with corrections written out for every wrong answer

Week 5

Environmental and Energy Considerations, Services and Sustainability & Building Services and Thermal Performance

  • Calculate U-values for a cavity wall and a warm roof from given layer thicknesses and conductivities, and state the effect of a 20 mm insulation increase in each case

  • Explain the difference between airtightness and insulation, and list five common air-leakage paths in a dwelling

  • Describe the operating principle and one control requirement for ventilation (MVHR or background ventilators), space heating, and domestic hot water

  • Compare three renewable options (air-source heat pump, solar thermal, PV) on output profile, roof area needed and typical running cost driver

  • Set out the condensation risk in a wall or roof build-up using the temperature-gradient idea, and state where the vapour control layer belongs

Your checkpoint

A one-page U-value and condensation-risk calculation sheet for two build-ups, with a labelled temperature-gradient sketch for each

Week 6

Drawing, Graphical Communication and Applied Design Project & Environmental and Energy Considerations, Services and Sustainability

  • Produce a full planning-application drawing set for a small extension: site/location plan, floor plan, two elevations and one section, all consistently scaled and titled

  • Write a 300-word design rationale linking your proposal to orientation, daylight, thermal performance and site constraints

  • Apply the passive design hierarchy (fabric first, then services, then renewables) to your own project and justify three decisions in writing

  • Check your drawing set against a self-made 15-point compliance checklist covering dimensions, levels, annotations, scale and title block

Your checkpoint

A complete five-sheet applied design project set with a 300-word design rationale, checked against your 15-point checklist

Week 7

Planning and Site Assessment & Building Services and Thermal Performance & Drawing, Graphical Communication and Applied Design Project

  • Carry out a desk-based site appraisal of a hypothetical plot: ground conditions, access, drainage, orientation, overlooking and services availability, recorded as a scored table

  • Explain how site investigation (trial pits, boreholes, percolation tests) informs foundation choice, and match three ground conditions to suitable foundation types

  • Position and size service runs (soil stack, water main, consumer unit, boiler or heat pump) on your project plan and check for clashes

  • Annotate your project drawings with a services layout and a site-constraint overlay

Your checkpoint

An updated project plan sheet with services layout and site-constraint overlay, plus a scored site-appraisal table of at least eight criteria

Week 8

Construction Technology and Building Elements & Structural Principles and Building Stability & Environmental and Energy Considerations, Services and Sustainability & Building Services and Thermal Performance & Drawing, Graphical Communication and Applied Design Project

  • Complete two full timed mock papers under exam conditions and record the score by domain to expose weak areas

  • Re-teach your three weakest domain areas using your own notes, then re-attempt the missed questions without looking at the answers

  • Condense all eight weeks of notes into a single two-page revision sheet of facts, formulae and detail sketches

  • Rehearse the drawing task once more at exam pace, finishing a labelled detail within the time allowance

Your checkpoint

A domain-by-domain mock score log showing improvement on the second paper, plus a two-page condensed revision sheet

Milestones

Week 2: Can label a wall/floor junction and three foundation types from memory with no reference material, scoring at least 80% on your own recall check

Week 4: Can complete a load takedown and a U-value calculation unaided and score at least 16/20 on the structural self-test

Week 6: A complete, internally consistent drawing set exists with a written rationale; a peer or tutor can follow the proposal without verbal explanation

Week 8: Second mock paper scores at least 10 percentage points above the first, with no domain below 50%