OFTEC Oil Firing (OFT101/105E) · Give each week a clear focus.

8 weeks · About 7 hours per week

Week 1

Oil Storage, Supply and Fuel Properties & Health and Safety, Legislation and Industry Standards

  • Explain how fuel oil grades (kerosene, 28-second, 35-second gas oil) differ in viscosity, calorific value, sulphur and waxing behaviour, and state where each is typically used

  • Describe the legal and practical requirements for domestic oil storage: bunding, tank siting, fire separation distances, and secondary containment for tanks over 200 litres

  • Identify the supply-chain components (tank, filter, fire valve, isolating valve, de-aeration device, pipework) and state the purpose of each

  • Calculate the usable capacity and bund capacity needed for a given domestic tank installation scenario

Your checkpoint

A one-page annotated oil supply schematic plus a completed storage-compliance checklist covering 8 siting and bunding criteria

Week 2

Oil Fired Appliances: Types, Construction and Operation & Combustion, Burner Components and Settings

  • Distinguish pressure-jet, vaporising and rotary-cup burner types by construction and operating principle, and match each to suitable appliance types

  • Trace the sequence of a pressure-jet burner through pre-purge, ignition, flame establishment and lockout, naming each component involved

  • Explain the roles of the oil pump, nozzle, electrodes, photocell, solenoid valve and control box in the combustion process

  • Interpret nozzle flow-rate and spray-angle markings and select a nozzle for a stated appliance output using a nozzle chart

Your checkpoint

A labelled burner component diagram with a written start-up sequence of at least 8 steps, plus three worked nozzle-selection calculations

Week 3

Combustion, Burner Components and Settings & Oil Fired Appliances: Types, Construction and Operation

  • Set pump pressure, electrode gap and position, and air settings to manufacturer specification on a burner, and state the effect of each adjustment on combustion

  • Interpret flue gas readings (CO2, O2, CO, smoke number, flue temperature) and diagnose rich, lean and incomplete combustion from them

  • Describe the construction and operation of condensing and non-condensing oil boilers, including heat exchanger materials and condensate handling

  • Explain why correct combustion settings matter for efficiency, safety and compliance with emissions expectations

Your checkpoint

A combustion-diagnosis table matching 6 sets of flue readings to likely faults and the corrective adjustment for each

Week 4

Installation of Oil Fired Appliances and Systems & Flues, Ventilation and Combustion Air

  • Apply siting and separation requirements for oil-fired appliances, including distances from combustible materials and protected openings

  • Size and specify combustion and ventilation air openings for a given appliance location, distinguishing ventilated and unventilated compartments

  • Describe flue options (conventional, balanced, room-sealed, condensing) and state terminal siting and clearance requirements for each

  • Explain the requirements for fire valves, remote emergency stops and their correct positioning in the oil line

Your checkpoint

A full installation plan for a fictional domestic boiler: appliance siting, oil line layout with fire valve position, flue route and terminal clearances, and ventilation opening sizes with calculations

Week 5

Health and Safety, Legislation and Industry Standards & Electrical Controls, Safety Devices and Wiring

  • List the key legal duties and industry standards relevant to oil installation work, including notification, competence and records requirements

  • Identify the electrical safety requirements for oil-fired appliances: isolation, earthing, and separation of control and mains circuits

  • Trace a typical control circuit from programmer through thermostat, limit stat and burner control box, and explain the lockout and safety shutdown functions

  • Explain the purpose and testing of the fire valve, overheat thermostat, and flame-failure device in the safety chain

Your checkpoint

A wiring and safety-device schematic for a typical oil boiler with a written explanation of each safety shutdown path

Week 6

Commissioning, Testing and Handover & Servicing, Fault Diagnosis and Repair

  • Carry out a commissioning sequence in the correct order: pre-checks, oil line pressure test, combustion analysis, and safety-device proving

  • Record commissioning results on a handover document, including flue readings, oil pressure, nozzle fitted and appliance output

  • Plan a routine service: list tasks, required tools and the checks that must be completed before and after cleaning

  • Diagnose common faults (lockout, poor flame, pump noise, air in line, water in tank) from symptoms and describe the repair path for each

Your checkpoint

A completed mock commissioning and handover record for a domestic boiler, plus a fault-finding flowchart covering 8 symptoms and their causes

Week 7

Servicing, Fault Diagnosis and Repair & Oil Storage, Supply and Fuel Properties

  • Diagnose oil supply faults including blocked filters, failed fire valves, air ingress and tank contamination, and state the corrective action for each

  • Explain the causes and prevention of oil line air locks, and describe how de-aeration devices and correct pipe sizing reduce them

  • Evaluate a tank installation for contamination risk, water ingress and sludge, and recommend remedial measures

  • Describe the procedure for safely isolating, draining and recommissioning an oil supply system during repair

Your checkpoint

A written fault-report for three realistic supply-system scenarios, each with diagnosis, evidence, repair steps and post-repair checks

Week 8

Health and Safety, Legislation and Industry Standards & Commissioning, Testing and Handover & Servicing, Fault Diagnosis and Repair

  • Consolidate weak areas identified from earlier weeks by re-testing each domain with timed practice questions

  • Explain, without notes, the full life cycle of an oil installation from survey through commissioning to service and handover

  • State the key legal, safety and combustion facts in a condensed revision sheet you can recall under exam conditions

  • Complete a full timed mock exam and review every incorrect answer to identify the underlying knowledge gap

Your checkpoint

A timed mock exam result with a written review of every wrong answer and a personal revision sheet of no more than two pages

Milestones

Week 2: Can explain the pressure-jet burner start-up sequence and select a nozzle from a chart without reference material

Week 4: Can produce a compliant installation plan covering siting, oil line, flue and ventilation with correct calculations

Week 6: Can complete a commissioning record and diagnose at least 6 common faults from symptoms alone

Week 8: Achieve a pass mark on the timed mock exam and have a written remediation note for every incorrect answer