AIC AO flashcards
AIC AO · Build recall with a focused review session.
33 cards. Read the term and the definition here. The deck at the top of this page is optional.
- Active listening
- A communication technique in which the receiver attends fully, paraphrases the sender's message, reflects feelings, and asks clarifying questions to confirm understanding before responding.
- Communication channel richness
- The capacity of a medium to convey meaning: face-to-face is richest because it carries immediate feedback and nonverbal cues; written impersonal media are leanest.
- Communication plan
- A document identifying stakeholders, their information needs, message format, frequency, responsible sender, and escalation path for project communications.
- Thomas-Kilmann conflict modes
- Five conflict-handling approaches: competing, collaborating, compromising, avoiding, and accommodating. Collaborating seeks a win-win outcome and suits important issues with adequate time.
- Stress and strain
- Stress is force per unit area (σ = P/A); strain is change in length over original length (ε = ΔL/L). Their ratio in the elastic range is the modulus of elasticity.
- Water-cement ratio
- The mass of water divided by mass of cement in a concrete mix. Lower ratios increase strength and reduce permeability; higher ratios improve workability but weaken concrete.
- Optimum moisture content
- The moisture percentage at which a soil reaches maximum dry density under a given compaction effort, determined by a Proctor test.
- Factor of safety
- The ratio of a structure's ultimate or yield capacity to the allowable or design load, accounting for uncertainty in loads, materials, and analysis.
- Projectized organization
- An organizational structure in which teams report directly to the project manager, who holds high authority over resources and priorities; staff are often co-located.
- Triple constraint
- The interdependent project constraints of scope, schedule, and cost, with quality affected by all three; changing one typically requires adjusting another.
- Herzberg two-factor theory
- Hygiene factors such as pay and working conditions prevent dissatisfaction but do not motivate; motivators such as achievement and recognition create satisfaction and drive performance.
- Stakeholder power-interest grid
- A classification mapping stakeholders by influence and interest; high power with high interest requires close management, while low power with low interest needs only monitoring.
- Level of Development (LOD)
- A BIM classification from 100 to 500 describing how reliable and complete a model element is, from conceptual through as-built, for use by project teams.
- Clash detection
- A modeling process that compares building systems across disciplines, such as structure and mechanical piping, to find and resolve spatial conflicts before construction.
- Cut and fill balance
- An earthwork approach that matches excavated cut volume to required fill volume on site, minimizing haul distance and off-site disposal or import costs.
- Slump test
- A field test measuring fresh concrete workability by the vertical settlement of a standard cone; it indicates consistency but not directly compressive strength.
- Bid bond
- A surety instrument guaranteeing that a selected bidder will enter the contract and furnish required bonds; failure allows the owner to claim the difference.
- Quantity takeoff
- A measured inventory of materials and work items derived from drawings and specifications, forming the basis for pricing in an estimate.
- Addendum
- A written modification to bidding documents issued before bid opening; bidders must acknowledge material addenda or risk having their bid rejected.
- Unbalanced bid
- A bid that raises prices on early or likely-increased items and lowers others, increasing cash flow or profit; it may be rejected as nonresponsive.
- Cost Performance Index
- Earned value divided by actual cost (CPI = EV/AC). A value below 1.0 means work is costing more than planned per unit of earned value.
- Estimate at Completion
- A forecast of total project cost. The common formula EAC = BAC/CPI assumes current cost performance continues; EAC = AC + (BAC − EV) assumes remaining work proceeds at budget.
- Management reserve
- A contingency fund held outside the cost baseline for unknown-unknown risks; it requires management approval and is not part of the project budget baseline.
- Life-cycle cost
- The total cost of a facility over its full life, including acquisition, operation, maintenance, and disposal, used to compare design alternatives.
- Total float
- The amount of time an activity can be delayed without delaying project completion, calculated as late start minus early start or late finish minus early finish.
- Critical path
- The longest-duration sequence of dependent activities through a network; it determines project duration and has zero total float.
- PERT expected duration
- A weighted three-point estimate: (Optimistic + 4×Most Likely + Pessimistic)/6, with variance equal to ((Pessimistic − Optimistic)/6) squared.
- Resource leveling
- A scheduling technique that adjusts activity timing to resolve resource peaks or shortages; it may extend project duration and can change the critical path.
- Hierarchy of controls
- A safety ranking from most to least effective: elimination, substitution, engineering controls, administrative controls, then personal protective equipment as the last defense.
- Excavation protective system
- A shoring, shielding, sloping, or benching system required for trenches 5 feet or deeper; spoil and equipment must be kept at least 2 feet from the edge.
- Job Hazard Analysis
- A pre-task process that breaks work into steps, identifies hazards at each step, and defines controls and required PPE before work begins.
- Change order
- A written, signed modification to the contract adjusting scope, price, or time; a construction change directive orders the work before price is fully agreed.
- Retainage
- A percentage of each progress payment withheld by the owner until substantial or final completion to protect against incomplete or defective work.